Area | Country | Project | Customer | Product | Capacity | Qty | Year |
---|---|---|---|---|---|---|---|
PT PLN BATAM |
1 |
BUMN |
DISTRIBUTION LINE PENGADAAN TRAFO DISTRIBUSI 20 KV |
2017 |
TRAFO 400 KVA |
36 |
|
PT. PLN (PERSERO) WILAYAH TERSEBAR |
2 |
BUMN |
DISTRIBUTION LINE PENGADAAN TRANSFORMATOR DISTRIBUSI TAHUN 2017 |
2018 |
TRAFO 25 KVA |
274 |
|
PT. PLN (PERSERO) WILAYAH TERSEBAR |
3 |
BUMN |
DISTRIBUTION LINE PENGADAAN TRANSFORMATOR DISTRIBUSI TAHUN 2017 |
2018 |
TRAFO 100 KVA |
1363 |
|
PT. PLN (PERSERO) WILAYAH TERSEBAR |
4 |
BUMN |
DISTRIBUTION LINE PENGADAAN TRANSFORMATOR DISTRIBUSI TAHUN 2017 |
2018 |
TRAFO 250 KVA |
199 |
|
PT. PLN (PERSERO) WILAYAH TERSEBAR |
5 |
BUMN |
DISTRIBUTION LINE PENGADAAN TRANSFORMATOR DISTRIBUSI TAHUN 2017 |
2018 |
TRAFO 400 KVA |
225 |
|
PT. PLN (PERSERO) WILAYAH TERSEBAR |
6 |
BUMN |
DISTRIBUTION LINE PENGADAAN TRANSFORMATOR DISTRIBUSI TAHUN 2018 |
2018 |
TRAFO 160 KVA |
469 |
|
PT. PLN (PERSERO) WILAYAH TERSEBAR |
7 |
BUMN |
DISTRIBUTION LINE PENGADAAN TRANSFORMATOR DISTRIBUSI TAHUN 2018 |
2018 |
TRAFO 250 KVA |
168 |
|
PT. PLN (PERSERO) WILAYAH TERSEBAR |
8 |
BUMN |
DISTRIBUTION LINE PENGADAAN TRANSFORMATOR DISTRIBUSI TAHUN 2018 |
2018 |
TRAFO 400 KVA |
53 |
|
PT. PROTON NUSANTARA BERKAH |
9 |
- |
- |
2018 |
TRAFO 500 KVA |
1 |
|
PT. SENTRA KARYA CAHAYA RAYA |
10 |
2018 |
TRAFO 50 KVA |
2 |
|||
PT. SINAR KARYA MONICA |
11 |
2018 |
TRAFO 315 KVA |
1 |
|||
PT. SINAR KARYA MONICA |
12 |
2018 |
TRAFO 630 KVA |
3 |
|||
PT. SINAR KARYA MONICA |
13 |
2018 |
TRAFO 1.250 KVA |
1 |
|||
PT. SINAR ANISA MANDIRI |
14 |
2018 |
TRAFO 1.000 KVA |
2 |
|||
PT. RAJAWALI PERKASA RAYA |
15 |
2018 |
TRAFO 100 KVA |
8 |
|||
PT. BUNTU RANNU |
16 |
2018 |
TRAFO 250 KVA |
4 |
|||
PT. GLOBAL ELEKTRIK SENTOSA |
17 |
2018 |
TRAFO 630 KVA |
1 |
|||
PT. FIRMA JAYA MURNI |
18 |
2018 |
TRAFO 1.000 KVA |
1 |
|||
PT. ATEKINDO |
19 |
COMMERCIAL |
CIBITUNG STASIUN |
2018 |
TRAFO 250 KVA |
1 |
|
PT. PLN (PERSERO) WILAYAH TERSEBAR |
20 |
BUMN |
DISTRIBUTION LINE PENGADAAN TRANSFORMATOR DISTRIBUSI TAHUN 2019 |
2019 |
TRAFO 250 KVA |
1301 |
|
PT. PLN (PERSERO) WILAYAH TERSEBAR |
21 |
BUMN |
DISTRIBUTION LINE PENGADAAN TRANSFORMATOR DISTRIBUSI TAHUN 2019 |
2019 |
TRAFO 400 KVA ID |
524 |
|
PT. PLN (PERSERO) WILAYAH TERSEBAR |
22 |
BUMN |
DISTRIBUTION LINE PENGADAAN TRANSFORMATOR DISTRIBUSI TAHUN 2019 |
2019 |
TRAFO 100 KVA |
2270 |
|
PT. PLN (PERSERO) WILAYAH TERSEBAR |
23 |
BUMN |
DISTRIBUTION LINE PENGADAAN TRANSFORMATOR DISTRIBUSI TAHUN 2019 |
2019 |
TRAFO 160 KVA |
1609 |
|
PT. PLN (PERSERO) WILAYAH TERSEBAR |
24 |
BUMN |
DISTRIBUTION LINE PENGADAAN TRANSFORMATOR DISTRIBUSI TAHUN 2019 |
2019 |
TRAFO 25 KVA |
251 |
|
PT. WAHANA ACEH POWER |
25 |
2019 |
TRAFO 800 KVA |
1 |
|||
PT. MARANNU MEGAH ELEKTRIK |
26 |
2019 |
TRAFO 1.000 KVA |
1 |
|||
PT. BUMI JAYA |
27 |
2019 |
TRAFO DISTRIBUSI 3P, 20KV/400V, 2500KVA, Dyn5, CU-CU |
1 |
|||
PT. ADI PUTRA |
28 |
2019 |
TRAFO 400 KVA |
1 |
|||
PT. GLOBAL ELEKTRIK SENTOSA |
29 |
2019 |
TRAFO 630 KVA |
1 |
|||
PT. FAMATEX |
30 |
2019 |
TRAFO 1.600 KVA |
1 |
|||
PT. SOLAS LANGGENG SEJAHTERA |
31 |
2019 |
TRAFO 1.250 KVA |
1 |
|||
PT. FAMATEX |
32 |
2019 |
TRAFO 630 KVA |
1 |
|||
PT. KARYA LOGAM AGUNG |
33 |
INDUSTRY |
KOMP. INDUSTRI MODERN CIKANDE SERANG |
2019 |
TRAFO 630 KVA |
1 |
|
PT. SINAR ANISA MANDIRI |
34 |
2019 |
TRAFO 100 KVA |
1 |
|||
PT. SINAR ANISA MANDIRI |
35 |
2019 |
TRAFO 160 KVA |
1 |
|||
PT. IRIANA KARYA UTAMA |
36 |
2019 |
TRAFO 400 KVA |
1 |
|||
PT. BATRAJA WIRENINDO UTAMA |
37 |
2019 |
TRAFO 1.600 KVA |
1 |
|||
PT. PUTRA DUA PERKASA |
38 |
2019 |
TRAFO 1.000 KVA |
2 |
|||
PT. SINAR ANISA MANDIRI |
39 |
2019 |
TRAFO 5.000 KVA |
1 |
|||
PT. UNGGUL CIPTA INDRAMEGAH |
40 |
2019 |
TRAFO 400 KVA |
1 |
|||
PT. SINAR ANISA MANDIRI |
41 |
2019 |
TRAFO 400 KVA |
1 |
|||
PT. GLOBAL ELEKTRIK SENTOSA |
42 |
2019 |
TRAFO 630 KVA |
1 |
|||
PT. AZKA ALGHAZALI LAMPUNG |
43 |
2019 |
TRAFO 160 KVA |
4 |
|||
PT. ATEKINDO |
44 |
2019 |
TRAFO 250 KVA |
1 |
|||
PT. SINAR ANISA MANDIRI |
45 |
2019 |
TRAFO 4.000 KVA |
4 |
|||
PT. KARIANGAU POWER |
46 |
2019 |
TRAFO 50 KVA |
2 |
|||
PT. KALLA ELECTRIC |
47 |
2019 |
TRAFO STEP DOWN 1.000 KVA |
1 |
|||
PT. GLOBAL ELEKTRIK SENTOSA |
48 |
2020 |
TRAFO 630 KVA |
1 |
|||
PT. CARAKA ANUGRAH SANTOSO |
49 |
2020 |
TRAFO HEAVY DUTY 2.000 KVA |
1 |
|||
PT. CARAKA ANUGRAH SANTOSO |
50 |
2020 |
TRAFO HEAVY DUTY 2.500 KVA |
1 |
|||
PT. ATEKINDO |
51 |
2020 |
TRAFO 250 KVA |
2 |
|||
PT. BORNEO MAJU JAYA |
52 |
MINING |
TAMBANG BATUBARA ARUTMIN |
2020 |
TRAFO 1.000 KVA |
1 |
|
PT. BORNEO MAJU JAYA |
53 |
MINING |
TAMBANG BATUBARA ARUTMIN |
2020 |
TRAFO 1.600 KVA |
1 |
|
PT. CILEGON FABRICATOR |
54 |
2020 |
TRAFO 1.500 KVA |
1 |
|||
PT. HYUNDAI ENGINEERING & CONSTRUCTION |
55 |
2020 |
TRAFO 3.500 KVA |
1 |
|||
PT. PUTRA DUA PERKASA |
56 |
2020 |
TRAFO 400 KVA |
2 |
|||
PT. MUTIARA AGRO SEJAHTERA |
57 |
2020 |
TRAFO 630 KVA |
1 |
|||
CV SANTIKA JAYA ABADI |
58 |
2020 |
TRAFO 2.500 KVA |
1 |
|||
PT. BORNEO MAJU JAYA |
59 |
MINING |
TAMBANG BATUBARA ARUTMIN |
2020 |
TRAFO 1.250 KVA |
1 |
|
PT. KARIANGAU POWER |
60 |
INDUSTRY |
KAWASAN INDUSTRI KARIANGAU |
2020 |
TRAFO 200 KVA |
2 |
|
PT. TRIMULYA DAYA UTAMA |
61 |
2020 |
TRAFO 400 KVA |
1 |
|||
PT. BORNEO MAJU JAYA |
62 |
MINING |
TAMBANG BATUBARA ARUTMIN |
2020 |
TRAFO 2.000 KVA |
2 |
|
PT. JAYA JUMLI PERKASA |
63 |
2020 |
TRAFO 630 KVA |
1 |
|||
PT. SINAR ANISA MANDIRI |
64 |
2020 |
TRAFO 160 KVA |
1 |
|||
PT. SINAR ANISA MANDIRI |
65 |
2020 |
TRAFO 160 KVA |
1 |
|||
BAPAK DONNY |
66 |
2020 |
TRAFO 630 KVA |
1 |
|||
PT. GLOBAL ELEKTRIK SENTOSA |
67 |
2020 |
TRAFO 315 KVA |
1 |
|||
PT. SINAR ANISA MANDIRI |
68 |
2020 |
TRAFO 250 KVA |
1 |
|||
BAPAK PAMUDJI RAHARDJO |
69 |
2020 |
TRAFO 315 KVA |
1 |
|||
PT. MANORIAN ENGINEERING PRAKARSA |
70 |
2020 |
TRAFO 4.000 KVA |
2 |
|||
PT. SUN KACA INDONESIA |
71 |
2020 |
TRAFO 1.250 KVA |
1 |
|||
PT. SINAR ANISA MANDIRI |
72 |
2020 |
TRAFO 250 KVA |
2 |
|||
PT. ANUGERAH FUJI UTAMA |
73 |
2020 |
TRAFO 160 KVA |
3 |
|||
PT. SIANTAR TARA SEJATI |
74 |
2020 |
TRAFO 1.600 KVA |
1 |
|||
PT. SINAR ANISA MANDIRI |
75 |
2020 |
TRAFO 160 KVA |
1 |
|||
PT. SINAR ANISA MANDIRI |
76 |
2020 |
TRAFO 160 KVA |
1 |
|||
PT. BORNEO MAJU JAYA |
77 |
MINING |
TAMBANG BATUBARA ARUTMIN |
2020 |
TRAFO 3.500 KVA |
2 |
|
PT. SINAR ANISA MANDIRI |
78 |
2020 |
TRAFO 250 KVA |
6 |
|||
PT. KRAKATAU WIREMESH |
79 |
INDUSTRY |
KAWASAN INDUSTRI BONEN |
2020 |
TRAFO 1.000 KVA |
1 |
|
PT. SINAR ANISA MANDIRI |
80 |
2020 |
TRAFO 100 KVA |
1 |
|||
PT. SINAR ANISA MANDIRI |
81 |
2020 |
TRAFO 160 KVA |
2 |
|||
CV. ADHI JAYA UTAMA |
82 |
2020 |
TRAFO 50 KVA |
1 |
|||
CV. ADHI JAYA UTAMA |
83 |
2020 |
TRAFO 160 KVA |
2 |
|||
CV. ADHI JAYA UTAMA |
84 |
2020 |
TRAFO 250 KVA |
1 |
|||
CV. ADHI JAYA UTAMA |
85 |
2020 |
TRAFO 400 KVA |
1 |
|||
PT. TRIMULYA DAYA UTAMA |
86 |
2020 |
TRAFO 200 KVA |
1 |
|||
PT. BUMILOKA TEGAR PERKASA |
87 |
2020 |
TRAFO 2.000 KVA |
2 |
|||
PT. SINAR ANISA MANDIRI |
88 |
2020 |
TRAFO 160 KVA |
1 |
|||
PT. BORNEO MAJU JAYA |
89 |
MINING |
TAMBANG BATUBARA ARUTMIN |
2020 |
TRAFO 400 KVA |
1 |
|
PT. SINAR ANISA MANDIRI |
90 |
2020 |
TRAFO 160 KVA |
1 |
|||
PT. GALLEON CAHAYA INVESTAMA |
91 |
2020 |
TRAFO 200 KVA |
1 |
|||
PT. SINAR ANISA MANDIRI |
92 |
2020 |
TRAFO 160 KVA |
1 |
|||
PT. SINAR ANISA MANDIRI |
93 |
2020 |
TRAFO 100 KVA |
1 |
|||
PT. BUKILLA MANDIRI |
94 |
2020 |
TRAFO 100 KVA |
1 |
|||
PT. ATEKINDO |
95 |
2020 |
TRAFO 100 KVA |
4 |
|||
BAPAK FEBRIANSYAH |
96 |
2020 |
TRAFO 25 KVA |
1 |
|||
PT. SINAR ANISA MANDIRI |
97 |
2021 |
TRAFO 160 KVA |
1 |
|||
BAPAK AKHMAD ARIFIN |
98 |
2021 |
TRAFO 630 KVA |
1 |
|||
PT. BORNEO MAJU JAYA |
99 |
MINING |
TAMBANG BATUBARA ARUTMIN |
2021 |
TRAFO 800 KVA |
1 |
|
PT. ALBASI PRIANGAN LESTARI |
100 |
2021 |
TRAFO 1.000 KVA |
1 |
|||
PT. INDONESIA PARADISE ISLAND |
101 |
2021 |
TRAFO 2.000 KVA |
1 |
|||
PT. SINAR ANISA MANDIRI |
102 |
2021 |
TRAFO 250 KVA |
1 |
|||
PT. PUTRA DUA PERKASA |
103 |
2021 |
TRAFO 400 KVA |
4 |
|||
PT. SINAR ANISA MANDIRI |
104 |
2021 |
TRAFO 160 KVA |
1 |
|||
ALLIANCE TECHNIC ENGINEER |
105 |
2021 |
TRAFO 1.000 KVA |
1 |
|||
BAPAK PURYONO, ST |
106 |
2021 |
TRAFO 160 KVA |
1 |
|||
PT. BORNEO MAJU JAYA |
107 |
MINING |
TAMBANG BATUBARA ARUTMIN |
2021 |
TRAFO 10 KVA |
2 |
|
PT. ATEKINDO |
108 |
2021 |
TRAFO 1.000 KVA |
1 |
|||
BAPAK AHMAD ANWAR |
109 |
2021 |
TRAFO 50 KVA |
1 |
|||
ALLIANCE TECHNIC ENGINEER |
110 |
2021 |
TRAFO 1.600 KVA |
1 |
|||
PT. BORNEO MAJU JAYA |
111 |
MINING |
TAMBANG BATUBARA ARUTMIN |
2021 |
TRAFO 200 KVA |
3 |
|
PT. BORNEO MAJU JAYA |
112 |
MINING |
TAMBANG BATUBARA ARUTMIN |
2021 |
TRAFO 630 KVA |
1 |
|
PT. GALLEON CAHAYA INVESTAMA |
113 |
2021 |
TRAFO 160 KVA |
1 |
|||
PT. GALLEON CAHAYA INVESTAMA |
114 |
2021 |
TRAFO 100 KVA |
2 |
|||
PT. SINAR ANISA MANDIRI |
115 |
2021 |
TRAFO 160 KVA |
1 |
|||
CV. SANTIKA JAYA ABADI |
116 |
2021 |
TRAFO 2.000 KVA |
1 |
|||
PT. SINAR ANISA MANDIRI |
117 |
2021 |
TRAFO 250 KVA |
2 |
|||
PT. SINAR ANISA MANDIRI |
118 |
2021 |
TRAFO 160 KVA |
2 |
|||
PT. HIDUP BARU ELECTRIC |
119 |
2021 |
TRAFO 160 KVA |
1 |
|||
PT. WIJAYA KARYA BANGUNAN GEDUNG TBK |
120 |
COMMERCIAL BUILDING |
PENGEMBANGAN PLBN JAGOI BABANG, KALBAR |
2021 |
TRAFO 300 KVA |
2 |
|
PT. SINTA AQUA CULTURE |
121 |
2021 |
TRAFO 1.250 KVA |
1 |
|||
PT. BORNEO MAJU JAYA |
122 |
MINING |
TAMBANG BATUBARA ARUTMIN |
2021 |
TRAFO 50 KVA |
1 |
|
PT. BORNEO MAJU JAYA |
123 |
MINING |
TAMBANG BATUBARA ARUTMIN |
2021 |
TRAFO 50 KVA |
1 |
|
PT. SERAMBI GAYO SENTOSA |
124 |
2021 |
TRAFO 40 KVA |
1 |
|||
PT. BORNEO MAJU JAYA |
125 |
MINING |
TAMBANG BATUBARA ARUTMIN |
2021 |
TRAFO 50 KVA |
1 |
|
PT. MITRA KARYA MANDIRI TANGGUH |
126 |
2021 |
TRAFO 250 KVA |
4 |
|||
PT. MITRA KARYA MANDIRI TANGGUH |
127 |
2021 |
TRAFO 160 KVA |
1 |
|||
PT. BUKILLA MANDIRI |
128 |
2021 |
TRAFO 160 KVA |
1 |
|||
PT. BORNEO MAJU JAYA |
129 |
MINING |
TAMBANG BATUBARA ARUTMIN |
2021 |
TRAFO 50 KVA |
2 |
|
PT. BUMILOKA TEGAR PERKASA |
130 |
2021 |
TRAFO 100 KVA |
1 |
|||
PT. SINAR ANISA MANDIRI |
131 |
2021 |
TRAFO 100 KVA |
1 |
|||
PT. SINAR ANISA MANDIRI |
132 |
2021 |
TRAFO 100 KVA |
1 |
|||
PT. MITRA KARYA MANDIRI TANGGUH |
133 |
2021 |
TRAFO 250 KVA |
1 |
|||
PT. GALLEON CAHAYA INVESTAMA |
134 |
2021 |
TRAFO 400 KVA |
1 |
|||
PT. BINA TEKNIK CIPTAMANDIRI |
135 |
2021 |
TRAFO 200 KVA |
1 |
|||
PT. SINAR ANISA MANDIRI |
136 |
2021 |
TRAFO 160 KVA |
1 |
|||
CV. SEJATI MARINE PERKASA |
137 |
2021 |
TRAFO 1.000 KVA |
1 |
|||
PT. BORNEO MAJU JAYA |
138 |
MINING |
TAMBANG BATUBARA ARUTMIN |
2021 |
TRAFO 500 KVA |
2 |
|
PT. BORNEO MAJU JAYA |
139 |
MINING |
TAMBANG BATUBARA ARUTMIN |
2021 |
TRAFO 1.000 KVA |
1 |
|
PT. MANDIRI REKA ABADI |
140 |
2021 |
TRAFO 100 KVA |
1 |
|||
PT. YUDHA DAYA ELEKTRIK MANDIRI |
141 |
2021 |
TRAFO 25 KVA |
1 |
|||
TOMTOMO TANGESTU, HO |
142 |
2021 |
TRAFO 100 KVA |
1 |
|||
PT. BORNEO MAJU JAYA |
143 |
MINING |
TAMBANG BATUBARA ARUTMIN |
2021 |
TRAFO STEP DOWN 500 KVA |
1 |
|
PT. BORNEO MAJU JAYA |
144 |
MINING |
TAMBANG BATUBARA ARUTMIN |
2021 |
TRAFO STEP UP 500 KVA |
1 |
|
PT. WIJAYA KARYA ANUGRAH |
145 |
2021 |
TRAFO 25 KVA |
3 |
|||
PT. PANGKATAN INDONESIA |
146 |
2021 |
TRAFO STEP UP 250 KVA |
1 |
|||
PT. PANGKATAN INDONESIA |
147 |
2021 |
TRAFO STEP DOWN 250 KVA |
1 |
|||
CV. INTAN MULIA |
148 |
2021 |
TRAFO 630 KVA SPLN 2007 |
1 |
|||
PT ANEKA BANGUN SARANA |
149 |
2021 |
TRAFO 1.250 KVA |
1 |
|||
PT. MANORIAN ENGINEERING PRAKARSA |
150 |
COMMERCIAL BUILDING |
HOSPITAL PROYEK RS. ISLAM AISYAH BOGOR |
2021 |
TRAFO 630 KVA |
1 |
|
PT. SINAR ANISA MANDIRI |
151 |
COMMERCIAL BUILDING |
PERUMAHAN MUTIARA SAMPURNA |
2021 |
TRAFO 250 KVA |
1 |
|
PT. SINAR ANISA MANDIRI |
152 |
COMMERCIAL BUILDING |
PERUMAHAN GRAHA CIPTA |
2021 |
TRAFO 250 KVA |
1 |
|
PT. ATEKINDO |
153 |
2021 |
TRAFO 100 KVA |
1 |
|||
PT. MULTISUKSES WAHANA KARYA |
154 |
2021 |
TRAFO 1.250 KVA |
1 |
|||
CV. VENUS INTI PERKASA |
155 |
2021 |
TRAFO 1.600 KVA |
1 |
|||
PT. NUSA INTI CEMERLANG |
156 |
2021 |
TRAFO 1.000 KVA |
1 |
|||
PT. USAHA ERA ABADI MANDIRI |
157 |
2021 |
TRAFO 630 KVA |
1 |
|||
PT. MANORIAN ENGINEERING PRAKARSA |
158 |
2021 |
TRAFO 630 KVA |
1 |
|||
PT CAHAYA PRINASMANDIRI |
159 |
2021 |
TRAFO 100 KVA |
1 |
|||
PT. MANORIAN ENGINEERING PRAKARSA |
160 |
2021 |
TRAFO 400 KVA |
1 |
|||
PT. MANORIAN ENGINEERING PRAKARSA |
161 |
2021 |
TRAFO 630 KVA |
1 |
|||
PT. MANORIAN ENGINEERING PRAKARSA |
162 |
INDUSTRY |
PABRIK SUSU PETERNAKAN SAPI REFFLES PACIFIC HARVEST |
2021 |
TRAFO 1.000 KVA |
1 |
|
BAPAK MARDI |
163 |
COMMERCIAL |
SIRKUIT MANDALIKA |
2021 |
TRAFO 630 KVA |
1 |
|
PT. SUMATERA KALIMANTAN JAYA |
164 |
2021 |
TRAFO 3.000 KVA |
1 |
|||
PT. HIDUP BARU ELECTRIC |
165 |
2021 |
TRAFO 25 KVA |
1 |
|||
PT. SENTRA KARYA CAHAYA RAYA |
166 |
2021 |
TRAFO 100 KVA |
2 |
|||
PT. GARAYA MANDIRI SENTOSA |
167 |
2021 |
TRAFO 630 KVA |
1 |
|||
PT. INDOHEAT METAL INTI |
168 |
2021 |
TRAFO 2.500 KVA |
1 |
|||
PT. GALLEON CAHAYA INVESTAMA |
169 |
2021 |
TRAFO 400 KVA |
1 |
|||
PT. PLN (PERSERO) WILAYAH TERSEBAR |
170 |
BUMN |
DISTRIBUTION LINE PENGADAAN TRANSFORMATOR DISTRIBUSI TAHUN 2022 |
2022 |
TRAFO 50 KVA |
1276 |
|
PT. PLN (PERSERO) WILAYAH TERSEBAR |
171 |
BUMN |
DISTRIBUTION LINE PENGADAAN TRANSFORMATOR DISTRIBUSI TAHUN 2022 |
2022 |
TRAFO 100 KVA |
2001 |
|
PT. PLN (PERSERO) WILAYAH TERSEBAR |
172 |
BUMN |
DISTRIBUTION LINE PENGADAAN TRANSFORMATOR DISTRIBUSI TAHUN 2022 |
2022 |
TRAFO 160 KVA |
254 |
|
PT. PLN (PERSERO) WILAYAH TERSEBAR |
173 |
BUMN |
DISTRIBUTION LINE PENGADAAN TRANSFORMATOR DISTRIBUSI TAHUN 2022 |
2022 |
TRAFO 250 KVA |
898 |
|
PT. PLN (PERSERO) WILAYAH TERSEBAR |
174 |
BUMN |
DISTRIBUTION LINE PENGADAAN TRANSFORMATOR DISTRIBUSI TAHUN 2022 |
2022 |
TRAFO 160 KVA |
335 |
|
PT. PLN (PERSERO) WILAYAH TERSEBAR |
175 |
BUMN |
DISTRIBUTION LINE PENGADAAN TRANSFORMATOR DISTRIBUSI TAHUN 2023 |
2023 |
TRAFO CSP 50 KVA Iio |
250 |
|
PT. PLN (PERSERO) WILAYAH TERSEBAR |
176 |
BUMN |
DISTRIBUTION LINE PENGADAAN TRANSFORMATOR DISTRIBUSI TAHUN 2023 |
2023 |
TRAFO 50 KVA |
2201 |
|
PT. PLN (PERSERO) WILAYAH TERSEBAR |
177 |
BUMN |
DISTRIBUTION LINE PENGADAAN TRANSFORMATOR DISTRIBUSI TAHUN 2023 |
2023 |
TRAFO 100 KVA |
2647 |
|
PT. PLN (PERSERO) WILAYAH TERSEBAR |
178 |
BUMN |
DISTRIBUTION LINE PENGADAAN TRANSFORMATOR DISTRIBUSI TAHUN 2023 |
2023 |
TRAFO 160 KVA |
404 |
|
PT. PLN (PERSERO) WILAYAH TERSEBAR |
179 |
BUMN |
DISTRIBUTION LINE PENGADAAN TRANSFORMATOR DISTRIBUSI TAHUN 2023 |
2023 |
TRAFO 400 KVA OD |
87 |
|
PT. PLN (PERSERO) WILAYAH TERSEBAR |
180 |
BUMN |
DISTRIBUTION LINE PENGADAAN TRANSFORMATOR DISTRIBUSI TAHUN 2023 |
2023 |
TRAFO 400 KVA ID |
201 |
|
PT. PLN (PERSERO) WILAYAH TERSEBAR |
181 |
BUMN |
DISTRIBUTION LINE PENGADAAN TRANSFORMATOR DISTRIBUSI TAHUN 2023 |
2023 |
TRAFO 630 KVA |
107 |
|
PT. BORNEO MAJU JAYA |
182 |
MINING |
TAMBANG BATUBARA ARUTMIN |
2022 |
TRAFO 2.000 KVA |
1 |
|
PT. SENTRA KARYA CAHAYA RAYA |
183 |
2022 |
TRAFO 150 KVA |
1 |
|||
PT. TRUNOJOYO SUMBER LISTRINDO |
184 |
2022 |
TRAFO 630 KVA |
1 |
|||
PT. GALLEON CAHAYA INVESTAMA |
185 |
INDUSTRY |
WAREHOUSE |
2022 |
TRAFO 250 KVA |
1 |
|
PT. MANUNGGAL DAYA UTAMA |
186 |
2022 |
TRAFO 1.000 KVA |
1 |
|||
PT. CAPRIFARMINDO LABORATORIES |
187 |
INDUSTRY |
PABRIK CAPRIFARMINDO LABS |
2022 |
TRAFO 4.000 KVA |
1 |
|
PT. BORNEO MAJU JAYA |
188 |
MINING |
TAMBANG BATUBARA ARUTMIN |
2022 |
TRAFO 800 KVA |
1 |
|
PT. SENTRA KARYA CAHAYA RAYA |
189 |
|
2022 |
TRAFO 125 KVA |
1 |
||
PT. NAUFAL PUTRA ELEKTRINDO |
190 |
2022 |
TRAFO 630 KVA |
1 |
|||
PT. UNITED POWER |
191 |
INDUSTRY |
KAWASAN INDUSTRI |
2022 |
TRAFO 800 KVA |
1 |
|
PT. WAHANA ACEH POWER |
192 |
2022 |
TRAFO 630 KVA |
1 |
|||
PT. REMAJA JAYA MOBILINDO |
193 |
2022 |
TRAFO 400 KVA |
1 |
|||
PT. MANORIAN ENGINEERING PRAKARSA |
194 |
2022 |
TRAFO 4.000 KVA |
2 |
|||
PT. SUMBER BUDI SAKTI |
195 |
2022 |
TRAFO 1.250 KVA |
1 |
|||
PT. ARLISCO ELEKTRIKA PERKASA |
196 |
INDUSTRY |
ALAT TEST UJI |
2022 |
TRAFO 40 KVA |
1 |
|
PT. BRAMA SARI |
197 |
PORT & AIRPORT |
PELABUHAN INDONESIA |
2022 |
TRAFO 1.000 KVA |
1 |
|
PT. KINDEN INDONESIA |
198 |
INDUSTRY |
KAWASAN ESR INDONESIA, NO : E1022018 |
2022 |
TRAFO 400 KVA |
2 |
|
PT. UNITED POWER |
199 |
2022 |
TRAFO 800 KVA |
1 |
|||
PT. ENERGY SAKTI SENTOSA |
200 |
POWERPLANT |
PLTA PAKKAT SUMATERA UTARA |
2022 |
TRAFO 250 KVA |
1 |
|
TJHIN SOEI TJIN |
201 |
INDUSTRY |
PABRIK BANDUNG |
2022 |
TRAFO 630 KVA |
1 |
|
PT. MANORIAN ENGINEERING PRAKARSA |
202 |
2022 |
TRAFO 100 KVA |
2 |
|||
PT. ATEKINDO |
203 |
COMMERCIAL |
PT. FAJAR PUTERA DINASTI METLAND CIBITUNG - WATERLAND |
2022 |
TRAFO 250 KVA |
1 |
|
PT. ATEKINDO |
204 |
2022 |
TRAFO 250 KVA |
1 |
|||
PT. BORNEO MAJU JAYA |
205 |
MINING |
TAMBANG BATUBARA ARUTMIN |
2022 |
TRAFO 50 KVA |
1 |
|
PT. BORNEO MAJU JAYA |
206 |
MINING |
TAMBANG BATUBARA ARUTMIN |
2022 |
TRAFO 630 KVA |
1 |
|
PT. SUMBER BUDI SAKTI |
207 |
2022 |
TRAFO 400 KVA |
1 |
|||
PT. ENERGY SAKTI SENTOSA |
208 |
POWERPLANT |
PLTA PAKKAT SUMATERA UTARA |
2022 |
TRAFO 400 KVA |
1 |
|
PT. SENTRA KARYA CAHAYA RAYA |
209 |
2022 |
TRAFO 200 KVA |
1 |
|||
PT. BATRAJA WIRENINDO UTAMA |
210 |
2022 |
TRAFO 3.000 KVA |
1 |
|||
PT. PEDULI BANGSA |
211 |
COMMERCIAL BUILDING |
PEKERJAAN LANJUTAN PENYELESAIAN PEMBANGUNAN RUMAH SAKIT UMUM DAERAH KOTA MANADO 2022 |
2022 |
TRAFO 630 KVA |
1 |
|
CV. VENUS INTI PERKASA |
212 |
2022 |
TRAFO 1.250 KVA |
1 |
|||
PT. AURACO INSAN BORNEO |
213 |
2022 |
TRAFO 50 KVA |
1 |
|||
PT. SEMESTA ELTRINDO PURA |
214 |
COMMERCIAL |
PURA BESAKIH |
2022 |
TRAFO 400 KVA |
1 |
|
KSO. ADHI-NINDYA-PENTA |
215 |
COMMERCIAL |
PEMBANGUNAN INDOOR MULTIFUNCTION STADIUM DALAM RANGKA KEJUARAN DUNIA BOLA BASKET TAHUN 2023 |
2022 |
TRAFO STEP DOWN 1.600 KVA |
2 |
|
PT. ASWINDO JAYA SENTOSA |
216 |
2022 |
TRAFO 1.600 KVA |
1 |
|||
PT. PAS JAYA MANDIRI |
217 |
2022 |
TRAFO 30 KVA |
1 |
|||
PT. BORNEO MAJU JAYA |
218 |
MINING |
TAMBANG BATUBARA ARUTMIN |
2022 |
TRAFO 800 KVA |
1 |
|
PT. KARYA BANGUN MANDIRI PERSADA |
219 |
COMMERCIAL BUILDING |
RS.DR.SUYOTO PUSREHAB KEMHAN |
2022 |
TRAFO 2.500 KVA |
2 |
|
PT. ADHI KARYA (PERSERO) TBK |
220 |
COMMERCIAL BUILDING |
PEMBANGUNAN GEDUNG PRESISI DIV TIK POLRI |
2022 |
TRAFO 1.000 KVA |
1 |
|
PT. BINA TEKNIK CIPTAMANDIRI |
221 |
COMMERCIAL BUILDING |
RSUD TANGERANG |
2022 |
TRAFO 800 KVA |
1 |
|
PT. PP (PERSERO) |
222 |
COMMERCIAL BUILDING |
GEDUNG PRODUKSI VAKSIN BIO FARMA |
2022 |
TRAFO 2.500 KVA ESTER OIL |
3 |
|
PT. PP (PERSERO) |
223 |
COMMERCIAL BUILDING |
GEDUNG PRODUKSI VAKSIN BIO FARMA |
2022 |
TRAFO 2.500 KVA ESTER OIL |
3 |
|
PT. SENTRA KARYA CAHAYA RAYA |
224 |
2022 |
TRAFO 100 KVA |
1 |
|||
PT. SENTRA KARYA CAHAYA RAYA |
225 |
COMMERCIAL BUILDING |
PEMBANGUNAN GEDUNG PERKANTORAN PEMDA DUMAI |
2022 |
TRAFO 1.250 KVA |
1 |
|
PT. BORNEO MAJU JAYA |
226 |
MINING |
TAMBANG BATUBARA ARUTMIN |
2022 |
TRAFO 630 KVA |
1 |
|
PT. ATEKINDO |
227 |
COMMERCIAL BUILDING |
PT. FAJAR PUTERA DINASTI METLAND CIBITUNG - LISSE |
2022 |
TRAFO 250 KVA |
1 |
|
PT. GALLEON CAHAYA INVESTAMA |
228 |
2022 |
TRAFO 200 KVA |
2 |
|||
PT. ELMAC STARK ASIATIQ |
229 |
POWERPLANT |
PLTM CIBUNI |
2022 |
TRAFO 2.500 KVA |
2 |
|
PT. ELMAC STARK ASIATIQ |
230 |
POWERPLANT |
PLTM CIBUNI |
2022 |
TRAFO 100 KVA |
1 |
|
KSO PT. POESER INDONESIA - PT. MAHARANI PRIMA |
231 |
POWERPLANT |
PLTP DIENG |
2022 |
TRAFO 700 KVA |
1 |
|
PT. KINDEN INDONESIA |
232 |
INDUSTRY |
IPC EJIP CIKARANG |
2022 |
TRAFO 2.500 KVA |
1 |
|
PT. BORNEO MAJU JAYA |
233 |
MINING |
TAMBANG BATUBARA ARUTMIN |
2022 |
TRAFO 630 KVA |
1 |
|
PT. BORNEO MAJU JAYA |
234 |
MINING |
TAMBANG BATUBARA ARUTMIN |
2022 |
TRAFO 315 KVA |
1 |
|
PT. VALVINDO MEGAH |
235 |
2022 |
TRAFO 15 KVA |
1 |
|||
PT. JAYA AGRO PERSADA |
236 |
2022 |
TRAFO 1.250 KVA |
1 |
|||
PT. KINDEN INDONESIA |
237 |
INDUSTRY |
NIPPN BIIE - CIKARANG |
2022 |
TRAFO 400 KVA |
2 |
|
PT. BINA TEKNIK CIPTAMANDIRI |
238 |
2022 |
TRAFO STEP DOWN 150 KVA |
1 |
|||
PT. BINA TEKNIK CIPTAMANDIRI |
239 |
2022 |
TRAFO STEP UP 150 KVA |
1 |
|||
PT. SENTRA KARYA CAHAYA RAYA |
240 |
2022 |
TRAFO 800 KVA |
2 |
|||
PT. METSA |
241 |
2022 |
TRAFO 400 KVA |
1 |
|||
PT. METSA |
242 |
2022 |
TRAFO 100 KVA |
2 |
|||
PT. ERASAKTI WIRAFORESTAMA |
243 |
AGRO INDUSTRY |
PENGOLAHAN KEBUN SAWIT |
2022 |
TRAFO 25 KVA |
6 |
|
PT. ERASAKTI WIRAFORESTAMA |
244 |
AGRO INDUSTRY |
PENGOLAHAN KEBUN SAWIT |
2022 |
TRAFO 50 KVA |
1 |
|
PT. ERASAKTI WIRAFORESTAMA |
245 |
AGRO INDUSTRY |
PENGOLAHAN KEBUN SAWIT |
2022 |
TRAFO 200 KVA |
11 |
|
PT. ERASAKTI WIRAFORESTAMA |
246 |
AGRO INDUSTRY |
PENGOLAHAN KEBUN SAWIT |
2022 |
TRAFO 250 KVA |
2 |
|
PT. ERASAKTI WIRAFORESTAMA |
247 |
AGRO INDUSTRY |
PENGOLAHAN KEBUN SAWIT |
2022 |
TRAFO 4.500 KVA |
1 |
|
PT. LINARD POWER KONTRAKTOR |
248 |
2022 |
TRAFO 1.000 KVA |
1 |
|||
PT. TUNAS INTI ABADI |
249 |
POWERPLANT |
SUPLY POWER LISTRIK CONVEYOR |
2022 |
TRAFO 250 KVA |
2 |
|
PT. TIGA KREASI INDONESIA |
250 |
COMMERCIAL |
MWK-TALAKAR |
2022 |
TRAFO 1.000 KVA |
1 |
|
PT. SUKSES KARYA MANDIRI |
251 |
AGRO INDUSTRY |
PERKEBUNAN KELAPA SAWIT DAN KARET |
2022 |
TRAFO STEP UP 2.000 KVA |
1 |
|
PT. SUKSES KARYA MANDIRI |
252 |
AGRO INDUSTRY |
PERKEBUNAN KELAPA SAWIT DAN KARET |
2022 |
TRAFO STEP DOWN 2.000 KVA |
1 |
|
PT. BANYAN KOALINDO LESTARI |
253 |
BUMN |
ASANGAN LISTRIK PLN DI WILAYAH IZIN USAHA PERTAMBA |
2022 |
TRAFO 630 KVA |
1 |
|
PT. BINA TEKNIK CIPTAMANDIRI |
254 |
INDUSTRY |
PT. CEM |
2022 |
TRAFO 160 KVA |
4 |
|
PT. BORNEO MAJU JAYA |
255 |
MINING |
TAMBANG BATUBARA ARUTMIN |
2022 |
TRAFO 2.500 KVA |
1 |
|
PT. MAHAMERU SINERGI INDONESIA |
256 |
2023 |
TRAFO 400 KVA |
1 |
|||
PT. MAHAMERU SINERGI INDONESIA |
257 |
2023 |
TRAFO 160 KVA |
1 |
|||
PT. SAPTA MANUNGGAL KARYA |
258 |
BUMN |
PT PLN (PERSERO) WILAYAH MALUKU |
2023 |
TRAFO STEP UP SPD 50 KW - KONTINUE CAPASITAS 100 KVA |
21 |
|
PT. SAPTA MANUNGGAL KARYA |
259 |
BUMN |
PT PLN (PERSERO) WILAYAH MALUKU |
2023 |
TRAFO STEP UP SPD 100 KW - KONTINUE CAPASITAS 160 KVA |
6 |
|
PT. RELIS - MODERN - BARUNADRI KSO |
260 |
COMMERCIAL |
07/GREEN GARDEN/21 |
2023 |
TRAFO 3.500 KVA |
1 |
|
PT. GLOBAL ELEKTRIK SENTOSA |
261 |
COMMERCIAL BUILDING |
RS. PRASETYA BUNDA |
2023 |
TRAFO 630 KVA |
1 |
|
PT. SENTRA KARYA CAHAYA RAYA |
262 |
2023 |
TRAFO 800 KVA |
1 |
|||
PT MAYORA INDAH Tbk |
263 |
INDUSTRY |
PABRIK MAYORA JAYANTI 3 |
2023 |
TRAFO 2.000 KVA |
2 |
|
PT MAYORA INDAH Tbk |
264 |
INDUSTRY |
PABRIK MAYORA JAYANTI 3 |
2023 |
TRAFO 2.500 KVA |
2 |
|
PT MAYORA INDAH Tbk |
265 |
INDUSTRY |
PABRIK MAYORA JAYANTI 3 |
2023 |
TRAFO 3.000 KVA |
2 |
|
PT. ERASAKTI WIRAFORESTAMA |
266 |
INDUSTRY |
DAK PERKAPALAN DI PKS 2 PT. EWF |
2023 |
TRAFO 200 KVA |
2 |
|
PT. BORNEO MAJU JAYA |
267 |
AGRO INDUSTRY |
MULIA SAWIT KALTENG |
2023 |
TRAFO 1.250 KVA |
1 |
|
PT. REMCO RUBBER INDONESIA |
268 |
INDUSTRY |
FIBA |
2023 |
TRAFO 1.600 KVA |
1 |
|
PT. DELLIFOOD SENTOSA CORPINDO |
269 |
INDUSTRY |
PABRIK MAYORA JAYANTI 3 |
2023 |
TRAFO 3.000 KVA |
1 |
|
PT. DELLIFOOD SENTOSA CORPINDO |
270 |
INDUSTRY |
PABRIK MAYORA JAYANTI 4 |
2023 |
TRAFO 3.500 KVA |
2 |
|
PT. JFE SHOJI INDONESIA |
271 |
2023 |
TRAFO 2.500 KVA |
1 |
|||
PT. PERTAMINA HULU ROKAN |
272 |
OIL & GAS |
PENGADAAN TRANSFORMATOR DISTRIBUSI |
2023 |
TRAFO 300/300/300 KVA PAD MOUNTED |
100 |
|
PT. SURYA SENTRA GEMILANG SENTOSA |
273 |
KAWASAN WISATA |
PEMASANGAN DI BSD FROGGY FLOATING CASTLE |
2023 |
TRAFO 1.000 KVA |
1 |
|
PT. PERTAMINA HULU ROKAN |
274 |
OIL & GAS |
PENGADAAN TRANSFORMATOR DISTRIBUSI |
2023 |
TRAFO 300/300/300 KVA PAD MOUNTED |
16 |
|
PT. MAJU TERANG GEMILANG |
275 |
2023 |
TRAFO 630 KVA |
1 |
|||
PT. ERASAKTI WIRAFORESTAMA |
276 |
INDUSTRY |
DAK PERKAPALAN DI PKS 2 PT. EWF |
2023 |
TRAFO STEP DOWN 400 KVA |
1 |
|
PT. HOK TONG |
277 |
COMMERCIAL BUILDING |
FIBA BASKET |
2023 |
TRAFO 1.600 KVA |
1 |
|
PT. BINA TEKNIK CIPTAMANDIRI |
278 |
INDUSTRY |
GEPI |
2023 |
TRAFO 250 KVA |
1 |
|
PT. ETAM BERSAMA LESTARI |
279 |
2023 |
TRAFO STEP UP 160 KVA |
1 |
|||
PT. ETAM BERSAMA LESTARI |
280 |
2023 |
TRAFO STEP DOWN 160 KVA |
1 |
|||
PT. PERTAMINA HULU ROKAN |
281 |
OIL & GAS |
PENGADAAN TRANSFORMERS 150 KVA & 500 KVA |
2023 |
TRAFO 150 KVA PAD MOUNTED |
23 |
|
PT. PERTAMINA HULU ROKAN |
282 |
OIL & GAS |
PENGADAAN TRANSFORMERS 150 KVA & 500 KVA |
2023 |
TRAFO 500 KVA PAD MOUNTED |
22 |
|
PT. VARO TECH INDONESIA |
283 |
2023 |
TRAFO 1.250 KVA |
1 |
|||
PT. PLN (PERSERO) UPK LOMBOK |
284 |
BUMN |
PENGADAAN MATERIAL TRAFO PS PLTM PENGGA DAN PLTS G1 GILI TRAWANGAN ULPLTMH/S TANJUNG PT PLN (PERSERO) UNIT INDUK WILAYAH NTB UNIT PELAKSANA PEMBANGKITAN LOMBOK |
2023 |
TRANSFORMATOR 100 KVA, 0,38 KV/0,38 KV, 3P, 50HZ, DYN11, IEC 60076, Outdoor, ONAN, HERMETICALLY SEALED WINDING : CU-CU |
1 |
|
PT. ENSAS PELITA USAHA |
285 |
2023 |
TRAFO 250 KVA |
1 |
|||
PT. ALTINOVA KARYA MANDIRI |
286 |
2023 |
TRAFO 400 KVA |
1 |
|||
PT. PLN (PERSERO) UPK TIMOR |
287 |
BUMN |
PENGADAAN TRANSFORMATOR STEP UP MESIN CUMMINS PLTD SEBA PT. PLN (PERSERO) UNIT INDUK WILAYAH NTT UNIT PELAKSANA PEMBANGKITAN TIMOR |
2023 |
TRANSFORMATOR STEP-UP, 0,4KV/20KV, ONAN, 1000 KVA, YND5, 3 PHASE, 50HZ, WINDING : COPPER (CU-CU), OFF- LOAD TAP CHANGER 5 POS, HERMETICALLY SEALED TOTALLY OIL FILLED, PROTEKSI : ISD; OUTDOOR BUSHING CERAMIC, IEC 60076/SPLN 97 |
1 |
|
PT. BORNEO MAJU JAYA |
288 |
MINING |
TAMBANG BATUBARA ARUTMIN |
2023 |
TRAFO 500 KVA |
1 |
|
PT. BORNEO MAJU JAYA |
289 |
MINING |
TAMBANG BATUBARA ARUTMIN |
2023 |
TRAFO 3.500 KVA |
1 |
|
PT. ATW SOLAR INDONESIA |
290 |
POWEPLANT |
RAPP PHASE 3 PELALAWAN |
2023 |
TRAFO ISOLASI 630 KVA |
1 |
|
PT. ERASAKTI WIRAFORESTAMA |
291 |
AGRO INDUSTRY |
TRAFO POMPA KEBUN DI PKS 4 PT. EWF |
2023 |
TRAFO 600 KVA STEP DOWN |
1 |
|
PT MAYORA INDAH Tbk |
292 |
INDUSTRY |
MAYORA INDAH WAFER DAAN MOGOT |
2023 |
TRAFO 2.500 KVA |
1 |
|
PT. PERTAMINA HULU ROKAN |
293 |
OIL & GAS |
DISTRIBUTION TRANSFORMER 300KVA |
2023 |
TRAFO 300/300/300 KVA PAD MOUNTED |
210 |
|
PT. PERTAMINA HULU ROKAN |
294 |
OIL & GAS |
PENGADAAN TRANSFORMERS 150 KVA & 500 KVA |
2023 |
TRAFO 500 KVA PAD MOUNTED |
14 |
|
PT. ATEKINDO |
295 |
COMMERCIAL BUILDING |
SITE PROJECT PT. PURADELTA LESTARI - RUKO ALMANDINE |
2023 |
TRAFO 250 KVA |
1 |
|
PT. MAJU TERANG GEMILANG |
296 |
OIL & GAS |
GAS ENGINE PT PEMA GLOBAL ENERGI - LHOKSUKON ACEH |
2023 |
TRAFO 500 KVA STEP DOWN |
1 |
|
PT. MAJU TERANG GEMILANG |
297 |
OIL & GAS |
GAS ENGINE PT PEMA GLOBAL ENERGI - LHOKSUKON ACEH |
2023 |
TRAFO 1.600 KVA STEP UP |
1 |
|
PT. NUSABARA SINERGI BERSAMA |
298 |
2023 |
TRAFO 1.600 KVA |
5 |
|||
C.V. NOGO SOSTRO BAJINTEN |
299 |
2023 |
TRAFO 250 KVA STEP DOWN |
1 |
|||
C.V. NOGO SOSTRO BAJINTEN |
300 |
2023 |
TRAFO 400 KVA STEP DOWN |
1 |
|||
KSO PT. POESER INDONESIA - PT. MAHARANI PRIMA |
301 |
POWERPLANT |
HCE 33 PLTP DIENG |
2023 |
TRAFO 1.000 KVA |
1 |
|
PT. ADHI KARYA (PERSERO) TBK |
302 |
COMMERCIAL BUILDING |
PEMBANGUNAN GEDUNG PRESISI POLRI TAHAP II |
2023 |
TRAFO 1.250 KVA |
1 |
|
PT. ALTINOVA KARYA MANDIRI |
303 |
2023 |
TRAFO 400 KVA |
1 |
|||
PT MAYORA INDAH Tbk |
304 |
INDUSTRY |
PT. MAYORA INDAH AREA PURWOSARI PASURUAN |
2023 |
TRAFO 1.600 KVA |
1 |
|
PT MAYORA INDAH Tbk |
305 |
INDUSTRY |
PT. MAYORA INDAH AREA PURWOSARI PASURUAN |
2023 |
TRAFO 2.500 KVA OLTC |
1 |
|
PT. SENTRA KARYA CAHAYA RAYA |
306 |
2023 |
TRAFO 250 KVA |
3 |
|||
PT. PLN (PERSERO) UP3 GORONTALO |
307 |
BUMN |
PENGADAAN TRAFO SPESIAL 50 KVA YZN5 OD DAN TRAFO SPESIAL 250 KVA DYN5 OD PT. PLN (PERSERO) UP3 GORONTALO |
2023 |
Transformator; 3 Phase, 50 kVA, 20 kV - 400 V, 50 Hz, Yzn5, ONAN, Al-Al, Off- Load Tap Changer 7 Pos (16-22 kV), Hermetically Sealed Totally Oil Filled, Outdoor, IEC 60076 |
1 |
|
PT. PLN (PERSERO) UP3 GORONTALO |
308 |
BUMN |
PENGADAAN TRAFO SPESIAL 50 KVA YZN5 OD DAN TRAFO SPESIAL 250 KVA DYN5 OD PT. PLN (PERSERO) UP3 GORONTALO |
2023 |
Transformator; 3 Phase, 250 kVA, 20 kV - 400 V, 50 Hz, Dyn5, ONAN, Al-Al, Off- Load Tap Changer 7 Pos (16-22 kV), Hermetically Sealed Totally Oil Filled, Outdoor, IEC 60076 |
2 |
|
PT. DWIWIRA LESTARI JAYA |
309 |
2023 |
TRAFO 315 KVA |
1 |
|||
PT. DIGA DIVA PERDANA |
310 |
COMMERCIAL BUILDING |
DINAS DSDM PROV. RIAU, TA.2023 |
2023 |
TRAFO 100 KVA |
2 |
|
PT. PERTAMINA HULU ROKAN |
311 |
OIL & GAS |
CALL-OFF ORDER (COO) TRANSFORMER (PAKET 1) |
2023 |
TRAFO 500 KVA PAD MOUNTED |
2 |
|
PT. PERTAMINA HULU ROKAN |
312 |
OIL & GAS |
CALL-OFF ORDER (COO) TRANSFORMER (PAKET 1) |
2023 |
TRAFO 112,5 KVA POLE MOUNTED |
29 |
|
PT. PERTAMINA HULU ROKAN |
313 |
OIL & GAS |
CALL-OFF ORDER (COO) TRANSFORMER (PAKET 1) |
2023 |
TRAFO 150 KVA POLE MOUNTED |
16 |
|
PT. PERTAMINA HULU ROKAN |
314 |
OIL & GAS |
CALL-OFF ORDER (COO) TRANSFORMER (PAKET 1) |
2023 |
TRAFO 500 KVA PAD MOUNTED |
1 |
|
PT. PERTAMINA HULU ROKAN |
315 |
OIL & GAS |
CALL-OFF ORDER (COO) TRANSFORMER (PAKET 1) |
2023 |
TRAFO 150 KVA POLE MOUNTED |
5 |
|
PT. WAHANA IDEA CIPTA |
316 |
PABRIK DI BINTAN INDUSTRI LOT 19-23 BIIE |
2023 |
TRAFO 1.000 KVA |
2 |
||
PT. PERTAMINA HULU ROKAN |
317 |
OIL & GAS |
CALL-OFF ORDER (COO) TRANSFORMER (PAKET 1) |
2023 |
TRAFO 150 KVA POLE MOUNTED |
14 |
|
PT. GUNA MITRA PRIMA |
318 |
2023 |
TRAFO 630 KVA STEP DOWN |
1 |
|||
PT. PLN (PERSERO) UPK TIMOR |
319 |
BUMN |
PENGADAAN TRAFO STEP UP PEMBANGKITAN KAPASITAS 630 KVA PLTD WAITABULA PT PLN (PERSERO) UNIT PELAKSANA PEMBANGKITAN TIMOR |
2023 |
TRANSFORMATOR STEP UP, 630KVA, 400V/20KV, YND5, 3 PHASE, 50HZ, OUTDOOR, IEC 60076, PROTEKSI : ISD, BUSHING CERAMIC, WINDING : CU-CU |
1 |
|
PT. PERTAMINA HULU ENERGI KAMPAR |
320 |
OIL & GAS |
PENGADAAN 3 (TIGA) UNIT TRANSFORMATOR STEP DOWN |
2023 |
TRAFO 200 KVA |
3 |
|
PT. BINA TEKNIK CIPTAMANDIRI |
321 |
INDUSTRY |
PEKAN BARU-RIAU |
2023 |
TRAFO 100 KVA |
1 |
|
PT. PERTAMINA HULU ROKAN |
322 |
OIL & GAS |
CALL-OFF ORDER (COO) TRANSFORMER (PAKET 1) |
2023 |
TRAFO 112,5 KVA POLE MOUNTED |
15 |
|
PT. PERTAMINA HULU ROKAN |
323 |
OIL & GAS |
CALL-OFF ORDER (COO) TRANSFORMER (PAKET 1) |
2023 |
TRAFO 150 KVA PAD MOUNTED |
21 |
|
PT. KURNIA TUNGGAL NUGRAHA |
324 |
2023 |
TRAFO 630 KVA STEP DOWN |
1 |
|||
PT MAYORA INDAH Tbk |
325 |
INDUSTRY |
MAYORA INDAH WAFER DAAN MOGOT |
2023 |
TRAFO 2.500 KVA |
1 |
|
PT. PERTAMINA HULU ROKAN |
326 |
OIL & GAS |
CALL-OFF ORDER (COO) TRANSFORMER (PAKET 1) |
2023 |
TRAFO 500 KVA PAD MOUNTED |
12 |
|
PT. ATW SOLAR INDONESIA |
327 |
INDUSTRY |
DMIA OFFGRID |
2023 |
TRAFO ISOLASI 150 KVA |
1 |
|
PT. MAHAMERU SINERGI INDONESIA |
328 |
INDUSTRY |
BATURAJA SUMATERA SELATAN |
2023 |
TRAFO 630 KVA OLTC |
1 |
|
PT. BASUDARA SUKSES BERSAMA |
329 |
BUMN |
PT. PLN (PERSERO) WILAYAH MALUKU |
2023 |
TRAFO ISOLASI 100 KVA |
1 |
|
PT. METSA |
330 |
2023 |
TRAFO 160 KVA YNd5 |
1 |
|||
PT. METSA |
331 |
2023 |
TRAFO 160 KVA DYN5 |
1 |
|||
PT. WINDU NABATINDO LESTARI |
332 |
AGRO INDUSTRY |
KEBUN SAWIT PKS BGA GROUP , BANJARMASIN |
2023 |
TRAFO 630 KVA (OLTC) |
1 |
|
PT. PRASS |
333 |
INDUSTRY |
JARINGAN KAB. KEPULAUAN MERANTI |
2023 |
TRAFO 100 KVA |
1 |
|
PT. MAHAMERU SINERGI INDONESIA |
334 |
2023 |
TRAFO 315 KVA |
1 |
|||
PT. PLN (PERSERO) UP3 SANGGAU |
335 |
BUMN |
GRID PLTD BELIKAI DAN PLTD SEBERUANG |
2023 |
TRAFO AVR 5.000 KVA |
1 |
|
PT. SENTOSA PRIMA AGRO |
336 |
AGRO INDUSTRY |
KEBUN SAWIT PKS BGA GROUP , BANJARMASIN |
2023 |
TRAFO 630 KVA (OLTC) |
1 |
|
PT. LADANG SAWIT MAS |
337 |
AGRO INDUSTRY |
KEBUN SAWIT PKS BGA GROUP , BANJARMASIN |
2023 |
TRAFO 1.000 KVA (OLTC) |
1 |
|
PT. PERTAMINA HULU ROKAN |
338 |
OIL & GAS |
CALL-OFF ORDER (COO) TRANSFORMER (PAKET 1) |
2023 |
TRAFO 500 KVA PAD MOUNTED |
14 |
|
PT. ANDALAS PETROLEUM SERVICES |
339 |
INDUSTRY |
BUMI SIAK PUSAKO |
2023 |
TRAFO 100 KVA |
5 |
|
PT. ANDALAS PETROLEUM SERVICES |
340 |
INDUSTRY |
BUMI SIAK PUSAKO |
2023 |
TRAFO 50 KVA |
9 |
|
PT. METSA |
341 |
BUMN |
PROJECT NUSA TENGGARA TIMUR |
2023 |
TRAFO 250 KVA |
1 |
|
PT. PLN (PERSERO) UPK TIMOR |
342 |
BUMN |
PT PLN (PERSERO) |
2023 |
TRAFO 630 KVA STEP UP |
1 |
|
PT. PLN (PERSERO) UPK TIMOR |
343 |
BUMN |
PENGADAAN TRAFO STEP UP PEMBANGKITAN KAPASITAS 630 KVA PLTD WAITABULA PT PLN (PERSERO) UNIT PELAKSANA PEMBANGKITAN TIMOR |
2023 |
TRANSFORMATOR STEP UP, 630KVA, 400V/20KV, YND5, 3 PHASE, 50HZ, OUTDOOR, IEC 60076, PROTEKSI : ISD, BUSHING CERAMIC, WINDING : CU-CU |
1 |
|
PT. PLN (PERSERO) UP2D JAWA TIMUR |
344 |
BUMN |
PENGADAAN TRAFO PS GI |
2023 |
TRAFO STEP DOWN 315 KVA |
5 |
|
PT. SWADAYA DWIPANTARA |
345 |
POWERPLANT |
PLTU PUNAGAYA |
2023 |
TRAFO STEP UP 2.000 KVA |
4 |
|
PT. BORNEO MAJU JAYA |
346 |
MINING |
PKS BATU KALI |
2023 |
TRAFO 315 KVA |
1 |
|
PT. SINAR ANISA MANDIRI |
347 |
2023 |
TRAFO 400 KVA |
1 |
|||
PT. BAKER HUGHES INDONESIA |
348 |
2023 |
TRAFO ISOLASI 100 KVA |
3 |
|||
PT. ATEKINDO |
349 |
COMMERCIAL BUILDING |
METLAND SCHOOL |
2023 |
TRAFO 250 KVA |
1 |
|
PT. MAHAMERU SINERGI INDONESIA |
350 |
MINING |
TRIPUTRA AGRO PERSADA |
2023 |
TRAFO 200 KVA |
1 |
|
PT. MAHAMERU SINERGI INDONESIA |
351 |
MINING |
TRIPUTRA AGRO PERSADA |
2023 |
TRAFO 315 KVA |
1 |
|
PT. SARANA UTAMA ADIMANDIRI |
352 |
INDUSTRY |
ESR-3 |
2023 |
TRAFO OIL IMMERSED TYPE 2000KVA, 20KV/400V, DYN5, 50HZ, INDOOR, ONAN, 3P, OFF-LOAD TAP CHANGER 5 POS, HERMETICALLY SEALED, IEC 60076, LV COPPER LINK, WINDING : CU-CU |
1 |
|
PT. SARANA UTAMA ADIMANDIRI |
353 |
INDUSTRY |
PROJECT CODE : K-23-46 (SANWA SUBANG) |
2023 |
TRAFO OIL IMMERSED TYPE 630KVA; 20KV/400V;DYN5;50HZ; INDOOR; ONAN;3 PHASE;ISD (DGPT BRAND); HERMETICALLY SEALED; IEC 60076, WELDING CU-CU C/W HV LV CABLE BOX PROTECTION |
1 |
|
PT. PLN (Persero) UP3 PONTIANAK |
354 |
BUMN |
PENGADAAN MANUAL STABILIZER UNTUK PROGRAM DEDIESELISASI LIMBUNG LOKASI : PT PLN (PERSERO) UP3 PONTIANAK |
2023 |
MANUAL STABILIZER 50 KVA |
1 |
|
PT. PLN (Persero) UP3 PONTIANAK |
355 |
BUMN |
PENGADAAN MANUAL STABILIZER UNTUK PROGRAM DEDIESELISASI LIMBUNG LOKASI : PT PLN (PERSERO) UP3 PONTIANAK |
2023 |
MANUAL STABILIZER 200 KVA |
1 |
|
PT. BORNEO MAJU JAYA |
356 |
MINING |
TAMBANG BATUBARA ARUTMIN |
2023 |
TRAFO 1.000 KVA |
1 |
|
PT. SARANA UTAMA ADIMANDIRI |
357 |
INDUSTRY |
ESR-3 |
2023 |
TRAFO OIL IMMERSED TYPE 2000KVA, 20KV/400V, DYN5, 50HZ, INDOOR, ONAN, 3P, OFF-LOAD TAP CHANGER 5 POS, HERMETICALLY SEALED, IEC 60076, LV COPPER LINK, WINDING : CU-CU |
1 |
|
PT. BORNEO ADELIA PRATAMA |
358 |
BUMN |
PENGADAAN DAN PEMASANGAN KONSTRUKSI AUTOMATIC VOLTAGE REGULATOR (AVR) PERBAIKAN TEGANGAN DROP UP3 PONTIANAK ULP RASAU JAYA |
2023 |
Transformator Automatic Voltage Regulator; 3 Phase, 4000 kVA, Input 17 kV up to 21 kV, 500 Volt/Step Output 20 kV, 50 Hz, YNa0, ONAN, Cu-Cu, On-Load Tap Changer 9 Pos, Hermetically Sealed with Conservator, Outdoor, IEC 60076 |
1 |
|
PT. SARANA UTAMA ADIMANDIRI |
359 |
INDUSTRY |
CODE : K-23-46 (SANWA SUBANG) |
2023 |
TRAFO OIL IMMERSED TYPE 630KVA; 20KV/400V;DYN5;50HZ; INDOOR; ONAN;3 PHASE;ISD (DGPT BRAND); HERMETICALLY SEALED; IEC 60076, WELDING CU-CU C/W HV LV CABLE BOX PROTECTION |
1 |
|
PT. PLN (Persero) UP3 PONTIANAK |
360 |
BUMN |
PENGADAAN TRAFO MANUAL STABILIZER 50KVA DAN 200KVA |
2023 |
Manual Stabilizer 50kVA (Transformator; 3 Phase, 50 kVA, 20 kV - 400 V, 50 Hz, Yzn5, ONAN, Al-Al, Off Load Tap Changer 7 Pos (20.000-19.000- 18.000-17.000-15.000-14.000 V),Hermetically Sealed Totally Oil Filled, Outdoor,SPLN D3.002-1: 2007) |
1 |
|
PT. PLN (Persero) UP3 PONTIANAK |
361 |
BUMN |
PENGADAAN TRAFO MANUAL STABILIZER 50KVA DAN 200KVA |
2023 |
Manual Stabilizer 200kVA (Transformator; 3 Phase, 200 kVA, 20 kV - 400 V, 50 Hz, Dyn5, ONAN, Al-Al,Off Load Tap Changer 7 Pos (20.000-19.000- 18.000-17.000-15.000-14.000 V),Hermetically Sealed Totally Oil Filled,Outdoor, SPLN D3.002-1: 2007) |
1 |
|
PT. PLN (PERSERO) UP3 SINGKAWANG |
362 |
POWERPLANT |
REVITALISAI PLTS TEMAJUK LOKASI UP3 SINGKAWANG |
2023 |
TRANSFORMATOR,20 KV/0,4 KV,400KVA,ONAN,Off Load tap changer sisi 20KV,YNyn0+d1 Belitan delta tersier internal/buried, tidak ada koneksi keluar Rating kVa belitan delta tersier 35% dari kVa rating transformer, Rating Tegangan belitan delta tersier by manuf |
1 |
|
PT. PLN (PERSERO) UP2D JAWA TENGAH DAN D.I YOGYAKARTA |
363 |
BUMN |
PEKERJAAN PENGADAAN TRAFO PS GI SPESIFIKASI KHUSUS |
2023 |
Trafo 100 KVA 22 kV - 400 V, Ynyn0, 3 phase |
29 |
|
PT. MAJU TERANG GEMILANG |
364 |
COMMERCIAL BUILDING |
RS RKZ SURABAYA |
2023 |
TRAFO 1.000 KVA |
1 |
|
PT. LS ELECTRIC INDONESIA |
365 |
POWERPLANT |
DIESEL POWER PLANT NTB |
2023 |
TRAFO 1.500 KVA |
14 |
|
PT. DENKI ENGINEERING |
366 |
- |
- |
2023 |
TRAFO 1.000 KVA |
1 |
|
PT. BINA TEKNIK CIPTAMANDIRI |
367 |
INDUSTRY |
SURABAYA |
2023 |
TRAFO 50 KVA |
2 |
|
PT. WAHANA MULIA SEJATI |
368 |
COMMERCIAL BUILDING |
GTI TOWN SQUARE BEKASI |
2023 |
TRAFO 630 KVA |
1 |
|
PT. KINDEN INDONESIA |
369 |
INDUSTRY |
NBC KARAWANG INDONESIA |
2023 |
TRAFO 50 KVA |
1 |
|
PT. KINDEN INDONESIA |
370 |
INDUSTRY |
NBC KARAWANG INDONESIA |
2023 |
TRAFO 630 KVA |
1 |
|
PT. KINDEN INDONESIA |
371 |
INDUSTRY |
NBC KARAWANG INDONESIA |
2023 |
TRAFO 1.250 KVA |
1 |
|
PT. KINDEN INDONESIA |
372 |
INDUSTRY |
IWATANI INDUSTRIAL GAS INDONESIA |
2023 |
TRAFO 7.500 KVA |
1 |
|
PT. KINDEN INDONESIA |
373 |
INDUSTRY |
IWATANI INDUSTRIAL GAS INDONESIA |
2023 |
TRAFO 1.600 KVA |
1 |
|
PT. KINDEN INDONESIA |
374 |
INDUSTRY |
IWATANI INDUSTRIAL GAS INDONESIA |
2023 |
TRAFO 1.600 KVA |
1 |
|
PT. LS ELECTRIC INDONESIA |
375 |
INDUSTRY |
DAEWOONG PHARMACEUTICALS (KOREAN PROJECT) |
2023 |
TRAFO 1.000 KVA |
4 |
|
PT. SURYA PERDANA ELEKTRIKA |
376 |
COMMERCIAL BUILDING |
BIOFARMA GD. 41-B |
2023 |
TRAFO OIL ESTER SYNTHETIC 2.500 KVA |
1 |
|
PT. SURYA PERDANA ELEKTRIKA |
377 |
COMMERCIAL BUILDING |
BIOFARMA GD. 41-B |
2023 |
TRAFO OIL ESTER SYNTHETIC 2.500 KVA |
1 |
|
PT. KARIANGAU POWER |
378 |
POWERPLANT |
PLTU KARIANGAU POWER |
2023 |
TRAFO 200 KVA |
3 |
|
PT. KARIANGAU POWER |
379 |
POWERPLANT |
PLTU KARIANGAU POWER |
2023 |
TRAFO 50 KVA |
1 |
|
PT. BUMITAMA GUNAJAYA ABADI |
380 |
INDUSTRY |
LISTRIK LIMBAH PEMBUANGAN LIMBAH BGA GROUP BMKM |
2023 |
TRAFO 250 KVA |
2 |
|
PT. LS ELECTRIC INDONESIA |
381 |
INDUSTRY |
PT DONGJIN TEXTILE INDONESIA - KENDAL |
2023 |
TRAFO 2.000 KVA |
2 |
|
PT. KARYA RUATA |
382 |
INDUSTRY |
UNTUK INTERNAL PT KARYA RUATA |
2023 |
TRAFO 1.600 KVA |
1 |
|
PT. ARLISCO ELEKTRIKA PERKASA |
383 |
INDUSTRY |
RnD PT. ARLISCO |
2023 |
TRAFO DRY NON RESIN 15 KVA |
2 |
|
PT. MAJU TERANG GEMILANG |
384 |
INDUSTRY |
PABRIK TEKSTIL SURABAYA |
2023 |
TRAFO 630 KVA |
1 |
|
PT. KARYA MAKMUR BAHAGIA |
385 |
INDUSTRY |
LISTRIK PEMBUANGAN LIMBAH BGRA GROUP, TRYM |
2023 |
TRAFO 250KVA |
1 |
|
PT. KARYA MAKMUR BAHAGIA |
386 |
INDUSTRY |
LISTRIK PEMBUANGAN LIMBAH BGRA GROUP, TRYM |
2023 |
TRAFO 100 KVA |
1 |
|
PT. PLN (PERSERO) UP2D JAWA TENGAH DAN D.I YOGYAKARTA |
387 |
BUMN |
PEKERJAAN PENGADAAN TRAFO PS GI SPESIFIKASI KHUSUS |
2023 |
Trafo 100 KVA 22 kV - 400 V, Ynyn0, 3 phase |
29 |
|
PT. PLN (PERSERO) UP3 PALU |
388 |
BUMN |
PENGADAAN TRAFO DISTRIBUSI 250 KVA (TYPE KHUSUS) PT. PLN (PERSERO) UP3 PALU |
2024 |
Transformator; 3 Phase, 250 kVA, 20 kV - 400 V, 50 Hz, Dyn11, ONAN, Al-Al, Off- Load Tap Changer 9 Pos (12-20 kV), Hermetically Sealed Totally Oil Filled, Outdoor, IEC 60076 |
3 |
|
PT. PLN (PERSERO) UP2D JAWA TENGAH DAN D.I YOGYAKARTA |
389 |
BUMN |
PENGADAAN TRAFO PS GI SPEK KHUSUS 22KV-400V |
2024 |
Trafo 100 KVA 22 kV - 400 V, Ynyn0, 3 phase |
14 |
|
PT. HUTAMA KARYA (PERSERO) |
390 |
COMMERCIAL BUILDING |
RUMAH SUSUN ASN 2 IKN |
2024 |
TRAFO OIL ESTER SYNTHETIC 1.600 KVA |
2 |
|
PT. HUTAMA KARYA (PERSERO) |
391 |
COMMERCIAL BUILDING |
KANTOR KEMENTERIAN KOORDINATOR 2 IKN |
2024 |
TRAFO OIL ESTER SYNTHETIC 2.500 KVA |
1 |
|
PT. WASKITA KARYA (Persero) Tbk |
392 |
COMMERCIAL BUILDING |
RUMAH SUSUN ASN 3 KALTIMRA |
2024 |
TRAFO OIL ESTER SYNTHETIC 2.000 KVA |
2 |
|
PT. LENTERA CIPTA KARYA |
393 |
COMMERCIAL BUILDING |
PASPAMPRES IKN |
2024 |
TRAFO OIL ESTER SYNTHETIC 1.250 KVA |
3 |
|
PT. KINDEN INDONESIA |
394 |
INDUSTRY |
HITACHI CONSTRUCTION MACHINERY |
2024 |
TRAFO 2.500 KVA |
1 |
|
PT MAYORA INDAH Tbk |
395 |
INDUSTRY |
PABRIK MAYORA JAYANTI 3 |
2024 |
TRAFO 3.500 KVA |
1 |
|
PT. BAKER HUGHES INDONESIA |
396 |
INDUSTRY |
PENGADAAN TRAFO SWASTA PEKANBARU |
2024 |
TRAFO 550 KVA |
4 |
|
PT. INDEXIM COALINDO |
397 |
MINING |
TAMBANG BATUBARA KALTIM KALIORANG |
2024 |
TRAFO 3.500 KVA (OLTC) |
2 |
|
PT. INDEXIM COALINDO |
398 |
MINING |
TAMBANG BATUBARA KALTIM KALIORANG |
2024 |
TRAFO 200 KVA |
2 |
|
PT. INDEXIM COALINDO |
399 |
MINING |
TAMBANG BATUBARA KALTIM KALIORANG |
2024 |
TRAFO 100 KVA |
1 |
|
CV. SAMUDERA JAYA ELEKTRIK |
400 |
INDUSTRY |
PT. SANSAN SAUDARATEX JAYA - PABRIK TEKSTIL |
2024 |
TRAFO STEP DOWN 1.600 KVA |
1 |
|
PT. BAKER HUGHES INDONESIA |
401 |
INDUSTRY |
PENGADAAN TRAFO SWASTA KUALO MUDO-KULIM KM.6 RIAU |
2024 |
TRAFO 260 KVA |
1 |
|
PT. BAKER HUGHES INDONESIA |
402 |
INDUSTRY |
PENGADAAN TRAFO SWASTA KUALO MUDO-KULIM KM.6 RIAU |
2024 |
TRAFO 500 KVA |
2 |
|
PT. LS ELECTRIC INDONESIA |
403 |
POWERPLANT |
SPACE TECHNOLOGY - PLTD LOMBOK |
2024 |
TRAFO 1.600 KVA |
9 |
|
PT. LA TANSA PALEMBANG JAYA |
404 |
COMMERCIAL BUILDING |
PROVINSI BABEL KOTA TOBOALI |
2024 |
TRAFO 25 KVA |
1 |
|
PT. PUTERA JAYA ANDALAN |
405 |
COMMERCIAL BUILDING |
PASAR GODEAN SLEMAN YOGYAKARTA |
2024 |
TRAFO OIL ESTER SYNTHETIC 400 KVA |
1 |
|
PT. LS ELECTRIC INDONESIA |
406 |
PLTD |
SPACE TECHNOLOGY - PLTD LOMBOK |
2024 |
TRAFO 2.000 KVA |
1 |
|
PT. ADHI KARYA (PERSERO) TBK |
407 |
COMMERCIAL BUILDING |
PENGADAAN CONSTRUCTION TRANSFORMER PUPUK SRIWIJAYA III-B PALEMBANG |
2024 |
TRAFO 750 KVA |
1 |
|
PT. ADHI KARYA (PERSERO) TBK |
408 |
COMMERCIAL BUILDING |
PENGADAAN CONSTRUCTION TRANSFORMER PUPUK SRIWIJAYA III-B PALEMBANG |
2024 |
TRAFO 400 KVA |
1 |
|
ABIPRAYA-SBS-SILCON,KSO |
409 |
COMMERCIAL BUILDING |
PEMBANGUNAN TEMPAT PENGOLAHAN SAMPAH TERPADU 1 KAWASAN INTI PUSAT PEMERINTAHAN IBU KOTA NEGARA (TPST 1 KIPP IKN) |
2024 |
TRAFO OIL ESTER SYNTHETIC 2.500 KVA |
1 |
|
PT. WOOJIN CONSTRUCTION INDONESIA |
410 |
INDUSTRY |
SY TECH |
2024 |
TRAFO 800 KVA |
1 |
|
PT. WOOJIN CONSTRUCTION INDONESIA |
411 |
INDUSTRY |
SY TECH |
2024 |
TRAFO 175 KVA |
1 |
|
PT. BEKASI POWER |
412 |
INDUSTRY |
DISTRIBUSI KIOS BEKASI POWER |
2024 |
TRAFO 1.250 KVA |
1 |
|
PT. LS ELECTRIC INDONESIA |
413 |
POWERPLANT |
SPACE TECHNOLOGY - PLTD LOMBOK |
2024 |
TRAFO 1.600 KVA |
2 |
|
PT. SENTRA KARYA CAHAYA RAYA |
414 |
ESTATE |
PERKEBUNAN KELAPA SAWIT-RIAU |
2024 |
TRAFO 350 KVA |
1 |
|
PP-URBAN-JAYA KONSTRUKSI,KSO |
415 |
COMMERCIAL BUILDING |
RUMAH SUSUN ASN 1 IKN KALIMANTAN TIMUR |
2024 |
TRAFO OIL ESTER SYNTHETIC 2.000 KVA |
1 |
|
PP-URBAN-JAYA KONSTRUKSI,KSO |
416 |
COMMERCIAL BUILDING |
RUMAH SUSUN ASN 1 IKN KALIMANTAN TIMUR |
2024 |
TRAFO OIL ESTER SYNTHETIC 1.600 KVA |
1 |
|
KSO.ADHI-NINDYA-WIRATMAN |
417 |
COMMERCIAL BUILDING |
RUMAH SUSUN POLRI BIN IKN KALIMANTAN TIMUR |
2024 |
TRAFO OIL ESTER SYNTHETIC 1.600 KVA |
1 |
|
KSO.ADHI-NINDYA-WIRATMAN |
418 |
COMMERCIAL BUILDING |
RUMAH SUSUN POLRI BIN IKN KALIMANTAN TIMUR |
2024 |
TRAFO OIL ESTER SYNTHETIC 2.000 KVA |
1 |
|
PT. PLN (PERSERO) UP3 PALU |
419 |
BUMN |
PENGADAAN TRAFO DISTRIBUSI 250 KVA (TYPE KHUSUS) PT. PLN (PERSERO) UP3 PALU |
2024 |
Transformator; 3 Phase, 250 kVA, 20 kV - 400 V, 50 Hz, Dyn11, ONAN, Al-Al, Off- Load Tap Changer 9 Pos (12-20 kV), Hermetically Sealed Totally Oil Filled, Outdoor, IEC 60076 |
3 |
|
PT. SUMBER BUDI SAKTI |
420 |
INDUSTRY |
BALI DAN LOMBOK |
2024 |
TRAFO 400 KVA OCTC |
1 |
|
PT. PLN (PERSERO) UP3 GORONTALO |
421 |
BUMN |
PENGADAAN TRAFO KHUSUS : 3 UNIT 3P 50 KVA YZN5, 1 UNIT 3P 100 KVA YZN5 DAN 1 UNIT 160 KVA YZN5 PT PLN (PERSERO) UP3 GORONTALO TAHUN 2024 |
2024 |
Transformator; 3 Phase, 50 kVA, 20 kV - 400 V, 50 Hz, Yzn5, ONAN, Al-Al, Off Load Tap Changer 9 Pos (16-16.5 - 17- 17.5 - 18-18.5 - 19-19.5 - 20 kV), Hermetically Sealed Totally Oil Filled, Outdoor, IEC 60076 |
3 |
|
PT. PLN (PERSERO) UP3 GORONTALO |
422 |
BUMN |
PENGADAAN TRAFO KHUSUS : 3 UNIT 3P 50 KVA YZN5, 1 UNIT 3P 100 KVA YZN5 DAN 1 UNIT 160 KVA YZN5 PT PLN (PERSERO) UP3 GORONTALO TAHUN 2024 |
2024 |
Transformator; 3 Phase, 100 kVA, 20 kV - 400 V, 50 Hz, Yzn5, ONAN, Al-Al, Off Load Tap Changer 9 Pos (16-16.5 - 17- 17.5 - 18-18.5 - 19-19.5 - 20 kV), Hermetically Sealed Totally Oil Filled, Outdoor, IEC 60076 |
1 |
|
PT. PLN (PERSERO) UP3 GORONTALO |
423 |
BUMN |
PENGADAAN TRAFO KHUSUS : 3 UNIT 3P 50 KVA YZN5, 1 UNIT 3P 100 KVA YZN5 DAN 1 UNIT 160 KVA YZN5 PT PLN (PERSERO) UP3 GORONTALO TAHUN 2024 |
2024 |
Transformator; 3 Phase, 160 kVA, 20 kV - 400 V, 50 Hz, Yzn5, ONAN, Al-Al, Off Load Tap Changer 9 Pos (16-16.5 - 17- 17.5 - 18-18.5 - 19-19.5 - 20 kV), Hermetically Sealed Totally Oil Filled, Outdoor, IEC 60076 |
1 |
|
PT. BASUDARA SUKSES BERSAMA |
424 |
2024 |
TRAFO 800 KVA |
1 |
|||
PT PLN (PERSERO) UP3 PADANG |
425 |
BUMN |
PENGADAAN TRAFO 200 KVA LOKASI PT PLN (PERSERO) UNIT PELAKSANA PELAYANAN PELANGGAN PADANG |
2024 |
Transformator; 3 Phase, 200 kVA, 20 kV - 400 V, 50 Hz, Yzn5, ONAN, Al-Al, Off Load Tap Changer 7 Pos, Hermetically Sealed Totally Oil Filled, Outdoor, SPLN D3.002-1: 2007 |
3 |
|
PT. INDOAUSTRA UTAMA |
426 |
COMMERCIAL BUILDING |
RUSUN ASN 4 IKN |
2024 |
TRAFO OIL ESTER SYNTHETIC 1.250 KVA |
1 |
|
PT. INDOAUSTRA UTAMA |
427 |
COMMERCIAL BUILDING |
RUSUN ASN 4 IKN |
2024 |
TRAFO OIL ESTER SYNTHETIC 1.600 KVA |
2 |
|
PT. PLN (PERSERO) UP3 GORONTALO |
428 |
BUMN |
PELAKSANAAN PENGADAAN TRAFO KHUSUS : 3 UNIT 3P 50 KVA YZN5, 1 UNIT 3P 100 KVA YZN5 DAN 1 UNIT 160 KVA YZN5 PT PLN (PERSERO) UP3 GORONTALO TAHUN 2024 |
2024 |
TRANSFORMATOR; 3 PHASE, 50 KVA IEC 60076 |
3 |
|
PT. PLN (PERSERO) UP3 GORONTALO |
429 |
BUMN |
PELAKSANAAN PENGADAAN TRAFO KHUSUS : 3 UNIT 3P 50 KVA YZN5, 1 UNIT 3P 100 KVA YZN5 DAN 1 UNIT 160 KVA YZN5 PT PLN (PERSERO) UP3 GORONTALO TAHUN 2024 |
2024 |
TRANSFORMATOR; 3 PHASE, 100 KVA IEC 60076 |
1 |
|
PT. PLN (PERSERO) UP3 GORONTALO |
430 |
BUMN |
PELAKSANAAN PENGADAAN TRAFO KHUSUS : 3 UNIT 3P 50 KVA YZN5, 1 UNIT 3P 100 KVA YZN5 DAN 1 UNIT 160 KVA YZN5 PT PLN (PERSERO) UP3 GORONTALO TAHUN 2024 |
2024 |
TRANSFORMATOR; 3 PHASE, 160 KVA IEC 60076 |
1 |
|
PT. PUTRA UTAMA SAWIT SUNGAI ANGIT |
431 |
PABRIK PENGOLAHAN KELAPA SAWIT |
2024 |
TRAFO 630 KVA |
1 |
||
PT. SARANA UTAMA ADIMANDIRI |
432 |
INDUSTRY |
PROJECT CODE : K-23-60 - (NIPPON KONPO (NKI) ) |
2024 |
TRAFO 315 KVA STEP DOWN |
1 |
|
PT. MAJU TERANG GEMILANG |
433 |
COMMERCIAL BUILDING |
PERGUDANGAN EKSPEDISI |
2024 |
TRAFO 1.250 KVA |
1 |
|
PT. LS ELECTRIC INDONESIA |
434 |
POWERPLANT |
SPACE TECHNOLOGY - PLTD LOMBOK |
2024 |
TRAFO 1.600 KVA |
1 |
|
ADHI-HK KSO |
435 |
COMMERCIAL BUILDING |
RUMAH SAKIT VERTIKAL IBU KOTA NEGARA (IKN) NUSANTARA |
2024 |
TRAFO OIL ESTER SYNTHETIC 2.000 KVA |
2 |
|
PT. PERTAMINA HULU ROKAN |
436 |
OIL & GAS |
CALL-OFF ORDER (COO) TRANSFORMER (PAKET 1) |
2024 |
TRAFO 112,5 KVA POLE MOUNTED |
60 |
|
PT PLN (PERSERO) UP3 BULUNGAN |
437 |
BUMN |
PENGADAAN TRAFO 1.000 KVA UNTUK SPKLU KANTOR PUSAT |
2024 |
TRAFO DISTRIBUSI 20KV/400V 3 PHASE 1000 KVA DYN5 ID IEC 60076 |
1 |
|
PT. PERTAMINA HULU ROKAN |
438 |
OIL & GAS |
CALL-OFF ORDER (COO) TRANSFORMER (PAKET 1) |
2024 |
TRAFO 150 KVA PAD MOUNTED |
30 |
|
PT. PERTAMINA HULU ROKAN |
439 |
OIL & GAS |
CALL-OFF ORDER (COO) TRANSFORMER (PAKET 1) |
2024 |
TRAFO 150 KVA POLE MOUNTED |
10 |
|
PT. PERTAMINA HULU ROKAN |
440 |
OIL & GAS |
CALL-OFF ORDER (COO) TRANSFORMER (PAKET 1) |
2024 |
TRAFO 300 KVA PAD MOUNTED |
50 |
|
PT. ERAN PLASTINDO UTAMA |
441 |
INDUSTRY |
PABRIK PLASTIK |
2024 |
TRAFO 1.500 KVA |
1 |
|
PT. SARANA UTAMA ADIMANDIRI |
442 |
INDUSTRY |
K-24-14- (OSG INDONESIA) |
2024 |
TRANSFORMER MINERAL OIL IMMERSED TYPE 500 KVA |
1 |
|
PT. MAJU TERANG GEMILANG |
443 |
INDUSTRY |
UNTUK STOK |
2024 |
TRANSFORMATOR OIL IMMERSED 1.600 KVA |
1 |
|
PT. MAJU TERANG GEMILANG |
444 |
INDUSTRY |
UNTUK STOK |
2024 |
TRANSFORMATOR OIL IMMERSED 1.250 KVA |
1 |
|
PT. MAJU TERANG GEMILANG |
445 |
INDUSTRY |
UNTUK STOK |
2024 |
TRANSFORMATOR OIL IMMERSED 630 KVA |
1 |
|
PT. MAHAMERU SINERGI INDONESIA |
446 |
ESTATE |
TRIPUTRA AGRO PERSADA KEBUN KELAPA SAWIT |
2024 |
TRAFO 100 KVA |
1 |
|
PT. INDOPOLY SWAKARSA INDUSTRY TBK |
447 |
INDUSTRY |
PERLUASAN PABRIK BOPP LINE 3 PT. INDOPOLY SWAKARSA INDUSTRY TBK KOTA BUKUT INDAH- PURWAKARTA |
2024 |
TRAFO OIL CONSERVATOR TYPE 2.000 KVA |
1 |
|
PT. INDOPOLY SWAKARSA INDUSTRY TBK |
448 |
INDUSTRY |
PERLUASAN PABRIK BOPP LINE 3 PT. INDOPOLY SWAKARSA INDUSTRY TBK KOTA BUKUT INDAH- PURWAKARTA |
2024 |
TRAFO OIL CONSERVATOR TYPE 2.500 KVA |
2 |
|
PT. DUTA PERSADA POWER |
449 |
POWERPLANT |
PLTD PLN NUSA DAYA |
2024 |
TRAFO OIL IMMERSED 1.000 KVA |
2 |
|
PT. DUTA PERSADA POWER |
450 |
POWERPLANT |
PLTD PLN NUSA DAYA |
2024 |
TRAFO OIL IMMERSED 2.000 KVA |
4 |
|
PT. KINDEN INDONESIA |
451 |
INDUSTRY |
NARUMI MANUFACTURING INDONESIA, PROJECT NO: E1023186 |
2024 |
TRAFO OIL IMMERSED 800 KVA |
1 |
|
PT. KINDEN INDONESIA |
452 |
INDUSTRY |
NARUMI MANUFACTURING INDONESIA, PROJECT NO: E1023186 |
2024 |
TRAFO OIL IMMERSED 500 KVA |
1 |
|
PT. MULTI TEKNIK ENGINEERING |
453 |
INDUSTRY |
PABRIK KAIN PT. GAJAH PUTIH ELASTIC |
2024 |
TRAFO OIL IMMERSED 1.000 KVA |
1 |
|
PT. SURYA CITRA INTI SEMESTA |
454 |
INDUSTRY |
PABRIK TEKSITIL - RIAU |
2024 |
TRAFO OIL IMMERSED 630 KVA |
1 |
|
PT. MEDIA TELEMATIKA JAYA |
455 |
COMMERCIAL BUILDING |
PEKERJAAN UMUM RUSUN DOSEN SEMARANG |
2024 |
TRAFO OIL ESTER SYNTHETIC 400 KVA |
1 |
|
PT. LS ELECTRIC INDONESIA |
456 |
POWERPLANT |
SPACE TECHNOLOGY - PLTD LOMBOK |
2024 |
TRANSFORMER MINERAL OIL TYPE 1.600 KVA |
1 |
|
PT. KARYA MAKMUR BAHAGIA |
457 |
INDUSTRY |
PABRIK KELAPA SAWIT - KALIMANTAN (MIGRASI PLN DI KTWM & GMKM |
2024 |
TRAFO OIL IMMERSED 1.000 KVA OLTC MR GERMANY |
1 |
|
PT. BUMITAMA GUNAJAYA ABADI |
458 |
INDUSTRY |
PABRIK KELAPA SAWIT - KALIMANTAN (MIGRASI PLN DI KTWM & GMKM |
2024 |
TRAFO OIL IMMERSED 1.000 KVA OLTC MR GERMANY |
1 |
|
PT. PLN MANDAU CIPTA TENAGA NUSANTARA |
459 |
OIL & GAS |
PROJECT AC PCR - PERTAMINA DURI |
2024 |
TRANSFORMER FOR AIR CONDITIONER POWER CONTROL ROOM (PCR);TYPE; DRY;30KVA |
1 |
|
PT. MAJU DAYA UNGGUL |
460 |
OIL & GAS |
GEOTHERMAL DIENG |
2024 |
ZIG ZAG TRAFO 30 KVA |
1 |
|
PT. LS ELECTRIC INDONESIA |
461 |
INDUSTRY |
DONGSUNG CHEMICAL - KARAWANG |
2024 |
TRAFO OIL IMMERSED 1.000 KVA OCTC |
2 |
|
PT. LS ELECTRIC INDONESIA |
462 |
INDUSTRY |
DONGSUNG CHEMICAL - KARAWANG |
2024 |
TRAFO OIL IMMERSED 2.000 KVA |
1 |
|
PT. ANDALAS PETROLEUM SERVICES |
463 |
INDUSTRY |
BUMI SIAK PUSAKO |
2024 |
DISTRIBUTION TRANSFORMER 50KVA |
2 |
|
PT. LS ELECTRIC INDONESIA |
464 |
INDUSTRY |
PROJECT. ILJIN |
2024 |
TRANSFORMER MINERAL OIL IMMERSED TYPE 3 PHASE, 630KVA |
1 |
|
PT. LS ELECTRIC INDONESIA |
465 |
INDUSTRY |
PROJECT. ILJIN |
2024 |
TRANSFORMER MINERAL OIL IMMERSED 800KVA |
1 |
|
PT. LS ELECTRIC INDONESIA |
466 |
INDUSTRY |
PROJECT. ILJIN |
2024 |
TRANSFORMER MINERAL OIL IMMERSED 300KVA |
1 |
|
PT. WENANG PERKASA ABADI |
467 |
INDUSTRY |
PROJECT PALU |
2024 |
TRANSFORMATOR; 800 KVA |
1 |
|
CV. SAMUDERA JAYA ELEKTRIK |
468 |
INDUSTRY |
PT. SANSAN SAUDARATEX JAYA - PABRIK TEKSTIL |
2024 |
TRAFO OIL IMMERSED 1600KVA |
1 |
|
PT. SUMBER BUDI SAKTI |
469 |
INDUSTRY |
PROJECT. RANGKASBITUNG |
2024 |
TRANSFORMER OIL IMMERSED TYPE 630KVA |
1 |
|
PT. PLN (PERSERO) UP2D JAWA TENGAH DAN D.I YOGYAKARTA |
470 |
BUMN |
PENGADAAN TRAFO PS GI SPEK KHUSUS 22KV-400V |
2024 |
Trafo 100 KVA 22 kV - 400 V, Ynyn0, 3 phase |
14 |
|
PT. LS ELECTRIC INDONESIA |
471 |
COMMERCIAL BUILDING |
REHABILITASI DAN RENOVASI STADION DI PROVINSI JAWA TIMUR |
2024 |
TRAFO OIL ESTHER SYNTHETIC TYPE 650KVA |
1 |
|
PT. LS ELECTRIC INDONESIA |
472 |
COMMERCIAL BUILDING |
REHABILITASI DAN RENOVASI STADION DI PROVINSI JAWA TIMUR |
2024 |
TRAFO OIL ESTHER SYNTHETIC TYPE 400KVA |
1 |
|
PT. LS ELECTRIC INDONESIA |
473 |
COMMERCIAL BUILDING |
REHABILITASI DAN RENOVASI STADION DI PROVINSI JAWA TIMUR |
2024 |
TRAFO OIL ESTHER SYNTHETIC TYPE 400KVA |
1 |
|
PT. BORNEO MAJU JAYA |
474 |
MINING |
BATUBARA |
2024 |
TRANSFORMATOR DISTRIBUSI KAPASITAS 500KVA |
1 |
|
PT. LS ELECTRIC INDONESIA |
475 |
POWERPLANT |
PT. SPACE TECHNOLOGY NUSADAYA PLTD |
2024 |
TRANSFORMER MINERAL OIL TYPE 1500KVA |
1 |
|
PT. ADHI KARYA (PERSERO) TBK |
476 |
COMMERCIAL BUILDING |
PEMBANGUNAN GEDUNG BALAI DIKLAT KEUANGAN DENPASAR-BALI |
2024 |
TRAFO OIL IMMERSED TYPE STEP DOWN 630KVA |
1 |
|
PT. TUAH NAGA SAKTI |
477 |
COMMERCIAL BUILDING |
AKMIL MAGELANG |
2024 |
TRAFO OIL IMMERSED HERMATICALLY SEALED TOTALLY OIL FILLED TYPE 800KVA |
1 |
|
PT. TUAH NAGA SAKTI |
478 |
COMMERCIAL BUILDING |
AKMIL MAGELANG |
2024 |
TRAFO OIL IMMERSED HERMATICALLY SEALED TOTALLY OIL FILLED TYPE 400KVA |
1 |
|
PT. METSA |
479 |
COMMERCIAL BUILDING |
PASAR KOLPAJUNG |
2024 |
TRAFO OIL SYNTETIC ESTER TYPE 400KVA |
1 |
|
PT. GRAHA TAMBAK PINOTU |
480 |
MARINE SECTOR |
TAMBAK PALU |
2024 |
TRANSFORMATOR 2000 KVA |
1 |
|
PT. SENTOSA BATANGHARI MAKMUR |
481 |
MINING |
AMBI PT. SENTOSA BATANG HARI MAKMUR |
2024 |
TRANSFORMATOR 1000 KVA |
1 |
|
PT. LS ELECTRIC INDONESIA |
482 |
COMMERCIAL BUILDING |
STADION SURAJAYA LAMONGAN |
2024 |
TRANSFORMER SYNTHETIC ESTER OIL WITH THERMALLY UPGRADING PAPER TYPE 400KVA |
1 |
|
PT. ERASAKTI WIRAFORESTAMA |
483 |
MINING |
STOCKPILE BATUBARA& 5 CRUSHER TERMINAL 2 NIASO DI PKS 2 PT. EWF |
2024 |
TRANSFORMER OIL IMMERSED 200KVA STEP DOWN |
2 |
|
PT. GLOBAL ELEKTRIK SENTOSA |
484 |
INDUSTRY |
CV. SOLLU CITRA MUSLIM |
2024 |
TRAFO OIL IMMERSED TYPE 630KVA |
1 |
|
PT. LA TANSA PALEMBANG JAYA |
485 |
INDUSTRY |
BTS INDOSAT@PT.MEP MUBA PROPINSI SUMATERA SELATAN |
2024 |
TRAFO SPLN D3.002-1:2007 25 KVA 20/0.4KV OUTDOOR |
2 |
|
PT. HANSA PRATAMA ENGINEERING |
486 |
COMMERCIAL BUILDING |
OWJJ PLUIT |
2024 |
TRAFO OIL IMMERSED TYPE 630KVA |
1 |
|
PT. HANSA PRATAMA ENGINEERING |
487 |
COMMERCIAL BUILDING |
OWJJ PLUIT |
2024 |
TRAFO OIL IMMERSED TYPE 1000KVA |
1 |
|
PT. HANSA PRATAMA ENGINEERING |
488 |
COMMERCIAL BUILDING |
OWJJ PLUIT |
2024 |
TRAFO OIL IMMERSED TYPE 1250KVA |
1 |
|
PT. SELLON DATA INDONESIA |
489 |
COMMERCIAL BUILDING |
RUMAS SAKIT VERTIKAL PAPUA |
2024 |
TRAFO OIL ESTER SYNTHETIC TYPE 1250KVA |
1 |
|
PT. SELLON DATA INDONESIA |
490 |
COMMERCIAL BUILDING |
RUMAS SAKIT VERTIKAL PAPUA |
2024 |
TRAFO OIL ESTER SYNTHETIC TYPE 3150KVA |
2 |
|
PT. SELLON DATA INDONESIA |
491 |
COMMERCIAL BUILDING |
RUMAS SAKIT VERTIKAL PAPUA |
2024 |
TRAFO OIL ESTER SYNTHETIC TYPE STEP UP 2000KVA |
3 |
|
PT. HANEI INDONESIA |
492 |
INDUSTRY |
PT. SUGIURA INDONESIA, KARAWANG TIMUR |
2024 |
TRAFO OIL IMMERSED TYPE 400KVA |
1 |
|
PT. KARIANGAU POWER |
493 |
MINING |
PT. KARIANGAU POWER BALIKPAPAN |
2024 |
TRAFO OIL IMMERSED TYPE 200KVA |
2 |
|
PT. MITRA ENERGI PERKASA |
494 |
COMMERCIAL BUILDING |
BIOFARMA GEDUNG 34 BANDUNG |
2024 |
TRANSFORMATOR OIL ESTER SYNTHETIC TYPE 3500KVA |
1 |
|
PT. MITRA ENERGI PERKASA |
495 |
COMMERCIAL BUILDING |
BIOFARMA GEDUNG 34 BANDUNG |
2024 |
TRAFO OIL ESTER SYNTHETIC TYPE 3500KVA |
1 |
|
PT. MITRA ENERGI PERKASA |
496 |
COMMERCIAL BUILDING |
BIOFARMA GEDUNG 34 BANDUNG |
2024 |
TRAFO OIL ESTER SYNTHETIC TYPE 3500KVA |
1 |
|
PT. LS ELECTRIC INDONESIA |
497 |
PORT & AIRPORT |
bandara VVIP IKN |
2024 |
TRAFO OIL ESTER NATURAL TYPE 1250KVA |
1 |
|
PT. LS ELECTRIC INDONESIA |
498 |
PORT & AIRPORT |
bandara VVIP IKN |
2024 |
TRAFO OIL ESTER NATURAL TYPE 1600KVA |
3 |
|
PT. LS ELECTRIC INDONESIA |
499 |
PORT & AIRPORT |
bandara VVIP IKN |
2024 |
TRAFO OIL ESTER NATURAL TYPE 1600KVA |
2 |
|
PT. LS ELECTRIC INDONESIA |
500 |
PORT & AIRPORT |
bandara VVIP IKN |
2024 |
TRAFO OIL ESTER NATURAL TYPE 630KVA |
2 |
|
PT. FURUKAWA OPTICAL SOLUTIONS INDONESIA |
501 |
INDUSTRY |
PABRIK |
2024 |
TRAFO DRY NON RESIN ENCLOSURE TYPE 125KVA |
1 |
|
PT. REKSA DAYA BERJAYA |
502 |
POWERPLANT |
PENGADAAN TRAFO, ATS DAN AMF PLTA NGABEL |
2024 |
TRAFO OIL IMMERSED TYPE 30KVA |
1 |
|
KSO ADHI-SANGKURIANG |
503 |
COMMERCIAL BUILDING |
PEKERJAAN KONSTRUKSI TERINTEGRASI RANCANG BANGUN PRESISI 3, 10 LT. T.11.200 T.A 2024 |
2024 |
TRAFO OIL IMMERSED HERMATICALLY SEALED TOTALLY OIL FILLED TYPE 1000KVA |
1 |
|
PT. PERTAMINA HULU ROKAN |
504 |
OIL & GAS |
CALL-OFF ORDER (COO) TRANSFORMER (PAKET 1) |
2024 |
TRANSFORMER,3PH,300/300/300 kVA |
8 |
|
PT PP (PERSERO) Tbk DIVISI GEDUNG |
505 |
COMMERCIAL BUILDING |
BIOFARMA GEDUNG 37 |
2024 |
TRANSFORMATOR 2.1A Trafo Oil Ester Synthetic type 3500kVA; with Thermally Upgraded Paper; 3,3kV-400/230V; Dyn5; 3P; 50 Hz; Indoor; KNAN; OCTC 5 Tap; EDMCR; Midel 7131; Hermatically Sealed; IEC 60076 WINDING : CU-CU |
1 |
|
PT PP (PERSERO) Tbk DIVISI GEDUNG |
506 |
COMMERCIAL BUILDING |
BIOFARMA GEDUNG 37 |
2024 |
TRANSFORMATOR 2.1B Trafo Oil Ester Synthetic type 3500kVA; with Thermally Upgraded Paper; 20kV-400/230V; Dyn5; 3P; 50 Hz; Indoor; KNAN; OCTC 5 Tap; EDMCR; Midel 7131; Hermatically Sealed; IEC 60076 WINDING : CU-CU |
1 |
|
PT. DWI EKA BAKTI |
507 |
COMMERCIAL BUILDING |
GEDUNG BALI |
2024 |
TRAFO OIL IMMERSED TYPE 2500 KVA |
1 |
|
PT. BAKER HUGHES INDONESIA |
508 |
INDUSTRY |
PENGADAAN TRAFO SWASTA PEKANBARU |
2024 |
TRAFO OIL IMMERSED TYPE 550 KVA |
1 |
|
PT. ADHI KARYA (PERSERO) TBK |
509 |
POWERPLANT |
SUMBAWA-2 GAS ENGINE POWER PLANT 30MW |
2024 |
OIL IMMERSED TRANSFORMER TYPE, CONSERVATOR TYPE,11KV/0,4KV,2500KVA |
2 |
|
PT. ADHI KARYA (PERSERO) TBK |
510 |
POWERPLANT |
TOBELO PACKAGE GEPP TOBELO 10MW &TOBELO-2 |
2024 |
OIL IMMERSED TRANSFORMER TYPE, FREE BREATHING,CONSERVATOR TYPE,11KV/0,4KV,2500KVA |
2 |
|
PT. LS ELECTRIC INDONESIA |
511 |
POWERPLANT |
COAL FIRING POWER PLANT 2x5.5MW PLTU - KALIMANTAN |
2024 |
TRANSFORMATOR OIL IMMERSED TYPE 6500KVA |
2 |
|
PT. LS ELECTRIC INDONESIA |
512 |
POWERPLANT |
COAL FIRING POWER PLANT 2x5.5MW PLTU - KALIMANTAN |
2024 |
TRANSFORMATOR OIL IMMERSED TYPE 3000KVA |
1 |
|
PT. PLN (PERSERO) UP3 GORONTALO |
513 |
BUMN |
PELAKSANAAN PENGADAAN TRAFO KHUSUS : 3 UNIT 3P 50 KVA YZN5, 1 UNIT 3P 100 KVA YZN5 DAN 1 UNIT 160 KVA YZN5 PT PLN (PERSERO) UP3 GORONTALO TAHUN 2024 |
2024 |
TRANSFORMATOR; 3 PHASE, 50 KVA IEC 60076 |
3 |
|
PT. PLN (PERSERO) UP3 GORONTALO |
514 |
BUMN |
PELAKSANAAN PENGADAAN TRAFO KHUSUS : 3 UNIT 3P 50 KVA YZN5, 1 UNIT 3P 100 KVA YZN5 DAN 1 UNIT 160 KVA YZN5 PT PLN (PERSERO) UP3 GORONTALO TAHUN 2024 |
2024 |
TRANSFORMATOR; 3 PHASE, 100 KVA IEC 60076 |
1 |
|
PT. PLN (PERSERO) UP3 GORONTALO |
515 |
BUMN |
PELAKSANAAN PENGADAAN TRAFO KHUSUS : 3 UNIT 3P 50 KVA YZN5, 1 UNIT 3P 100 KVA YZN5 DAN 1 UNIT 160 KVA YZN5 PT PLN (PERSERO) UP3 GORONTALO TAHUN 2024 |
2024 |
TRANSFORMATOR; 3 PHASE, 160 KVA IEC 60076 |
1 |
|
PT. TML ENERGY |
516 |
COMMERCIAL BUILDING |
MALL PANAKUKANG MAKASSAR |
2024 |
TRAFO OIL IMMERSED TYPE 1250 KVA |
1 |
|
PT PLN (PERSERO) UP3 PADANG |
517 |
BUMN |
PENGADAAN TRAFO 200 KVA |
2024 |
TRANSFORMATOR; 3 PHASE, 200 KVA |
3 |
|
PT. KEKAL JAYA MAKMUR |
518 |
INDUSTRY |
PABRIK |
2024 |
TRAFO OIL IMMERSED TYPE 630KVA |
1 |
|
PT. MATRIX JAYA UNGGUL |
519 |
BUMN |
TEMPORARY PUSRI |
2024 |
TRAFO OIL IMMERSED TYPE 400KVA |
2 |
|
PT. MATRIX JAYA UNGGUL |
520 |
BUMN |
TEMPORARY PUSRI |
2024 |
TRAFO OIL IMMERSED TYPE 2500KVA |
1 |
|
CV. LATANSA JOGJAKARTA |
521 |
POWERPLANT |
SIMULATOR PLTD |
2024 |
TRAFO STEP UP/STEP DOWN, 3 PHASE, 10 KVA |
2 |
|
522 |
|||||||
PT. BESTINDO ANUGERAH |
523 |
INDUSTRY |
JAKARTA TIMUR |
2024 |
TRAFO OIL IMMERSED TYPE 800 KVA |
1 |
|
PT. MULTI TEKNIK ENGINEERING |
524 |
INDUSTRY |
PABRIK KAIN PT. GAJAH PUTIH GLOBAL |
2024 |
TRAFO OIL IMMERSED TYPE 1600KVA |
1 |
|
PT. BORNEO MAJU JAYA |
525 |
BUMN |
PDAM - KALIMANTAN |
2024 |
TRAFO OIL IMMERSED HERMETICALLY SEALED TYPE 800KVA |
1 |
|
PT. LS ELECTRIC INDONESIA |
526 |
COMMERCIAL BUILDING |
Proyek KSO Adhi Karya - APG MOBOX IKN |
2024 |
TRAFO OIL ESTHER SYNTHETIC W/ THERMALLY UPGRADING PAPER TYPE; 800KVA |
2 |
|
KSO ADHI - JAYA KONSTRUKSI |
527 |
COMMERCIAL BUILDING |
GEDUNG PERKANTORAN OTORITA IKN KALIMANTAN TIMUR |
2024 |
TRAFO OIL ESTER SYNTHETIC TYPE 1600KVA |
1 |
|
KSO ADHI - JAYA KONSTRUKSI |
528 |
COMMERCIAL BUILDING |
GEDUNG PERKANTORAN OTORITA IKN KALIMANTAN TIMUR |
2024 |
TRAFO OIL ESTER SYNTHETIC TYPE 630KVA |
1 |
|
PT. DIMAS AQNI PUTRA |
529 |
INDUSTRY |
PROJECT. MITRA BENING LESTARI |
2024 |
Trafo Oil Immersed type 630kVA; 20KV/400V; Dyn5; 50Hz; Indoor; ONAN; 3Phase; 5 tap; OCTC; Hermetically Sealed; IEC 60076; DMCR, Winding : AL-AL |
1 |
|
PT. INDOAUSTRA UTAMA |
530 |
COMMERCIAL BUILDING |
PROJECT. SUMBU KEBANGSAAN 2 IKN (ITEM 1 POS PEMADAM KEBAKARAN, ITEM 2 PLAZA YUDIKATIF & LEGISLATIF) |
2024 |
Trafo Oil Synthetic Ester type 400kVA; 20KV/400V; Dyn5; 50Hz; Indoor; KNAN; W/Thermal Upgrading Paper; 3Phase; 5 tap; OCTC; Hermetically Sealed; IEC 60076 Winding : CU-CU |
6 |
|
PT. INDOAUSTRA UTAMA |
531 |
COMMERCIAL BUILDING |
PROJECT. SUMBU KEBANGSAAN 2 IKN (ITEM 1 POS PEMADAM KEBAKARAN, ITEM 2 PLAZA YUDIKATIF & LEGISLATIF) |
2024 |
Trafo Oil Synthetic Ester type 315kVA; 20KV/400V; Dyn5; 50Hz; Indoor; KNAN; W/Thermal Upgrading Paper; 3Phase; 5 tap; OCTC; Hermetically Sealed; IEC 60076 Winding : CU-CU |
2 |
|
PT. LS ELECTRIC INDONESIA |
532 |
INDUSTRY |
PT. SK PLASMA - KARAWANG |
2024 |
Transformer Mineral Oil Type 1000kVA; 20kV/400V; Dyn5; Outdoor with HV LV Cable Box; ONAN; 3Phase; OCTC; DGPT-2; Hermetically Sealed; IEC 60076, Winding: AL-AL |
1 |
|
PT. LS ELECTRIC INDONESIA |
533 |
INDUSTRY |
PROJECT. NEW OPTIC - JABABEKA - CIKARANG |
2024 |
Transformer Mineral Oil type 1600kVA; 20kV/400-230V;Dyn5;50Hz; Indoor; ONAN; 3Phase; 5 Tap OCTC, Hermetically Sealed; IEC 60076 Winding: AL-AL |
2 |
|
PT. FURUKAWA OPTICAL SOLUTIONS INDONESIA |
534 |
INDUSTRY |
PROJECT. PABRIK |
2024 |
Transformator; 3 Phase, 25 kVA, 400 V - 200 V, 50 Hz, Dyn5, AN, Without Tap Changer, Dry Non Resin, Indoor with Enclosure, IEC 60076, Winding: AL-AL |
1 |
|
PT. BORNEO MAJU JAYA |
535 |
MINING |
BATUBARA-ADARO |
2024 |
TRANSFORMATOR DISTRIBUSI KAPASITAS 630, 20KV-400V, 3PHASE, 50HZ, ONAN, DYN5, INDOOR, HERMETICALLY SEALED, WINDING: AL-AL |
1 |
|
PT. RIAU SAMUDRA MANDIRI |
536 |
COMMERCIAL BUILDING |
PROJECT. LELANG - DINAS ENERGI SUMBER DAYA MINERAL PROVINSI RIAU |
2024 |
TRAFO DISTRIBUSI D3 20KV/400V 3 PHASE 100 KVA YZN5 OD |
1 |
|
KSO ADHI-HK-PENTA |
537 |
COMMERCIAL BUILDING |
KONSTRUKSI RANCANG DAN BANGUN PEMBANGUNAN SARANA PRASARANA PEMERINTAHAN IB DI IBU KOTA NEGARA |
2024 |
Trafo Oil Ester Synthetic type 400kVA; with Thermally Upgraded Paper; 20kV- 400V; Dyn5; 3P; 50 Hz; Indoor; KNAN; OCTC 5 Tap; e-DMCR Skema 2; Midel 7131; Hermatically Sealed; IEC 60076 WINDING : CU-CU |
1 |
|
PT. CITRA GOLDEN TUNGGAL |
538 |
INDUSTRY |
PROJECT: BANGKA |
2024 |
Trafo Oil Immersed type 630kVA;20kV/400V; Dyn5; 50Hz; Indoor; ONAN; OCTC 5 Tap; Hermatically Sealed; IEC 60076; Winding: CU-CU |
1 |
|
PT. CITRA GOLDEN TUNGGAL |
539 |
INDUSTRY |
PROJECT: BANGKA |
2024 |
Trafo Oil Immersed type 800kVA;20kV/400V; Dyn5; 50Hz; Indoor; ONAN; OCTC 5 Tap; Hermatically Sealed; IEC 60076; Winding: CU-CU |
1 |
|
PT. SUMATERA ENERGI LESTARI |
540 |
POWERPLANT |
PROJECT. PLTM ORDI HULU |
2024 |
Trafo Step Down, 3 Phase, 50kVA, 20kV- 400V, 50Hz, Dyn5, ONAN, Hermetically Sealed Totally Oil Filled, Off Load Tap Changer 5 Pos, Outdoor, IEC 60076, Winding: AL-AL |
1 |
|
PT. LS ELECTRIC INDONESIA |
541 |
INDUSTRY |
PT. KAITI GLOBAL INDONESIA, CIWARIGIN, CIREBON |
2024 |
Transformer Mineral Oil type 1600kVA; 20kV/400-230V;Dyn5;50Hz; Indoor; ONAN; 3Phase; 5 Tap OCTC, Hermetically Sealed; IEC 60076 Winding: AL-AL |
1 |
|
PT. PELAYANAN LISTRIK NASIONAL BATAM |
542 |
BUMN |
DISTRIBUTION LINE PENGADAAN TRANSFORMER MCC 45 KV UNTUK PLTG MPP 500 MW TERSEBAR |
2024 |
Transformer MCC 45kVA,Primary V:400/480V, Primary A:64.9/54.1A,Secondary V:230V, Secondary :112.9 A, 50/60 Hz, Ambient: 30o C,Duty: Cont, Ins Class:F- 155,Standards: BS EN 61558, BS EN60742, BS177, Dry, LxWxH = 480x230x410 |
1 |
|
PT. PELAYANAN LISTRIK NASIONAL BATAM |
543 |
BUMN |
DISTRIBUTION LINE PENGADAAN TRANSFORMER MCC 45 KV UNTUK PLTG MPP 500 MW TERSEBAR |
2024 |
Transformer MCC 45kVA,Primary V:400/480V, Primary A:64.9/54.1A,Secondary V:230V, Secondary :112.9 A, 50/60 Hz, Ambient: 30o C,Duty: Cont, Ins Class:F- 155,Standards: BS EN 61558, BS EN60742, BS177, Dry, LxWxH = 480x230x410 |
1 |
|
PT. PELAYANAN LISTRIK NASIONAL BATAM |
544 |
BUMN |
DISTRIBUTION LINE PENGADAAN TRANSFORMER MCC 45 KV UNTUK PLTG MPP 500 MW TERSEBAR |
2024 |
Transformer MCC 45kVA,Primary V:400/480V, Primary A:64.9/54.1A,Secondary V:230V, Secondary :112.9 A, 50/60 Hz, Ambient: 30o C,Duty: Cont, Ins Class:F- 155,Standards: BS EN 61558, BS EN60742, BS177, Dry, LxWxH = 480x230x410 |
1 |
|
PT. PELAYANAN LISTRIK NASIONAL BATAM |
545 |
BUMN |
DISTRIBUTION LINE PENGADAAN TRANSFORMER MCC 45 KV UNTUK PLTG MPP 500 MW TERSEBAR |
2024 |
Transformer MCC 45kVA,Primary V:400/480V, Primary A:64.9/54.1A,Secondary V:230V, Secondary :112.9 A, 50/60 Hz, Ambient: 30o C,Duty: Cont, Ins Class:F- 155,Standards: BS EN 61558, BS EN60742, BS177, Dry, LxWxH = 480x230x410 |
1 |
|
PT. PELAYANAN LISTRIK NASIONAL BATAM |
546 |
BUMN |
DISTRIBUTION LINE PENGADAAN TRANSFORMER MCC 45 KV UNTUK PLTG MPP 500 MW TERSEBAR |
2024 |
Transformer MCC 45kVA,Primary V:400/480V, Primary A:64.9/54.1A,Secondary V:230V, Secondary :112.9 A, 50/60 Hz, Ambient: 30o C,Duty: Cont, Ins Class:F- 155,Standards: BS EN 61558, BS EN60742, BS177, Dry, LxWxH = 480x230x410 |
2 |
|
PT. PLN (PERSERO) UP3 BANDENGAN |
547 |
BUMN |
PENGADAAN TRAFO 1.000 KVA |
2024 |
TRAFO DISTRIBUSI 20KV/400V 3 PHASE 1000 KVA DYN5 ID IEC 60076 |
1 |
|
PT. MAJU JAYA PRIMA PERKASA |
548 |
INDUSTRY |
STOCK |
2024 |
Trafo Oil Immersed type 630kVA; 3 Phase; 20kV/400V; Dyn5; 50 Hz; Indoor; ONAN; OCTC 5 Tap; Hermatically Sealed; IEC 60076; DMCR Winding : AL-AL |
1 |
|
PT. MAJU JAYA PRIMA PERKASA |
549 |
INDUSTRY |
STOCK |
2024 |
Trafo Oil Immersed type 1000kVA; 3 Phase; 20kV/400V; Dyn5; 50 Hz; Indoor; ONAN; OCTC 5 Tap; Hermatically Sealed; IEC 60076; DMCR Winding : AL-AL |
1 |
|
PT. PLN (PERSERO) UP3 LUBUK LINGGAU |
550 |
BUMN |
PT. PLN (PERSERO) |
2024 |
Trafo 3 Phase, 50 kVA, 20 kV - 400 V, 50 Hz, ONAN, Yzn5, Hermetically Sealed Totally Oil Filled, Off Load Tap Changer 9 Pos (14-14,75-15,5-16,25- 17-17,75- 18,5-19,25-20 kV), AL-AL Outdoor, (Losses mengacu SPLN D3.002-1: 2020) |
1 |
|
PT. PLN (PERSERO) UP3 LUBUK LINGGAU |
551 |
BUMN |
PT. PLN (PERSERO) |
2024 |
Trafo 3 Phase, 100 kVA, 20 kV - 400 V, 50 Hz, ONAN, Yzn5, Hermetically Sealed Totally Oil Filled, Off Load Tap Changer 9 Pos (14-14,75-15,5-16,25- 17-17,75- 18,5-19,25-20 kV), AL-AL Outdoor, (Losses mengacu SPLN D3.002-1: 2020 |
1 |
|
PT. PLN (PERSERO) UP3 LUBUK LINGGAU |
552 |
BUMN |
PT. PLN (PERSERO) |
2024 |
Trafo 3 Phase, 160 kVA, 20 kV - 400 V, 50 Hz, ONAN, Yzn5, Hermetically Sealed Totally Oil Filled, Off Load Tap Changer 9 Pos (14-14,75-15,5-16,25- 17-17,75- 18,5-19,25-20 kV), AL-AL Outdoor, (Losses mengacu SPLN D3.002-1: 2020 |
1 |
|
PT. PLN (PERSERO) UP3 LUBUK LINGGAU |
553 |
BUMN |
PT. PLN (PERSERO) |
2024 |
Trafo 3 Phase, 250 kVA, 20 kV - 400 V, 50 Hz, ONAN, Dyn5, Hermetically Sealed Totally Oil Filled, Off Load Tap Changer 9 Pos (14-14,75-15,5-16,25- 17-17,75- 18,5-19,25-20 kV), AL-AL Outdoor, (Losses mengacu SPLN D3.002-1: 2020 |
1 |
|
PT. SWEET GREENS INDONESIA |
554 |
COMMERCIAL BUILDING |
GREEN HOUSE - PURWAKARTA |
2024 |
Trafo Oil Immersed type 1250KVA;20kV/0,4KV; Dyn5;3P; 50Hz; Indoor; Bushing; ONAN; HermeticallySealed Winding : AL-AL |
1 |
|
PT. SENTRA KARYA CAHAYA RAYA |
555 |
MARINE SECTOR |
TAMBAK UDANG |
2024 |
Trafo oil immersed 3 Phase, 250 kVA, 20 kV - 400 V, 50 Hz, ONAN, Dyn5, Hermetically Sealed Totally Oil Filled, Off Load Tap Changer 9 Pos (14-14,75-15,5- 16,25- 17-17,75-18,5-19,25-20 kV), Outdoor, Winding: AL-AL |
2 |
|
PT. BAKER HUGHES INDONESIA |
556 |
INDUSTRY |
PENGADAAN TRAFO SWASTA PEKANBARU |
2024 |
Trafo oil Immersed Hermetically Sealed with N2 Sealed type 550kVA; 0,48kV/1,12-2,4kV (Delta Delta); 1,94-4, 157kV (wye); dD0 & dYn1; 60Hz; Outdoor;ONAN;3 Phase; OCTC 25 TAPS;K- Factor K4;IEEEC57.12.00(Drawing no.A61D11Y08H5CC1) Winding:CU-CU |
2 |
|
PT. BAKER HUGHES INDONESIA |
557 |
INDUSTRY |
PENGADAAN TRAFO SWASTA KUALO MUDO-KULIM KM.6 RIAU |
2024 |
Trafo oil Immersed Hermetically Sealed with N2 Sealed type 260kVA; 0,48kV/1,1- 2,2kV (Delta Delta); 1,905-3,811kV (wye); dD0 & dYn1;60Hz;Outdoor;ONAN;3 Phase;OCTC 25 TAPS;K-Factor K4; IEEEC57.12.00(Drawing no. A14D11Y08H5CC1)Winding:CU-CU |
1 |
|
PT. MAJU JAYA PRIMA PERKASA |
558 |
INDUSTRY |
PROJECT. KALIMANTAN |
2024 |
Trafo Oil Immersed type 1500kVA; 20KV/400V; Dyn5; 50Hz; Outdoor; ONAN; 3Phase; OCTC 5 tap; Hermetically Sealed; IEC 60076; DMCR, Winding: AL-AL |
1 |
|
PT. MULTI TEKNIK ENGINEERING |
559 |
INDUSTRY |
PT. ALASMAS BERKAT UTAMA PABRIK SEPATU |
2024 |
Trafo Oil Immersed type 2500kVA; 20KV/400V; Dyn5; 50Hz; Indoor; ONAN; 3Phase; 5 tap; OCTC; DGPT-2. Hermetically Sealed; IEC 60076. Winding : CU-CU |
1 |
|
PT. ATEKINDO |
560 |
COMMERCIAL BUILDING |
TEMPORARY MICROSOFT (DATA CENTER) |
2024 |
Trafo Step down, 3 Phase, 630 kVA, 20 kV - 400 V, 50 Hz, Dyn5, ONAN, Hermetically sealed totally oil filled, Off Load Tap Changer 5 Pos, Outdoor, IEC 60076. Winding: AL-AL |
1 |
|
PT. MAJU TERANG GEMILANG |
561 |
AGRO INDUSTRY |
PT. WNL - KALTENG (PERKEBUNAN SAWIT) |
2024 |
Transformator Step down, 3 Ph, 200 kVA, 20 kV-400 V, Dyn5, ONAN, D3 Hermatically Sealled totally oil filled OCTC, AL-AL, Outdoor, SPLN D3 2007. Winding AL-AL |
2 |
|
PT. BINA TEKNIK CIPTAMANDIRI |
562 |
INDUSTRY |
GENSET BENGKALIS RIAU |
2024 |
Transformer Step Up, 3 Phase, 1500 kVA, 480 V - 13.2 Kv, 60 Hz, YNd11, ONAN, AL-AL, Hermetically Sealed Totally Oil Filled with Corrugated Radiator, Off Load Tap Changer 5 Pos, Indoor/Outdoor, IEC 60076. |
1 |
|
PT. BINA TEKNIK CIPTAMANDIRI |
563 |
INDUSTRY |
GENSET BENGKALIS RIAU |
2024 |
Transformer Step Up, 3 Phase, 1500 kVA, 480 V - 4,16 Kv, 60 Hz, YNd11, ONAN, AL-AL, Hermetically Sealed Totally Oil Filled with Corrugated Radiator, Off Load Tap Changer 5 Pos, Indoor/Outdoor, IEC 60076. |
1 |
|
PT. PRECISION PIPE INDONESIA |
564 |
INDUSTRY |
PROJECT. PULAU BATAM |
2024 |
Transformator 3 Phase; 2400 kVA; 20kV - 400V; 50 Hz; Dyn 11; ONAN; Hermetically sealed totally oil filled with Corrugated Radiator; Off Load tap Charger 5 Pos; lndoor; Protection device DMCR;IEC 60O76. Winding: CU-CU |
2 |
|
PT. PRECISION PIPE INDONESIA |
565 |
INDUSTRY |
PROJECT. PULAU BATAM |
2024 |
Transformator 3 Phase; 2250kVA; 20 kV - 660 V, 50 Hz; Dyn 11, ONAN; Hermetically sealed totally oil filled with Corrugated Radiator; Off Load tap Charger 5 Pos; lndoor; Protection device DMCR;IEC 60076. Winding: CU-CU |
1 |
|
PT. PRECISION PIPE INDONESIA |
566 |
INDUSTRY |
PROJECT. PULAU BATAM |
2024 |
Transformator 3 Phase; 1250kVA; 20 kV - 400V; 50 Hz; Dyn 11; ONAN; Hermetically sealed totally oil filled with Corrugated Radiator; Off Load tap Charger 5 Pos; lndoor; Protection device DMCR;IEC 60076. Winding: CU-CU |
1 |
|
PT. PRECISION PIPE INDONESIA |
567 |
INDUSTRY |
PROJECT. PULAU BATAM |
2024 |
Transformator 3 Phase; 630kVA; 20 kV - 400V; 50 Hz; Dyn 11; ONAN; Hermetically sealed totally oil filled with Corrugated Radiator; Off Load tap Charger 5 Pos; lndoor; Protection device DMCR;IEC 60076. Winding: CU-CU |
1 |
|
PT. HORAS BANGUN PERSADA |
568 |
MINING |
PENGASPALAN JALAN CRUSHER DAN AMP DI JANTHO |
2024 |
Transformator; 3 Phase, 630 kVA, 20 kV - 400 V, 50 Hz, Dyn5, ONAN, Cu-Cu, Off- Load Tap Changer 5 Pos, Hermetically Sealed Totally Oil Filled, Outdoor, IEC 60076 |
1 |
|
PT. LA TANSA PALEMBANG JAYA |
569 |
COMMERCIAL BUILDING |
PROJECT. PROV. BABEL KOTA TOBOALI |
2024 |
TRAFO SPLN D3.002-1:2007 25 KVA 20/0,4KV OUTDOOR |
1 |
|
PT. MERGE MINING INDUSTRI |
570 |
MINING |
TAMBANG BATU BARA PT MARGE MINING INDUSTRI |
2024 |
Transformator Step Down, 2500 kVA, 20 kV - 10.5 kV, Dyn5, On Load Tap Changer, Trafo German MR 17 Pos ( 15- 21 kV, 360 V/Step), Winding: AL-AL |
1 |
|
PT. SENTRA KARYA CAHAYA RAYA |
571 |
INDUSTRY |
SAMARINDA |
2024 |
Transformator 630 kVA, 24/20KV 400/231V, Dyn5, 50 HZ, 3P, ONAN. Proteksi : Integrated Safety Device. Winding: CU-CU |
1 |
|
PT. TOTAL GRAHA DUNIA KONSTRUKSI |
572 |
COMMERCIAL BUILDING |
PIK2 PT PUSAT AUTOMOTIF INDONESIA |
2024 |
Trafo Oil Immersed Type 630 KVA; 20kV/400V Dyn5 50Hz, ONAN; 3 Phase 5 Tap; DGPT-2. Hermetically Sealed; Indoor, IEC 60076. Winding: AL-AL |
1 |
|
PT. PLN (PERSERO) UP3 PAMEKASAN |
573 |
BUMN |
PENGADAAN UNDER VOLTAGE STABILIZER 50 KVA |
2024 |
3 Phase, 50 kVA, 20 kV - 400 V, 50 Hz, ONAN, Yzn5, Hermetically Sealed Totally Sealed Oil Filled, Off Load Tap Changer 9 Pos (14-14,75-15,5-16,25-17-17,75- 18,5-19,25-20 kV) AL-AL, Outdoor, IEC 60076 (Losses mengacu SPLN D3.002-1 : 2020 |
7 |
|
PT. EMP ENERGI RIAU |
574 |
OIL AND GAS |
PENGADAAN TRAFO DISTRIBUSI |
2024 |
Step Down, 3 Phase, 2500 kVA, 13,8 kV - 480 V, 60 Hz, Dyn5, ONAN, Hermetically Sealed with Conservator & Radiator Corrugated, Off Load Tap Changer 5 Pos, CU-CU, Outdoor. IEC 60076. Winding: CU- CU |
1 |
|
PT. EMP ENERGI RIAU |
575 |
OIL AND GAS |
PENGADAAN TRAFO DISTRIBUSI |
2024 |
Step Up, 3 Phase, 300 kVA, 480 V - 13,8 kV, 60 Hz, Dyn7, ONAN, Hermetically Sealed with Conservator & Radiator Corrugated, Off Load Tap Changer 5 Pos, CU-CU, Outdoor, IEC 60076. Winding: CU- CU |
1 |
|
PT. EMP ENERGI RIAU |
576 |
OIL AND GAS |
PENGADAAN TRAFO DISTRIBUSI |
2024 |
Step Up3, 3 Phase, 2450 kVA, 2,4 kV - 13,8 kV, 60 Hz, Dyn5, ONAN, Hermetically Sealed with Conservator & Radiator Corrugated, Off Load Tap Changer 5 Pos, CU-CU, Outdoor, IEC 60076. Winding: CU-CU |
1 |
|
PT. EMP ENERGI RIAU |
577 |
OIL AND GAS |
PENGADAAN TRAFO DISTRIBUSI |
2024 |
Step Down, 3 Phase, 300 kVA, 380 V - 20 kV, 50 Hz, Dyn5, ONAN, Hermetically Sealed with Conservator & Panel Radiator, Off Load Tap Changer 5 Pos, CU-CU, Outdoor, IEC 60076. Winding: CU-CU |
1 |
|
PT. LS ELECTRIC INDONESIA |
578 |
INDUSTRY |
SPACE TECH |
2024 |
Trafo Oil Immersed Type 2500 kVA 20 kV/400V Dyn5, 50Hz, Outdoor, ONAN 3 Phase, 5 Tap OCTC, Hermetically Sealed, IEC 60076, DMCR. Winding: CU-CU |
1 |
|
PT. BINA TEKNIK CIPTAMANDIRI |
579 |
INDUSTRY |
BENGKALIS RIAU |
2024 |
Step Down, 3 Phase, 1000 kVA, 13.2 kV - 480 V, 60Hz, Dyn5, ONAN, AL-AL, Hermetically Sealed Totally Oil Filled and Corrugated Radiator, Off Load Tap Changer 5 Pos, Indoor/Outdoor, IEC 60076. Winding: AL-AL |
1 |
|
PT. BINA TEKNIK CIPTAMANDIRI |
580 |
INDUSTRY |
BENGKALIS RIAU |
2024 |
Step Down, 3 Phase, 1250 kVA, 4.16 kV - 480 V, 60 Hz, Dyn5, ONAN, AL-AL, Hermetically Sealed Totally Oil Filled and Corrugated Radiator, Off Load Tap Changer 5 Pos, Indoor/Outdoor, IEC 60076. Winding: AL-AL |
1 |
|
PT. LS ELECTRIC INDONESIA |
581 |
COMMERCIAL INDUSTRY |
RSUD SEPAKU KALIMANTAN |
2024 |
Transformator Synthetic Ester Oil with Thermal Upgrading Paper Type 3 Phase, 630 kVA, 20kV - 400V, 50 Hz, Dyn5, KNAN, Indoor Termination, Hermetically Sealed Totally Oil FIlled, Off Load Tap Changer 5 Pos, DGPT-2, IEC 60076. Winding: CU-CU |
1 |
|
ADHI-HK KSO |
582 |
COMMERCIAL INDUSTRY |
MASJID IKN |
2024 |
Trafo Oil Ester Synthetic Type 1250 kVA; with Thermally Upgraded Paper; 20kV- 400V; Dyn5; 3P; 50 Hz; Indoor; KNAN; OCTC 5 Tap; DMCR; Midel 7131; Hermatically Sealed; IEC 60076. Winding: CU-CU |
2 |
|
PT. PERTAMINA HULU ENERGI ONWJ |
583 |
OIL AND GAS |
PENGADAAN PROCUREMENT TRANSFORMER OSF 2024 |
2024 |
Step Down Trafo Oil Immersed Hermetically Sealed Type 1000 kVA; 13,8 kV/0,48 V; Dyn1; 3P; 60 Hz; Outdoor; ONAN; OCTC (5 Tap, 345 V/STAP); IEEEC57.12.00 Winding: CU-CU |
1 |
|
PT. PERTAMINA HULU ENERGI ONWJ |
584 |
OIL AND GAS |
PENGADAAN PROCUREMENT TRANSFORMER OSF 2024 |
2024 |
Step Down Trafo Oil Immersed Hermetically Sealed Type 750 kVA; 4,16kV/0,48; Dyn1; 3P; 60 Hz; Outdoor: ONAN; OCTC (5 Tap, 105 V/STAP); IEEEC57.12.00 Winding: CU-CU |
1 |
|
PP KSO RSUD AM PARIKESIT |
585 |
COMMERCIAL INDUSTRY |
RSUD A.M. PARIKESIT |
2024 |
Trafo Oil Immersed Hermetically Sealed Type 2000 kVA; 20kV-400V; Dyn5; 3P; 50 Hz; Indoor; ONAN; OCTC 5 Tap; DMCR; IEC 60076. Winding: CU-CU |
1 |
|
PT PLN (Persero) UP3 BULUNGAN |
586 |
BUMN |
PENGADAAN UNIT GARDU BERGERAK (UGB) 250 KVA TRAFO ISOLASI 2024 |
2024 |
UGB TRAFO ISOLASI 250 KVA. MATERIAL TAMBAHAN: ISOLATION TRANSFORMER, 3 PHASE, 250 KVA, 400 V, 50 Hz, Dyn5, ONAN, HERMETICALLY SEALED TOTALLY OIL FILLED, WITHOUT TAP CHANGER, OUTDOOR WITH PORCELAIN BUSHING, PROTECTION DEVICE DMCR, IEC 60076. |
1 |
|
PT. KURNIA TUNGGAL NUGRAHA SHIPYARD |
587 |
INDUSTRY |
PROJECT. DOCK NIASO PT. KTNS |
2024 |
Trafo Oil Immersed 400KVA 20 kV / 400 V, Dyn5, 50 Hz, Outdoor, ONAN, 3 Phase 5 Tap, DMCR, Hermetically Sealed, IEC 60076. Winding: AL-AL |
2 |
|
PT. KINDEN INDONESIA |
588 |
INDUSTRY |
PROJECT PT NBC INDONESIA |
2024 |
Transformator; 3 Phase, 315 kVA, 20 kV - 200 V, 50 Hz, Dyn5, ONAN, Cu-Cu, Off- Load Tap Changer 5 Pos, Hermetically Sealed Totally Oil Filled, Outdoor, IEC 60076 |
1 |
|
PT MAYORA INDAH Tbk |
589 |
INDUSTRY |
PROJECT. PABRIK MAYORA WAFER JAYANTI 3 |
2024 |
TRANSFORMER OIL TYPE 3000KVA, 20KV/400V, DYN5, 50HZ, 3P, ONAN, INDOOR DGPT 2 (EXCLUDE COOPER LINK), WINDING : CU-CU |
1 |
|
PT. PLN (Persero) UP3 SAMARINDA |
590 |
BUMN |
PENGADAAN TRAFO AVR (ON LOAD TAP CHANGER) 4.000 KVA PADA PENYULANG KTB 1 ULP KOTA BANGUN PT PLN (PERSERO) UP3 SAMARINDA |
2024 |
Trafo AVR, 3 Phasa, 4000 KVA, 20 kV - 20 kV, 50 Hz, YNa0, ONAN, On Load Tap Changer, IEC 60076. Winding CU-CU |
1 |
|
PT. PLN (PERSERO) UP3 MADURA |
591 |
BUMN |
PENGADAAN UNDER VOLTAGE STABILIZER 50 KVA |
2024 |
Under Voltage Stabilizer 50 KVA |
7 |
|
PT. SAPTA MANUNGGAL KARYA |
592 |
POWERPLANT |
PLTD |
2024 |
Transformator Step 160 kVA; 3 Phase; 400 V - 20 kV; 50 Hz; YNd5, ONAN, Off- Load Tap Changer 5 Pos; Hermetically Sealed; Totally Oil Filled; Outdoor; SPLN D3.002-1: 2007. Winding: CU-CU |
1 |
|
PT. DUTA SURYA ARCANA |
593 |
INDUSTRY |
PUPUK KUJANG, GROUP PUPUK INDONESIA |
2024 |
Trafo Oil Immersed Type 400 kVA; 460V/400V; Dyn11; 50Hz; Outdoor; ONAN; 3 Phase; 5 Tap; OCTC; Hermetically Sealed; IEC 60076. Winding: CU-CU |
1 |
|
PT. DUTA SURYA ARCANA |
594 |
INDUSTRY |
PUPUK KUJANG, GROUP PUPUK INDONESIA |
2024 |
Trafo Oil Immersed Type 750 kVA; 460V/400V; Dyn11; 50Hz; Outdoor; ONAN; 3 Phase; 5 Tap; OCTC; Hermetically Sealed; IEC 60076. Winding: CU-CU |
1 |
|
PT. PLN (PERSERO) UP3 MADURA |
595 |
BUMN |
TRAFO TAPPING KHUSUS |
2024 |
Transformator; 3 Phase, 100 kVA, 20 kV - 400 V, 50 Hz, Yzn5, ONAN, Al-Al, Off Load Tap Changer 9 Pos, Hermetically Sealed Totally Oil Filled, Outdoor, SPLN D3.002-1: 2020 |
5 |
|
PT. PLN (PERSERO) UP3 MADURA |
596 |
BUMN |
TRAFO TAPPING KHUSUS |
2024 |
Under Voltage Stabilizer 250 Kva |
2 |
|
PT. AYOE INDOTAMA TEXTILE |
597 |
INDUSTRY |
PABRIK TEXTILE BANDUNG |
2024 |
TRAFO OLI 200 KVA, 220V/380V, Dyn5, IEC. Winding: AL-AL |
1 |
|
PT. PLN (PERSERO) PUSAT SERTIFIKASI |
598 |
BUMN |
PENGADAAN TRANSFORMATOR 3 PHASE UNTUK PENGUJIAN KABUT GARAM TERMINASI KABEL LABORATORIUM TEGANGAN TINGGI |
2024 |
3 Phase, 40 kVA, 35 kV - 400 kV, 50Hz, YNyn0, ONAN, Hermetically Sealed Totally Oil Filled & Corrugated Radiator, Without Tap Changer, Outdoor, IEC 60076. Winding: CU-AL |
1 |
|
PT. BORNEO MAJU JAYA |
599 |
MINING |
TAMBANG BATUBARA |
2024 |
Transformator Hermetically Sealed 1000 kVA, 20kV - 400 V, 50Hz, Dyn5, ONAN, IEC, Indoor. Winding: AL-AL |
1 |
|
PT. BORNEO MAJU JAYA |
600 |
MINING |
TAMBANG BATUBARA |
2024 |
Transformator Hermetically Sealed; 400 kVA, 20kV - 400 V, 50Hz, Dyn5, ONAN, IEC, Indoor. Winding: AL-AL |
1 |
|
PT. MAJU TERANG GEMILANG |
601 |
INDUSTRY |
PABRIK KAIN BANTEN |
2024 |
Transformator; 3 Phase, 1000 kVA, 20 kV - 400 V, 50 Hz, Dyn5, ONAN, Off-Load Tap Changer 5 Pos, DMCR, Hermetically Sealed Totally Oil Filled, Indoor, IEC 60076. Winding: AL-AL |
1 |
|
KCNR SOLUTIONS SDN BHD |
602 |
EXPORT MALAYSIA - SOLAR PLANT |
KUALA KETIL, KEDAH, MALAYSIA |
2024 |
Earthing Transformer; 3 Phase, 300 kVA, 33 kV - 415 V, 50 Hz, ZNyn11, ONAN, Without Tap Changer, Hermetically Sealed with Conservator, Outdoor with Cable Box, IEC 60076. Winding: CU-CU |
1 |
|
PT. TRI SUMBER ELEKTRIKA |
603 |
INDUSTRY |
PABRIK PENGECATAN BODI MOBIL PURWAKARTA |
2024 |
Trafo Oil Immersed Step Down type 1000kVA; 20kV/400V; Dyn5; 50Hz; Indoor; ONAN; 3 Phase; 5 Tap; OCTC; Hermetically Sealed; DMCR; IEC 60076. Winding: AL-AL |
1 |
|
PT. LS ELECTRIC INDONESIA |
604 |
INDUSTRY |
PT. YISU / PT KNT-21 CIKARANG. |
2024 |
Trafo Oil Immersed Hermetically Sealed type 2000 kVA; 20kV/400V; Dyn5; 50Hz; Indoor/Outdoor; ONAN; 3 Phase; 5 Tap; Off Load Tap Changer 5 Pos; IEC 60076. Winding: AL-AL |
1 |
|
PT. LS ELECTRIC INDONESIA |
605 |
COMMERCIAL BUILDING |
ASRAMA DAN MASJID STAN |
2024 |
Transformator Ester Synthetic Oil Type 1000kVA; W/ Thermal Upgrading Paper; 20kV/400V; Dyn5; 50Hz; Indoor; KNAN; OCTC 5 Tap; DMCR Transformer Safety Device; Hermetically Sealed; IEC 60076. Winding: CU-CU |
1 |
|
PT. PERTAMINA HULU ROKAN |
606 |
OIL AND GAS |
CALL-OFF ORDER (COO) TRANSFORMER (PAKET 1) |
2024 |
TRANSFORMER,3PH,300/300/300 kVA,13200V/480/960/1100V,PAD MOUNTED,5 TAPS(2X5% ABOVE&2X5% BELOW),60HZ,DYN1,IEEE,IMPEDANCE:4% , HV BILL:110KV,LV BILL:30KV,NO LOAD LOSSES:600 W, TOTAL LOSSES:2900 W, BUSHING POSITION HVTAB:TOP, LVTAB:SIDE,CU-CU |
72 |
|
PT. TUAH NAGA SAKTI |
607 |
COMMERCIAL BUILDING |
UNIVERSITAS PERTAHANAN SENTUL |
2024 |
Trafo Step Down, 3 Phase, 2000 kVA, 20kV/400V, 50Hz, Dyn5, ONAN, Hermetically Sealed Totally Oil Filled, Off Load Tap Changer 5 Pos, Indoor, Proteksi DMCR, IEC 60076. Include MV Bushing 70 mm2. Winding: CU-CU |
2 |
|
PT. MAHAMERU SINERGI INDONESIA |
608 |
AGRO INDUSTRY |
PROJECT PT. KTWM |
2024 |
Trafo Oil Immersed type 50 kVA; 20kV/400V; Dyn5; 50Hz; Outdoor; ONAN; OCTC 5 Tap; Hermetically Sealed; IEC 60076. Winding: CU-CU |
2 |
|
PT. MAHAMERU SINERGI INDONESIA |
609 |
AGRO INDUSTRY |
PROJECT PT. KTWM |
2024 |
Trafo Oil Immersed type 250 kVA; 20kV/400V; Dyn5; 50Hz; Outdoor; ONAN; OCTC 5 Tap; Hermetically Sealed; IEC 60076. Winding: CU-CU |
1 |
|
PT. MAHAMERU SINERGI INDONESIA |
610 |
AGRO INDUSTRY |
PROJECT PT. KTWM |
2024 |
Trafo Oil Immersed type 400 kVA; 20kV/400V; Dyn5; 50Hz; Outdoor; ONAN; DMCR; OCTC 5 Tap; Hermetically Sealed; IEC 60076. Winding: CU-CU |
1 |
|
PT. SURYA ENERGI INDOTAMA |
611 |
POWERPLANT |
EPC PLTS APUNG IGEO - PLTA BARITO 2024 |
2024 |
Trafo 2 Oil Immersed; Outdoor 500 kVA 0.8/0.38; Dyn11. Winding: CU-CU |
1 |
|
PT. PLN MANDAU CIPTA TENAGA NUSANTARA |
612 |
BUMN |
PENYEDIAAN TRAFO DISTRIBUSI 630 KVA |
2024 |
Transformator Oil Immersed Type 630 kVA; 20kV/400V; 3P; Dyn5; 50Hz; ONAN; OCTC; 5Tap; Hermetically Sealed; Outdoor, IEC 60076. Winding: AL-AL |
2 |
|
PT. HIDUP BARU ELECTRIC |
613 |
COMMERCIAL BUILDING |
RS AMBON |
2024 |
Transformer Mineral Oil Type 630 kVA; 20kV/400V; Dyn5; 50Hz; Outdoor; ONAN; OCTC 5 Tap; DMCR Transformer Safety Device; Hermetically Sealed; IEC 60076. Winding CU-CU |
1 |
|
PT. ATEKINDO |
614 |
COMMERCIAL BUILDING |
DATA CENTER MICROSOFT TEMPORARY |
2024 |
Trafo Oil Immersed Step Down type 500kVA; 20kV/400V; Dyn5; 50Hz; Outdoor; ONAN; 3 Phase; 5 Tap; OCTC; Hermetically Sealed; DMCR; IEC 60076. Winding: AL-AL |
1 |
|
PT. PRIMA KARUNIA KREASI |
615 |
INDUSTRY |
TENGGARONG KALIMANTAN TIMUR |
2024 |
TRAFO OIL IMMERSED HERMETICALLY SEALED TYPE 2000 KVA; 20kV/400V; Dyn5; 50Hz; Indoor; HV PIB: ONAN; 3 Phase; 5 Tap; Off Load Tap Changer; 5 Pos; DMCR. Winding: CU-CU |
1 |
|
PT. ATW SOLAR INDONESIA |
616 |
POWERPLANT |
PLTS MEDAN |
2024 |
Trafo Oil Immersed Step Up type 2500kVA; Beban Harmonic K-4; 400V/20kV; Dyn5; 50Hz; Outdoor; ONAN; 3 Phase; 5 Tap; OCTC; Hermetically Sealed; IEC 60076. Winding: AL-AL |
2 |
|
PT. INDAH KARYA NUSRAINDO |
617 |
COMMERCIAL BUILDING |
SIRKUIT MANDALIKA |
2024 |
Trafo Oil Immersed type 160 kVA; 20kV/400V; Yzn5; 50Hz; Outdoor; Hermetically Sealed; SPLN D3 2020. Winding: AL-AL |
1 |
|
PT. KURNIA TUNGGAL NUGRAHA SHIPYARD |
618 |
INDUSTRY |
DOCK NIASO PT. KTNS |
2024 |
Trafo Oil Immersed 400KVA 20 kV / 400 V, Dyn5, 50 Hz, Outdoor, ONAN, 3 Phase 5 Tap, DMCR, Hermetically Sealed, IEC 60076. Winding: AL-AL |
1 |
|
CV SINAR ALAM ELEKTRIC |
619 |
BUMN |
PDAM KALIMANTAN |
2024 |
WELTRAF TRAFO OIL 3P; 100kVA; 20kV/400V; Yzn5; Outdoor; SPLN 2020. Winding: AL-AL |
2 |
|
CV SINAR ALAM ELEKTRIC |
620 |
BUMN |
PDAM KALIMANTAN |
2024 |
WELTRAF TRAFO OIL 3P; 50kVA; 20kV/400V; Yzn5; Outdoor; SPLN 2020. Winding: AL-AL |
1 |
|
PT. DATA INTEGRASI INTERNUSA |
621 |
INDUSTRY |
PT WHISTLER GARDEN |
2024 |
Transformer Oil Immersed type 400 kVA; 20kV/400V; 50Hz; Indoor; Dyn5; ONAN; 3Phase; 5 Tap; OCTC; Hermetically Sealed; IEC 60076; DMCR. Winding: AL-AL |
1 |
|
PT. LS ELECTRIC INDONESIA |
622 |
COMMERCIAL BUILDING |
UPR KIPP IKN |
2024 |
Transformer Natural Ester Oil with Thermal Upgrading Paper type 400 kVA; 20kV/400V: Dyn5; 50Hz; Indoor; KNAN; 3 Phase; 5 Tap OCTC; Hermetically Sealed; IEC 60076. Winding: CU-CU |
1 |
|
CV. ZALBI CAKRA MEGA |
623 |
COMMERCIAL BUILDING |
UNPAD JATINANGOR BANDUNG |
2024 |
Transformator Oil Immersed; 3 Phase type 630 kVA; 20kV/400 V; 50 Hz; Dyn5; ONAN; Off-Load Tap Changer 5 Pos; Hermetically Sealed Totally Oil Filled; DMCR; Indoor; IEC 60076. Winding: CU- CU |
1 |
|
PT. PLN (Persero) UP3 SAMARINDA |
624 |
BUMN |
PENGADAAN TRAFO TEGANGAN KHUSUS UNTUK PELANGGAN DENGAN KELUHAN TEGANGAN DROP |
2024 |
Transformator; 3 Phase, 50 kVA, 20 kV - 400 V, 50 Hz, Yzn5, ONAN, Off Load Tap Changer 9 Pos (14-14,75-15,5-16,25-17- 17,75-18,5-19,25-20 kV), Hermetically Sealed Totally Oil Filled, Outdoor, IEC 60076 (Losses SPLN 2020) Winding AL- AL |
4 |
|
PT. PLN (Persero) UP3 SAMARINDA |
625 |
BUMN |
PENGADAAN TRAFO TEGANGAN KHUSUS UNTUK PELANGGAN DENGAN KELUHAN TEGANGAN DROP |
2024 |
Transformator; 3 Phase, 100 kVA, 20 kV - 400 V, 50 Hz, Yzn5, ONAN, Off Load Tap Changer 9 Pos (14-14,75-15,5-16,25-17- 17,75-18,5-19,25-20 kV), Hermetically Sealed Totally Oil Filled, Outdoor, IEC 60076 (Losses SPLN 2020) Winding: AL- AL |
1 |
|
PT. MAJU JAYA PRIMA PERKASA |
626 |
AGRO INDUSTRY |
PKS KLK KALIMANTAN TENGAH |
2024 |
Trafo 3 Phase 630 kVA; 20kV - 400 V; 50Hz; Dyn5; ONAN; Hermetically Sealed Totally Oil Filled; On Load Tap Changer ex. MR Germany 17 Pos (21 kV - 13 kV, 500 V/Step), Indoor; Protection Device DMCR; IEC 60076. Winding: CU-CU |
1 |
|
PT. BINA TEKNIK CIPTAMANDIRI |
627 |
INDUSTRY |
BKSI - PULO GADUNG |
2024 |
Trafo Oil Immersed; Hermetically Sealed Type 2500 kVA; 20kV/400V; Dyn5; 50Hz; Indoor; ONAN; 3 Phase; 5 Tap; OCTC; IEC 60076. Winding: AL-AL |
1 |
|
PT. LS ELECTRIC INDONESIA |
628 |
INDUSTRY |
PT SUNINDO MANDIRI PERKASA |
2024 |
Transformator Oil Immersed type 500 kVA; 20 kV/400 V; Dyn5; 50 Hz; Indoor; ONAN; 3Phase; 5 Tap; Hermetically Sealed Totally Oil Filled; DMCR; IEC 60076. Winding: AL-AL |
1 |
|
PT. SURYA ABADI ELEKTRINDO |
629 |
COMMERCIAL BUILDING |
RSUD CEMPAKA PUTIH |
2024 |
Trafo Oil Immersed; Hermetically Sealed type 800 kVA; 20kV - 400 V; Dyn5; 50Hz; Outdoor/Indoor; ONAN; 3 Phase; 5 Tap; OCTC; IEC 60076. Winding CU-CU |
1 |
|
PT. LS ELECTRIC INDONESIA |
630 |
EXPORT |
EXPORT WOODEN CRATE, SEA WORTHY |
2024 |
Transformer Oil Immersed Type Step Down; 3 Phase; 12000 kVA; 24,9 kV - 4,16 kV; 60Hz; Dyn11; KNAN with Natural Ester Oil (FR3); Hermetically Sealed with N2 Sealed & Panel Radiator, Off Load Tap Changer 5 Pos Temperature Rise Oil/Winding 50/55K, Outdoor wi |
3 |
|
PT. LS ELECTRIC INDONESIA |
631 |
EXPORT |
EXPORT WOODEN CRATE, SEA WORTHY |
2024 |
Transformer Oil Immersed Type Step Down; 3 Phase; 2000 kVA; 4,16 kV - 480 V; 60Hz; Dyn11; KNAN with Natural Ester Oil; Hermetically Sealed with N2 Sealed & Panel Radiator; Off Load Tap Changer 5 Pos Temperature Rise Oil/Winding 50/55K, Outdoor with Cable |
4 |
|
PT. WENANG PERKASA ABADI |
632 |
COMMERCIAL BUILDING |
RSUD TRIKORA BANGGAI KEPULAUAN |
2024 |
Trafo Oil Immersed Hermetically Sealed type 400 kVA; 20kV/400V; Dyn5; 50Hz; Indoor; ONAN; 3 Phase; 5 Tap; OCTC; IEC 60076. Winding: AL-AL |
1 |
|
PT. BERKAH CIPTA PERSADA |
633 |
2024 |
Trafo Step Up; 3 Phase; 750kVA; 2,4kV- 2250-4500V; 60Hz; Dyn1; ONAN; Padmounted with N2 Sealed and Panel Radiator; Off Load Tap Changer 25 Pos; Outdoor; with HV/LV Cable Box; Radiator Valve 1 Set; Ansl C57.12; Hazardous Class; Class 1; Div 2; Group D. Win |
2 |
|||
PT. LS ELECTRIC INDONESIA |
634 |
INDUSTRY |
PROJECT CHANGSUNG |
2024 |
Trafo Oil Immersed type 500 kVA; 20kV400/231V; Dyn5; 50Hz; Indoor; ONAN; 3 Phase; 5 Tap; OCTC; Hermetically Sealed; IEC 60076; DMCR. Winding: AL-AL |
1 |
|
CV. GALAXI MEGA ELECTRIC |
635 |
COMMERCIAL BUILING |
BANK BRI MALANG |
2024 |
Trafo Oil Syntetic Ester Hermetically Sealed type 315 kVA; 20kV/400V; Dyn5; 50Hz; Indoor; KNAN, DMCR; 3 Phase; 5 Tap; OCTC; IEC 60076/ANSI (IEE) 57. Winding: CU-CU |
1 |
|
CV. ANDALAN MITRA SEJATI |
636 |
OIL AND GAS |
PROJECT: PT. SPR LANGGAK RIAU |
2024 |
Trafo Step Down; 3 Phase; 300kVA; 13,2kV-960V & 480 V; 60Hz; Dyn1; ONAN; Hermetically Sealed Totally Oil Filled and Corrugated Radiator; Off Load Tap Changer 5 Pos; Indoor/Outdoor. IEC 60076. Winding: CU-CU |
1 |
|
PT. WG - APIK KSO |
637 |
COMMERCIAL BUILDING |
HUNIAN PEKERJA KONSTRUKSI 2 IKN |
2024 |
Trafo Step Down; 3 Phase; 1000kVA; 20kV-400V; 50Hz; Dyn5; ONAN; Oil Immersed Hermetically Sealed; 5 Tap; OCTC; DMCR Transformer Safety Device; Indoor; IEC 60076. Winding: CU-CU |
2 |
|
PT. TRIMULYA DAYA UTAMA |
638 |
INDUSTRY |
PROJECT: CIANJUR |
2024 |
Trafo Oil Immersed Hermetically Sealed type 500kVA; 20kV/400; Dyn5; 50Hz; Outdoor; ONAN; OCTC; 5 Tap; IEC 60076; DMCR. Winding: AL-AL |
1 |
|
PT. LS ELECTRIC INDONESIA |
639 |
COMMERCIAL BUILDING |
POSCO CILEGON (COIL YARD at HSM) |
2024 |
Transformer Oil Immersed Type, Step Down; 3Phase; 3000kVA; 6 kV - 400 V; 50Hz; Dd0; ONAN; Hermetically Sealed Totally Oil Filled & Corrugated Radiator; Off Load Tap Changer 5 Pos; Outdoor with HV/LV Cable Box (Elephat Type); IEC 60076. Winding: CU-CU. |
1 |
|
ALLIANCE TECHNIC ENGINEER |
640 |
INDUSTRY |
PT. INSANSANDANG |
2024 |
Trafo Oil Immersed Hermetically Sealed Totally Oil FIlled type 1600kVA; 20kV/0,4kV; Dyn5; 50Hz; Indoor; ONAN; OCTC 5 Taps; DMCR Transformer Safety Device; IEC 60076. Winding: CU-CU |
1 |
|
PT. LS ELECTRIC INDONESIA |
641 |
INDUSTRY |
PJT WILDWOOD/UJT |
2024 |
Trafo Oil Immersed type 1600 kVA; 20kV/400V; Dyn5; 50Hz; Indoor; ONAN; 3Phase; 5 Tap; OCTC; Hermetically Sealed; IEC 60076; DMCR. Winding: AL-AL |
1 |
|
PT. MAJU TERANG GEMILANG |
642 |
INDUSTRY |
PABRIK KAYU-SAMARINDA |
2024 |
WELTRAF Trafo Oil Immersed 2500 kVA; 20kV-400V; Dyn5; 3 Phase; 50Hz; ISD+Keramik Bushing; ONAN. Winding: AL- AL |
1 |
|
PT. PLN (PERSERO) PUSAT PENELITIAN DAN PENGEMBANGAN KETENAGALISTRIKAN |
643 |
BUMN |
PLN PUSLITBANG |
2024 |
Transformator Low Losses + Ester Oil 100 kVA Spesifikasi: 100 kVA AMDT, Low No Load Losses, Low Load Losses, Ester Oil. Winding: AL-AL |
1 |
|
PT. WASKITA BETON PRECAST TBK. |
644 |
Terminal Peti Kemas Batu Ampar Batam |
Terminal Peti Kemas Batu Ampar Batam |
2024 |
Step Down; 3 Phase; 2500 kVA; 20kV/0.415kV; 50Hz; Dd0; ONAN; Hermetically Sealed Totally Oil Filled & Corrugated Radiator; Off Load Tap Changer 5 Pos; Indoor; IEC 60076. Winding: CU-CU |
1 |
|
PT. WASKITA BETON PRECAST TBK. |
645 |
BUMN |
Terminal Peti Kemas Batu Ampar Batam |
2024 |
Step Down; 3 Phase; 5000 kVA; 20kV/6,6kV; 50 Hz; Dyn5; ONAN; Hermetically Sealed Totally Oil Filled & Corrugated Radiator; OCTC 5 Tap; Indoor; 60076. Winding: CU-CU |
1 |
|
PT. WASKITA BETON PRECAST TBK. |
646 |
BUMN |
Terminal Peti Kemas Batu Ampar Batam |
2024 |
Step Down; 3 Phase; 6300 kVA; 20kV/6,6kV; 50Hz; Dyn5; ONAN; Hermetically Sealed Totally Oil Filled & Corrugated Radiator; OCTC 5 Tap; Indoor; IEC 60076. Winding: CU-CU |
1 |
|
PT. WASKITA BETON PRECAST TBK. |
647 |
BUMN |
Terminal Peti Kemas Batu Ampar Batam |
2024 |
Step Down; 3 Phase; 3150 kVA; 20kV/0,4kV; 50 Hz; Dyn5; ONAN; Hermetically Sealed Totally Oil Filled & Corrugated Radiator; OCTC 5 Tap; Indoor; IEC 60076. Winding: CU-CU |
1 |
|
PT. WASKITA BETON PRECAST TBK. |
648 |
BUMN |
Terminal Peti Kemas Batu Ampar Batam |
2024 |
Step Down; 3 Phase; 2500 kVA; 20kV/0,4kV; 50 Hz; Dyn5; ONAN; Hermetically Sealed Totally Oil Filled & Corrugated Radiator; OCTC 5 Tap; Indoor; IEC 60076. Winding: CU-CU |
1 |
|
PT. WASKITA BETON PRECAST TBK. |
649 |
BUMN |
Terminal Peti Kemas Batu Ampar Batam |
2024 |
Step Down; 3 Phase; 1600 kVA; 20kV/0,48kV; 50 Hz; Dyn5; ONAN; Hermetically Sealed Totally Oil Filled & Corrugated Radiator; OCTC 5 Tap; Indoor; IEC 60076. Winding: CU-CU |
1 |
|
PT. WASKITA BETON PRECAST TBK. |
650 |
BUMN |
Terminal Peti Kemas Batu Ampar Batam |
2024 |
Step Down; 3 Phase; 5000 kVA; 20kV/0,415kV; 50Hz; Dd0; ONAN; Hermetically Sealed Totally Oil FIlled & Corrugated Radiator; OCTC 5 Tap; Indoor; IEC 60076. Winding: CU-CU |
1 |
|
PT. WASKITA BETON PRECAST TBK. |
651 |
BUMN |
Terminal Peti Kemas Batu Ampar Batam |
2024 |
Trafo Isolasi; 3 Phase; 1600kVA; 0.48kV - 0.48 kV; 50Hz; Dyn5; ONAN; Hermetically Sealed Totally Oil Filled and Corrugated Radiator; Without Tap Changer; Outdoor; IEC 60076. Winding: CU-CU |
1 |
|
PT. DWI EKA BAKTI |
652 |
COMMERCIAL BUILDING |
BALI |
2024 |
Transformator; 3 Phase, 630 kVA, 20 kV - 400 V, 50 Hz, Dyn5, ONAN, Off-Load Tap Changer 5 Pos, Hermetically Sealed Totally Oil Filled, Indoor, IEC 60076. Winding: CU-CU |
1 |
|
PT. ATW SOLAR INDONESIA |
653 |
POWERPLANT |
PLTS RIAU ANDALAN PULP & PAPER (RAPP) |
2024 |
Trafo Dry Non Resin; 3 Phase; 375 kVA (225 kVA/150kVA); 400V - 400 & 900 V; 50Hz; Dyn11&d0; AN; Outdoor with Enclosure; IEC 60076. Winding: CU-CU |
1 |
|
PT. ATW SOLAR INDONESIA |
654 |
POWERPLANT |
PLTS RIAU ANDALAN PULP & PAPER (RAPP) |
2024 |
Trafo Dry Non Resin; 3 Phase; 150 kVA; 900 V - 400 V; 50Hz; Dyn11; AN; Dry non Resin; Outdoor with Enclosure; IEC 60076. Winding: CU-CU |
1 |
|
PT. ATEKINDO |
655 |
OIL & GAS |
INFILL WELLS |
2024 |
Step Down; 3 Phase; 150 kVA; 13,2 kVA - 480 V; 60Hz; Dyn5; ONAN; Hermetically Sealed Totally Oil Filled and Corrugated Radiator with Conservator; Off Load Tap Changer 5 Pos; Indoor/Outdoor; IEC 60076. Winding: CU-CU |
5 |
|
PT. ATEKINDO |
656 |
OIL & GAS |
INFILL WELLS |
2024 |
Step Down; 3 Phase; 150 kVA; 4.1 kVA - 480 V; 60Hz; Dyn5; ONAN; Hermetically Sealed Totally Oil Filled and Corrugated with Conservator; Off Load Tap Changer 5 Pos; Indoor/Outdoor; IEC 60076. Winding: CU-CU |
2 |
|
PT. PILAR GARBA INTI |
657 |
COMMERCIAL BUILDING |
CROWN PLAZA - LABUAN BAJO |
2024 |
Step Down; 3 Phase; 630 kVA; 20/0,38 kV; 50Hz; Dyn5; TEMP.65/60 PETIKC; ONAN; Hermetically Sealed with Box Acrylic; IEC 60076. Winding: AL-AL |
1 |
|
PT. DREDOLF INDONESIA |
658 |
POWERPLANT |
PLTD NIAS |
2024 |
Trafo Oil Immersed type 1000 kVA; 400V / 20kV; Ynd5; 50Hz; Outdoor; ONAN; 3 Phase; 5 Tap; DMCR; Hermetically Sealed; IEC 60076. Winding: AL-AL |
5 |
|
PT. DREDOLF INDONESIA |
659 |
POWERPLANT |
PLTD NIAS |
2024 |
Trafo Oil Immersed type 1250 kVA; 400V/20kV; Ynd5; 50Hz; Outdoor; ONAN; 3 Phase; 5 Tap; DMCR; Hermetically Sealed; IEC 60076. Winding: AL-AL |
2 |
|
PT. MAJU JAYA PRIMA PERKASA |
660 |
INDUSTRY |
TIMIKA PAPUA |
2024 |
Trafo Oil Immersed Hermetically Sealed type 400 kVA; 20kV/400V; Dyn5; 50Hz; Indoor; ONAN; 3 Phase; 5 Tap; OCTC; IEC 60076. Winding: AL-AL |
1 |
|
PT PLN (Persero) UP3 CILACAP |
661 |
BUMN |
TRAFO DISTRIBUSI 1 PHASA SPESIFIKASI KHUSUS PT. PLN (PERSERO) UP3 CILACAP |
2024 |
Trafo 50 kVA; li-0, 1 Phase (CSP) 462/231 V |
43 |
|
PT. ATW SOLAR INDONESIA |
662 |
POWERPLANT |
PLTS RIAU ANDALAN PULP & PAPER (RAPP) |
2024 |
Trafo Dry Non Resin; 3 Phase; 375 kVA (225 kVA/150kVA); 400V - 400 & 900 V; 50Hz; Dyn11&d0; AN; Outdoor with Enclosure; IEC 60076. Winding: CU-CU |
1 |
|
PT. ATW SOLAR INDONESIA |
663 |
POWERPLANT |
PLTS RIAU ANDALAN PULP & PAPER (RAPP) |
2024 |
Trafo Dry Non Resin; 3 Phase; 150 kVA; 900 V - 400 V; 50Hz; Dyn11; AN; Dry non Resin; Outdoor with Enclosure; IEC 60076. Winding: CU-CU |
1 |
|
PT. ATW SOLAR INDONESIA |
664 |
POWERPLANT |
PLTS RIAU ANDALAN PULP & PAPER (RAPP) |
2024 |
Trafo Dry Non Resin; 3 Phase; 375 kVA; 400 V - 400 V; 50Hz; Dyn11; AN; Dry Non Resin; Outdoor with Enclosure; IEC 60076. Winding: CU-CU |
1 |
|
PT. ATW SOLAR INDONESIA |
665 |
POWERPLANT |
PLTS RIAU ANDALAN PULP & PAPER (RAPP) |
2024 |
Trafo Dry Non Resin; 3 Phase; 400 kVA; 400 V - 400 V; 50Hz; Dyn11; AN; Dry Non Resin; Outdoor with Enclosure; IEC 60076. Winding: CU-CU |
1 |
|
CV. T-MURTI NUSANTARA |
666 |
POWERPLANT |
SUPREME GEOTHERMAL |
2024 |
Trafo Oil Immersed Hermetically Sealed Step Up type 1500kVA; 0,46kV/0,6kV; YNd5; 60Hz; Outdoor; ONAN; 3 Phase; 5 Tap; OCTC; DMCR; IEC 60076. Winding: CU-CU |
1 |
|
PT. MAJU JAYA PRIMA PERKASA |
667 |
INDUSTRY |
LAMPUNG |
2024 |
Trafo Oil Immersed Hermetically Sealed type 400 kVa; 20KV/400V; Dyn5; 50Hz; Outdoor; ONAN; 3 Phase; 5 tap; OCTC; DMCR; IEC 60076.Winding: CU-CU |
1 |
|
PT. LS ELECTRIC INDONESIA |
668 |
POWEPLANT |
PLTD PONTIANAK / PT. SPACE TECHNOLOGY |
2024 |
Trafo Oil Immersed Step Down type 2500kVA; 20KV/400V; Dyn5; 50Hz; Outdoor; ONAN; 3 Phase; 5 Tap; OCTC; Hermetically Sealed; IEC 60076; Winding: AL-AL |
16 |
|
PT. MAJU JAYA PRIMA PERKASA |
669 |
COMMERCIAL BUILDING |
PEMDA SOLO |
2024 |
Trafo Oil Immersed Hermetically Sealed type 1000 kVA; 20kV/400V; YNyn0; 50Hz; Indoor; ONAN; 3 Phase; 5 Tap; OCTC; DMCR; IEC 60076. Winding: CU-CU |
1 |
|
PT. BORNEO MAJU JAYA |
670 |
MINING |
KALIMANTAN |
2024 |
TRAFO OIL IMMMERSED (HV-LV CABEL BOX) 2500KVA; 20KV/400V; DYN5; 50HZ; OUTDOOR; ONAN; 3PHASE; 5 TAP; OCTC; HERMETICALLY SEALED; IEC 60076; WINDING: AL-AL |
1 |
|
KSO ADHI - PENTA |
671 |
COMMERCIAL BUILDING |
SARPAS II-B ISTANA WAKIL PRESIDEN IKN |
2024 |
Trafo Oil Ester Synthetic with Thermal Upgrading Paper; Hermaticall |
2 |
|
PT. KARIANGAU POWER |
672 |
POWERPLANT |
PT. KARIANGAU POWER BALIKPAPAN |
2024 |
Trafo Oil Immersed type 200kVA; 20KV/400V; Dyn5; 50Hz; Outdoor; ONAN; 3Phase; 7 tap; OCTC; Hermetically Sealed; IEC 60076 WINDING: AL-AL |
1 |
|
PT. BRINGIN KARYA SEJAHTERA |
673 |
POWERPLANT |
REVITALISASI MUSEUM BRI PURWOKERTO |
2024 |
Trafo Step Down; 3 Phase; 1000 kVA; 20kV/400V; 50Hz; Ynyn0; ONAN; Hermetically Sealed Totally Oil Filled; OCTC 5 Pos; Indoor; Proteksi DMCR; IEC 60076. Winding: CU-CU |
1 |
|
PT. SOLUNA BERLIMA PUTRA |
674 |
COMMERCIAL BUILDING |
KANTOR SEKRETARIAT DPRD MASOHI |
2024 |
Trafo Oil Immersed 3 Phase; 630 kVA; 20kV/400V; 50Hz; Dyn5; ONAN; Hermetically Sealed Totally Oil Filled; OCTC 5 Pos; Indoor; IEC 60076. Winding: AL-AL |
1 |
|
PT. LS ELECTRIC INDONESIA |
675 |
INDUSTRY |
POSCO CILEGON ( COIL YARD at HSM ) |
2024 |
Transformer Dry Non Resin Type; 3 Phase; 1600 kVA; 400 V - 400/220 V; 50 Hz; Dyn5; AN; Skid Base with Enclosure IP-31; Painting C3; IEC 60076. Winding: CU-CU |
1 |
|
PT. PURA MAYUNGAN |
676 |
INDUSTRY |
PT. SELANCAR PANEN RAYA (JATIUWUNG) |
2024 |
Trafo Oil Immersed type 1000 kVA; 20kV/400V; Dyn5; 50Hz; Indoor; ONAN; 3 Phase; 5 Tap; DMCR; Hermetically Sealed; IEC 60076. Winding: AL-AL |
1 |
|
PT. PLN (PERSERO) UP3 PRINGSEWU |
677 |
BUMN |
TRAFO SPEK KHUSUS YANG AKAN DIPASANG DI WILAYAH PT PLN (PERSERO) UP3 PRINGSEWU |
2024 |
Trafo 3 Phase; 100 kVA; 20kV - 400V; 50Hz; ONAN; Yzn5; Hermetically Sealed Totally Oil Filled; Off Load Tap Changer 9 Pos (14-14,75-15,5-16,25-17-17,75- 18,5-19,25-20kV) Outdoor; IEC 60076 (Losses mengacu SPLN D3.002-1:2020) Winding: AL-AL |
1 |
|
PT. PLN (PERSERO) UP3 PRINGSEWU |
678 |
BUMN |
TRAFO SPEK KHUSUS YANG AKAN DIPASANG DI WILAYAH PT PLN (PERSERO) UP3 PRINGSEWU |
2024 |
Trafo 3 Phase; 250 kVA; 20kV - 400V; 50Hz; ONAN; Yzn5; Hermetically Sealed Totally Oil Filled; Off Load Tap Changer 9 Pos (14-14,75-15,5-16,25-17-17,75- 18,5-19,25-20kV) Outdoor; IEC 60076 (Losses mengacu SPLN D3.002-1:2020) Winding: AL-AL |
2 |
|
PT. LS ELECTRIC INDONESIA |
679 |
EXPORT - PHILIPINES |
PROJECT HANN CASINO (FUJI HAYA ELECTRIC CORPORATION) |
2024 |
Transformer Oil Immersed Pad Mounted; Radial-Feed type; 3 Phase; 2500 kVA; 13.8 kV - 400 V; 60Hz; Dyn11; Z = 5.75%; KNAN-Cargill FR3, Hermetically Sealed with N2 Cushion and Corrugated Radiator, Off Load Tap Changer 5 Pos; Outdoor with HV-LV Cable Box; IE |
1 |
|
PT. LS ELECTRIC INDONESIA |
680 |
EXPORT - PHILIPINES |
PROJECT HANN CASINO (FUJI HAYA ELECTRIC CORPORATION) |
2024 |
Transformer Oil Immersed Pad Mounted; Radial-Feed type; 3 Phase; 3000 kVA; 13.8 kV - 400 V; 60Hz; Dyn11; Z = 5.75%; KNAN-Cargill FR3; Hermetically Sealed with N2 Cushion and Corrugated Radiator; Off Load Tap Changer 5 Pos; Outdoor with HV-LV Cable Box, IE |
1 |
|
PT. LS ELECTRIC INDONESIA |
681 |
EXPORT |
LS-USA TERMINAL 91 DUAL PRIMARY |
2024 |
Transformer Oil Immersed Type Step Down; Pad Mounted Radial Feed; 3 Phase; 3000 kVA; 13.8/4.16 kV - 480 V; 60 Hz; Dd0; ONAN; Hermetically Sealed with Nitrogen Cushion and Panel Radiator; Off Load Tap Changer 5 Pos (Dual Voltage) Outdoor with HV/LV Cabinet |
1 |
|
PT. INDRA CIPTA SENTOSA LESTARI |
682 |
INDUSTRY |
PT. MAYORA INDAH TBK |
2024 |
TRANSFORMER OIL TYPE 1000KVA, 20KV/400V, DYN5, 50HZ, 3P, ONAN, INDOOR DGPT 2 (EXCLUDE COOPER LINK), WINDING : CU-CU |
1 |
|
PT. HORAS BANGUN PERSADA |
683 |
AGRO INDUSTRY |
POTENSIAL BUMI SAKTI - ACEH |
2024 |
Trafo Oil Immersed Hermetically Sealed type 2500 kVA: 20kV/400V; Dyn5; 50Hz; Outdoor; ONAN; 3 Phase; 5 Tap OCTC; IEC 60076. Winding: CU-CU |
1 |
|
PT JAYA KENCANA |
684 |
COMMERCIAL BUILDING |
MANDAYA ROYAL HOSPITAL ANTASARI - JAKARTA |
2024 |
Trafo Oil Immersed Type 2000kVA; 20kV/400V; Dyn5; 50Hz; Indoor; ONAN; 3 Phase; 5 Tap; DGPT-2; Hermetically Sealed; IEC 60076. Winding: AL-AL |
2 |
|
PT JAYA KENCANA |
685 |
COMMERCIAL BUILDING |
MANDAYA ROYAL HOSPITAL ANTASARI - JAKARTA |
2024 |
Trafo Oil Immersed Type 3150kVA; 20kV/400V; Dyn5; 50Hz; Indoor; ONAN; 3 Phase; 5 Tap; DGPT-2; Hermetically Sealed; IEC 60076. Winding: AL-AL |
1 |
|
PT HELIO SYNAR ENERGI |
686 |
COMMERCIAL BUILDING |
IKN TPST 1 EV Charger |
2024 |
Transformer Ester Synthetic Oil Step Down 1250 kVA; with Thermal Upgrading Paper; 20kV/400V; Dyn5; 50Hz; Indoor; KNAN; OCTC 5 Tap; DMCR Transformer Safety Device; Hermetically Sealed; IEC 60076. Winding: CU-CU |
1 |
|
CV. ANUGERAH TEKNIK |
687 |
PORT & AIRPORT |
PELABUHAN WAINGAPU NTT |
2024 |
Trafo Oil Immersed Hermetically Sealed type 400kVA; 20kV/400V; Dyn5; 50Hz; Indoor; ONAN; 3 Phase; OCTC; Integrated Safety Device DMCR; IEC 60076. Winding: AL-AL |
1 |
|
PT. BERKIBAR BERSAMA BENDERA |
688 |
COMMERCIAL BUILDING |
PEMBANGUNGAN GEDUNG KPP PRATAMA SUMEDANG |
2024 |
Trafo Oil Immersed type 400 kVA; 20kV/400V; Dyn5; 50Hz; Indoor; ONAN; 3 Phase; 5 Tap; DMCR; Hermetically Sealed; IEC 60076. Winding: AL-AL |
1 |
|
PT. DUA PUTRA PERKASA PRATAMA |
689 |
MARINE SECTOR |
TAMBAK UDANG SUMBAWA DAN BIMA |
2024 |
Trafo Weltraf 3500 kVA; 20kV - 420V; 50Hz; Dyn5; ONAN; Hermetically Sealed with Conservator & Corrugated Radiator; On Load Tap Changer 25 Pos (9,88- 20,44kV; 440V/Step-Huaming); Indoor; IEC 60076. Winding: AL-AL |
1 |
|
PT. LS ELECTRIC INDONESIA |
690 |
INDUSTRY |
SK PLASMA |
2024 |
Transformer Mineral Oil Immersed type Step Down; 3 Phase; 8000kVA; 20kV - 6,6 kV; 50 Hz; Dyn5; ONAN; Hermetically Sealed with Conservator and Panel Radiator; Off Load Tap Changer 5 Pos; Outdoor (Side Bushing); IEC 60076. Winding: CU-CU |
1 |
|
PT. BORNEO MEGA ELEKTRINDO |
691 |
COMMERCIAL BUILDING |
PEMDA BANJARMASIN |
2024 |
Trafo Distribusi; Trafo Oil Immersed; 400 kVA; 20kV/400V; Dyn5; 50 Hz; Indoor; ONAN; 3 Phase. Winding: AL-AL |
1 |
|
PT. ASAHI SYNCHROTECH INDONESIA |
692 |
INDUSTRY |
UNO MINDA AUTOMOTIVE - INDONAKANO |
2024 |
Trafo Oil Immersed type 3000kVA; 20kV/400-230V; Dyn5; 50Hz; Indoor; ONAN; 3 Phase; DGPT-2; Hermetically Sealed; IEC 60076. Winding: AL-AL |
1 |
|
PT. SENTRA KARYA CAHAYA RAYA |
693 |
INDUSTRY |
PABRIK PVC KARBOL |
2024 |
Trafo Oil Immersed type 1500 kVA; 20kV/400V; Dyn5; 50Hz; Outdoor; ONAN; 3 Phasa; OCTC 5 Tap; DMCR; Hermetically Sealed; IEC 60076. Winding: CU |
1 |
|
PT. MAJU TERANG GEMILANG |
694 |
MARINE SECTOR |
TAMBAK UDANG NTB |
2024 |
Trafo Oil Immersed 630 kVA; 20kV-400V; Dyn5; SPLN 2020 (Tapping 7 x 2,5); 3 Phase; 50Hz; Indoor; ISD. Winding: AL-AL |
1 |
|
PT. PLN (Persero) Unit Induk Wilayah Nusa Tenggara Barat |
695 |
BUMN |
TRANSMISSION LINE |
2024 |
Transformator Automatic Voltage Regulator; 3 Phase, 10000 kVA, Input 7- 20 kV, Output 20-21 kV, 50 Hz, YNa0, ONAN, Cu-Cu, On-Load Tap Changer 21 Pos, Hermetically Sealed with Conservator, Outdoor, IEC 60076 |
2 |
|
PT. LS ELECTRIC INDONESIA |
696 |
COMMERCIAL BUILDING |
BRANTAS // RUSUN KEMENKEU KEMANGGISAN |
2024 |
Trafo Oil Ester Synthetic with Thermal Upgrading Paper; Hermetically Sealed type 630 kVA; 20kV/400V; Dyn5; 50Hz; Indoor; KNAN; OCTC 5 Tap; DMCR; Transformer Safety Device; IEC 60076. Winding: CU-CU |
1 |
|
PT. SUKSES TANET PERKASA |
697 |
INDUSTRY |
PABRIK PALEMBANG |
2024 |
Trafo Oil Immersed 630kVA; 20kV/400V; Dyn5; Indoor; IEC 60076. Winding: CU-CU |
1 |
|
PT. BINA TEKNIK CIPTAMANDIRI |
698 |
INDUSTRY |
PABRIK PALEMBANG |
2024 |
Trafo Oil Immersed Hermetically Sealed type 400kVA; 20kV/400V; Dyn5; 50Hz; Indoor; ONAN; 3 Phase; 5 Tap OCTC; IEC 60076. Winding: AL-AL |
1 |
|
PT. MAJU JAYA PRIMA PERKASA |
699 |
AGRO INDUSTRY |
SAWIT KALIMANTAN |
2024 |
Trafo 3 Phase; 400kVA; 20/0.4 kV; Dyn5; ONAN; Oil Immersed; HV Bushing Keramik + DMCR; OLTC Ecotap 9 Tap (16,5; 17; 17,5; 18; 18,5, 19; 19,5; 20; 20,5 kv) Outdoor; IEC 60076. Winding: CU-CU |
1 |
|
PT. SURYA ENERGI INDOTAMA |
700 |
POWERPLANT |
PLTS ITH Kramasan Palembang |
2024 |
Trafo Oil Immersed 3 Phase, 1000kVA, 6,3kV/400V, 50 Hz, Dyn11, ONAN, Hermetically Sealed totally oil filled, OCTC 5 Pos, Outdoor, IEC 60076 Winding : CU- CU |
1 |
|
PT. SURYA ENERGI INDOTAMA |
701 |
POWERPLANT |
PLTS ITH Kramasan Palembang |
2024 |
Trafo Oil Immersed 3 Phase, 1250kVA, 6,3kV/400V, 50 Hz, Dyn11, ONAN, Hermetically Sealed totally oil filled, OCTC 5 Pos, Outdoor, IEC 60076 Winding : CU- CU |
1 |
|
PT. LS ELECTRIC INDONESIA |
702 |
POWEPLANT |
PLTD PONTIANAK / PT. SPACE TECHNOLOGY |
2024 |
Trafo Oil Immersed type 2500kVA; 20KV/400V; Dyn5; 50Hz; Outdoor; ONAN; 3Phase; 5 tap; OCTC; Hermetically Sealed; IEC 60076; DMCR Winding : AL- AL |
1 |
|
PT. BORNEO MAJU JAYA |
703 |
MINING |
Arutmin tambang |
2024 |
TRANSFORMER 250 KVA 3 PHASE 20/0,4kV Dyn5, ONAN OUTDOOR SPECIAL TAPING UP TO 16kV 9 Tap Winding : AL-AL |
1 |
|
CV. SUKAPURA |
704 |
COMMERCIAL BUILDING |
HOSPITAL |
2024 |
Transformator; 1000 kVA, Dyn5, IEC, Indoor, Winding Al-Al |
1 |
|
PT. AYOE INDOTAMA TEXTILE |
705 |
INDUSTRY |
TEXTIL |
2024 |
Transformator; 1600 kVA, Dyn5, IEC, Indoor, Winding Al-Al |
1 |
|
PENDIDIKAN KEMALA BANGSA |
706 |
COMMERCIAL |
BUILDING |
2024 |
Transformator; 3 Phase, 800 kVA, 20 kV - 380 V, 50 Hz, Dyn5, KNAN, Cu-Cu, Off- Load Tap Changer 5 Pos, Hermetically Sealed Totally Oil Filled, Indoor, Synthetic Ester Oil, Thermally Upgraded Paper, IEC 60076 |
1 |
|
PT. PLN (PERSERO) UP3 MAMUJU |
707 |
BUMN |
TRANSMISSION LINE |
2024 |
Transformator; 3 Phase, 50 kVA, 20 kV - 400 V, 50 Hz, Yzn5, ONAN, Al-Al, Off Load Tap Changer 9 Pos, Hermetically Sealed Totally Oil Filled, Outdoor, IEC 60076 |
1 |
|
PT. PLN (PERSERO) UP3 MAMUJU |
708 |
BUMN |
TRANSMISSION LINE |
2024 |
Transformator; 3 Phase, 100 kVA, 20 kV - 400 V, 50 Hz, Yzn5, ONAN, Al-Al, Off Load Tap Changer 9 Pos, Hermetically Sealed Totally Oil Filled, Outdoor, IEC 60076 |
4 |
|
PT. SUKSES TANET PERKASA |
709 |
INDUSTRY |
DISTRIBUTOR TRAFO |
2024 |
Transformator; 3 Phase, 630 kVA, 20 kV - 400 V, 50 Hz, Dyn5, ONAN, Al-Al, Off- Load Tap Changer 5 Pos, Hermetically Sealed Totally Oil Filled, Indoor, IEC 60076 |
1 |
|
PT. PILAR GARBA INTI |
710 |
COMMERCIAL BUILDING |
CROWN PLAZA - LABUAN BAJO |
2024 |
Transformator; 630 kVA, Dyn5, IEC, Indoor, Winding Al-Al |
1 |
|
CV. INDAH SENTOSA BAN |
711 |
INDUSTRY |
INDUSTRY SURABAYA |
2024 |
Transformator; 1000 kVA, Dyn5, IEC, Indoor, Winding Al-Al |
1 |
|
CV SINAR ALAM ELEKTRIC |
712 |
INDUSTRY |
TEXTIL KALIMANTAN |
2024 |
Transformator; 3 Phase, 400 kVA, 20 kV - 400 V, 50 Hz, Dyn5, ONAN, Al-Al, Off- Load Tap Changer 5 Pos, Hermetically Sealed Totally Oil Filled, Outdoor, IEC 60076 |
1 |
|
CV SINAR ALAM ELEKTRIC |
713 |
INDUSTRY |
TEXTIL KALIMANTAN |
2024 |
Transformator; 630 kVA, Dyn5, IEC, Indoor, Winding Al-Al |
1 |
|
PT. INDOKOMAS BUANA PERKASA |
714 |
POWERPLANT |
PLTS APUNG LONTAR 1 MW- BANTEN |
2024 |
Transformator; 3 Phase, 750 kVA, 800 V - 400 V, 50 Hz, Dyn11, ONAN, Cu-Cu, Off- Load Tap Changer 5 Pos, Hermetically Sealed Totally Oil Filled, Outdoor, IEC 60076 |
1 |
|
PT. INDOKOMAS BUANA PERKASA |
715 |
POWERPLANT |
PLTS APUNG LONTAR 1 MW- BANTEN |
2024 |
Transformator; 3 Phase, 500 kVA, 800 V - 400V, 50 Hz, Dyn11, ONAN, Cu-Cu, Off- Load Tap Changer 5 Pos, Hermetically Sealed Totally Oil Filled, Outdoor, IEC 60076 |
1 |
|
PT. SUKSES TANET PERKASA |
716 |
INDUSTRY |
DITRIBUSI TRAFO |
2024 |
Transformator; 630 kVA, Dyn5, IEC, Indoor, Winding Al-Al |
1 |
|
PT. MAHAMERU SINERGI INDONESIA |
717 |
AGRO INDUSTRY |
SAWIT BUMITAMA GUNAJAYA AGRO |
2024 |
Transformator; 3 Phase, 250 kVA, 20 kV - 400 V, 50 Hz, Dyn5, ONAN, Cu-Cu, Off- Load Tap Changer 5 Pos, Hermetically Sealed Totally Oil Filled, Outdoor, IEC 60076 |
2 |
|
PT. MAHAMERU SINERGI INDONESIA |
718 |
AGRO INDUSTRY |
SAWIT BUMITAMA GUNAJAYA AGRO |
2024 |
Transformator; 3 Phase, 160 kVA, 20 kV - 400 V, 50 Hz, Dyn5, ONAN, Cu-Cu, Off- Load Tap Changer 5 Pos, Hermetically Sealed Totally Oil Filled, Outdoor, IEC 60076 |
2 |
|
PT. SURYA KARYA MANDIRI |
719 |
COMMERCIAL BUILDING |
Gedung Bisnis Pariwisata - DEPOK |
2024 |
Transformator; 1000 kVA, Dyn5, IEC, Indoor, Winding Al-Al |
1 |
|
PT. MAJU TERANG GEMILANG |
720 |
INDUSTRY |
Pabrik Semoyo Joyo - Kediri |
2024 |
Transformator; 3 Phase, 200 kVA, 20 kV - 400 V, 50 Hz, Dyn5, ONAN, Al-Al, Off- Load Tap Changer 5 Pos, Hermetically Sealed Totally Oil Filled, Outdoor, IEC 60076 |
2 |
|
PT. PAS JAYA MANDIRI |
721 |
BUMN |
DISTRIBUTION LINE PROJECT PLN KALIMANTAN TIMUR |
2024 |
Transformator; 3 Phase, 250 kVA, 20 kV - 400 V, 50 Hz, Dyn5, ONAN, Al-Al, Off- Load Tap Changer 9 Pos, Hermetically Sealed Totally Oil Filled, Outdoor, SPLN D3.002-1: 2020 |
8 |
|
PT. BASUDARA SUKSES BERSAMA |
722 |
BUMN |
PROJECT UPS MOBILE ( PLN MALUKU ) |
2024 |
Transformator Isolasi; 3 Phase, 100 kVA, 400 V - 400 V, 50 Hz, Dyn5, ONAN, Cu- Cu, No Taps, Dry Non Resin, IEC 60076, dengan Enclosure |
1 |
|
PT. METSA |
723 |
COMMERCIAL BUILDING |
PERUMAHAN PROJECT PERUM MILL |
2024 |
Transformator; 3 Phase, 315 kVA, 380V - 6,6kV, 50 Hz, Dyn5, ONAN, Al-Al, Off- Load Tap Changer 5 Pos, Hermetically Sealed Totally Oil Filled, Outdoor, IEC 60076 |
1 |
|
PT. METSA |
724 |
COMMERCIAL BUILDING |
PERUMAHAN PROJECT PERUM MILL |
2024 |
Transformator; 3 Phase, 200 kVA, 6,6kV - 380V, 50 Hz, Dyn5, ONAN, Al-Al, Off- Load Tap Changer 5 Pos, Hermetically Sealed Totally Oil Filled, Outdoor, IEC 60076 |
1 |
|
PT. METSA |
725 |
COMMERCIAL BUILDING |
PERUMAHAN PROJECT PERUM MILL |
2024 |
Transformator; 3 Phase, 50 kVA, 6,6kV - 400 V, 50 Hz, Dyn5, ONAN, Al-Al, Off- Load Tap Changer 5 Pos, Hermetically Sealed Totally Oil Filled, Outdoor, IEC 60076 |
1 |
|
PT. PLN NUSA DAYA |
726 |
BUMN |
PENGADAAN MOBILE TRANSFORMER UNTUK PROJECT RESERVE MARGIN BERGERAK 10 MW PT PLN NUSA DAYA |
2024 |
Transformator; 3 Phase, 1600 kVA, 400 V - 20 kV, 50 Hz, YNd5, ONAN, CU-CU, Off- Load Tap Changer 5 Pos, Hermetically Sealed Totally Oil Filled, Outdoor, IEC 60076 |
3 |
|
PT. PLN NUSA DAYA |
727 |
BUMN |
PENGADAAN MOBILE TRANSFORMER UNTUK PROJECT RESERVE MARGIN BERGERAK 10 MW PT PLN NUSA DAYA |
2024 |
Transformator; 3 Phase, 1250 kVA, 400 V - 20 kV, 50 Hz, YNd5, ONAN, CU-CU, Off- Load Tap Changer 5 Pos, Hermetically Sealed Totally Oil Filled, Outdoor, IEC 60076 |
1 |
|
CV. MAKMUR ABADI SENTOSA |
728 |
COMMERCIAL BUILDING |
HOSPITAL RSUD Kota Pinang -Kota Pinang |
2024 |
Transformator; 630 kVA, Dyn5, IEC, Outdoor, Winding Al-Al |
1 |
|
PT. SURYA SHUENN YUEH INDUSTRY |
729 |
INDUSTRY |
PROJECT PENGGANTIAN TRAFO EKSISTING - LOKASI TANGERANG |
2024 |
Transformator; 3 Phase, 2000 kVA, 20 kV - 400 V, 50 Hz, Dyn5, ONAN, Al-Al, Off- Load Tap Changer 5 Pos, Hermetically Sealed Totally Oil Filled, Intdoor, IEC 60076 |
1 |
|
CV. SAMUDERA JAYA ELEKTRIK |
730 |
INDUSTRY |
PROJECT PT CITRA FOOD ABADI 2 - BANDUNG |
2024 |
Transformator; 3 Phase, 1600 kVA, 20 kV - 400 V, 50 Hz, Dyn5, ONAN, Al-Al, Off- Load Tap Changer 5 Pos, Hermetically Sealed Totally Oil Filled, Indoor, IEC 60076 |
1 |
|
PT. MAJU TERANG GEMILANG |
731 |
INDUSTRY |
PABRIK PENGGILINGAN PADI-BONDOWOSO |
2024 |
Transformator; 3 Phase, 1250 kVA, 20 kV - 400 V, 50 Hz, Dyn5, ONAN, Al-Al, Off- Load Tap Changer 5 Pos, Hermetically Sealed Totally Oil Filled, Outdoor, IEC 60076 |
1 |
|
PT. SUNINDO MANDIRI PERKASA |
732 |
INDUSTRY |
PABRIK BANTEN |
2024 |
Transformator; 3 Phase, 1250 kVA, 20 kV - 400 V, 50 Hz, Dyn5, KNAN, Cu-Cu, Off- Load Tap Changer 5 Pos, Hermetically Sealed Totally Oil Filled, Indoor, Natural Ester Oil, Thermally Upgraded Paper, IEC 60076 |
1 |
|
PT. SUKSES TANET PERKASA |
733 |
INDUSTRY |
PABRIK JAWA TENGAH |
2024 |
Transformator; 3 Phase, 1250 kVA, 20 kV - 400 V, 50 Hz, YNyn0, ONAN, Cu-Cu, Off- Load Tap Changer 5 Pos, Hermetically Sealed Totally Oil Filled, Outdoor, IEC 60076 |
1 |
|
PT. HORAS BANGUN PERSADA |
734 |
INDUSTRY |
PABRIK CRUSER JANTHO - MEDAN |
2024 |
Transformator; 3 Phase, 630 kVA, 20 kV - 400 V, 50 Hz, Dyn5, ONAN, Cu-Cu, Off- Load Tap Changer 5 Pos, Hermetically Sealed Totally Oil Filled, Outdoor, IEC 60076 |
1 |
|
PT. LS ELECTRIC INDONESIA |
735 |
INDUSTRY |
PABRIK PROJECT WIRE ROD SUBANG |
2024 |
Transformator; 3 Phase, 3000 kVA, 20 kV - 400 V, 50 Hz, Dyn5, ONAN, Al-Al, Off- Load Tap Changer 5 Pos, Hermetically Sealed Totally Oil Filled, Indoor, IEC 60076 |
2 |
|
PT. LS ELECTRIC INDONESIA |
736 |
INDUSTRY |
PABRIK PROJECT WIRE ROD SUBANG |
2024 |
Transformator; 3 Phase, 2000 kVA, 20 kV - 400 V, 50 Hz, Dyn5, ONAN, Al-Al, Off- Load Tap Changer 5 Pos, Hermetically Sealed Totally Oil Filled, Intdoor, IEC 60076 |
1 |
|
PT. TAIYO SINAR RAYA TEKNIK |
737 |
INDUSTRY |
PABRIK MINUMAN PT HOKKAN INDONESIA - BOGOR |
2024 |
Transformator; 3 Phase, 1600 kVA, 20 kV - 400 V, 50 Hz, Dyn5, ONAN, Cu-Cu, Off- Load Tap Changer 5 Pos, Hermetically Sealed Totally Oil Filled, Indoor, IEC 60076 |
1 |
|
PT. TAIYO SINAR RAYA TEKNIK |
738 |
INDUSTRY |
PABRIK MINUMAN PT HOKKAN INDONESIA - BOGOR |
2024 |
Transformator; 3 Phase, 2500 kVA, 20 kV - 400 V, 50 Hz, Dyn5, ONAN, Cu-Cu, Off- Load Tap Changer 5 Pos, Hermetically Sealed Totally Oil Filled, Indoor, IEC 60076 |
2 |
|
PT. PERTAMINA HULU ROKAN |
739 |
OIL & GAS |
CALL-OFF ORDER (COO) TRANSFORMER (PAKET 1) |
2024 |
Transformator; 300/300/300 kVA, Dyn1, 13.2 kV - 1100/960/480 V, IEEE, Winding Cu-Cu |
35 |
|
PT. PLN SUKU CADANG |
740 |
BUMN |
PENGADAAN TAT ALAT UJI MCB PT PLN PUSERTIF |
2024 |
Transformer Mineral Oil Type 1250 kVA |
1 |
|
PT. VERITASINDO CITRA ABADI |
741 |
COMMERCIAL |
PABRIK PROYEK PT. AMNOR SHIPYARD LOKASI BATAM |
2025 |
Transformator; 3 Phase, 2000 kVA, 20 kV - 400 V, 50 Hz, Dyn5, ONAN, Al-Al, Off- Load Tap Changer 5 Pos, Hermetically Sealed Totally Oil Filled, Intdoor, IEC 60076 |
1 |
|
CV. INFINITE CAHAYA ELECTRIC |
742 |
INDUSTRY |
PABRIK PT. SHANGDE TECHNOLOGY INDONESIA |
2025 |
Transformator; 3 Phase, 1250 kVA, 20 kV - 400 V, 50 Hz, Dyn5, ONAN, Al-Al, Off- Load Tap Changer 5 Pos, Hermetically Sealed Totally Oil Filled, Outdoor, IEC 60076 |
1 |
|
PT. GLOBAL ELEKTRIK SENTOSA |
743 |
COMMERCIAL BUILDING |
HOSPITAL- MITRA IDAMAN KOTA BANJAR - LOKASI KOTA BANJAR |
2025 |
Transformator; 3 Phase, 800 kVA, 20 kV - 400 V, 50 Hz, Dyn5, ONAN, Al-Al, Off- Load Tap Changer 5 Pos, Hermetically Sealed Totally Oil Filled, Indoor, IEC 60076 |
1 |
|
CV. BINTANG MAS |
744 |
INDUSTRY |
PENGGANTIAN TRAFO EKSISTING UPK TIMOR LOKASI NTT |
2025 |
Transformator; 160/104 kVA, Dyn5, 20- 0.22/0.11 kV, Outdoor, IEC, Winding Cu- Cu |
1 |
|
PT. SURYA KARYA ENERGI |
745 |
POWERPLANT |
PROJECT PEMBANGKIT DIESEL |
2025 |
Transformator; 3 Phase, 1600 kVA, 400 V - 20 kV, 50 Hz, YNd5, ONAN, Al-Al, Off- Load Tap Changer 5 Pos, Hermetically Sealed Totally Oil Filled, Outdoor, IEC 60076 |
5 |
|
PT. SURYA KARYA ENERGI |
746 |
POWERPLANT |
PROJECT PEMBANGKIT DIESEL |
2025 |
Transformator; 3 Phase, 1600 kVA, 400 V - 20 kV, 50 Hz, YNd5, ONAN, Al-Al, Off- Load Tap Changer 5 Pos, Hermetically Sealed Totally Oil Filled, Outdoor, IEC 60076 |
5 |
|
PT. SURYA KARYA ENERGI |
747 |
POWERPLANT |
PROJECT PEMBANGKIT DIESEL |
2025 |
Transformator; 3 Phase, 1600 kVA, 20 kV - 400 V, 50 Hz, Dyn5, ONAN, Al-Al, Off- Load Tap Changer 5 Pos, Hermetically Sealed Totally Oil Filled, Outdoor, IEC 60076 |
1 |
|
WUHUAN ENGINEERING |
748 |
BUMN |
PROJECT PUSRI III B |
2025 |
Step-down distribution transformer TR-88 13.8±2x2.5%/2.4kV Dyn11 Uk=8%, 7500kVA, hermetically sealed tank with N2 gas cushion with Neutral grounding resistor (300A, 10s, 4.6Ω). Short-circuit current: 40kA (at Primary) Winding : CU- CU |
1 |
|
WUHUAN ENGINEERING |
749 |
BUMN |
PROJECT PUSRI III B |
2025 |
Step-down distribution transformer TR- 81A 13.8±2x2.5%/2.4kV Dyn11 Uk=7%, 5000kVA, hermetically sealed tank with N2 gas cushion with Neutral grounding resistor (300A, 10s, 4.6Ω). Short-circuit current: 40kA (at Primary) Winding : CU-CU |
1 |
|
WUHUAN ENGINEERING |
750 |
BUMN |
PROJECT PUSRI III B |
2025 |
Step-down distribution transformer TR- 811 13.8?2x2.5%/0.48kV, 2500kVA Dyn11 Uk=8%, hermetically sealed tank with N2 gas cushion. Short- circuit current: 40kA (at Primary) Winding: CU-CU |
2 |
|
WUHUAN ENGINEERING |
751 |
BUMN |
PROJECT PUSRI III B |
2025 |
Step-down distribution transformer TR- 81&TR-82 13.8?2?2.5%/0.48kV, 1600kVA Dyn11 Uk=6%, hermetically sealed tank with N2 gas cushion, Short- circuit current: 40kA (at Primary) Winding : CU-CU |
2 |
|
WUHUAN ENGINEERING |
752 |
BUMN |
PROJECT PUSRI III B |
2025 |
Step-down distribution transformer TR- 07&TR-08 13.8?2x2.5%/0.48kV, 400kVA Dyn11 Uk=4%, hermetically sealed tank with N2 gas cushion, Short- circuit current: 40kA (at Primary) Winding : CU-CU |
2 |
|
PT. QUADRO INDONESIA PERKASA |
753 |
INDUSTRY |
PABRIK PROYEK RETROFIT TRAFO PT TEL |
2025 |
TRAFO 2000/2500 KVA ONAN/ONAF Winding: CU-CU Scope Pekerjaan: 1. Rewinding 3 coil Cu-Cu 2. Penggantian Oil baru, jumlah liter sesuai rating plate original 3. Penggantian gasket tank cover, HV-LV bushing, dan tap changer 4. Penggant |
1 |
|
PT. DISTRITAMA PERKASA |
754 |
INDUSTRY |
PROYEK STONE CRUSHER LOKASI MOROWALI |
2025 |
Transformator; 3 Phase, 630 kVA, 20 kV - 400 V, 50 Hz, Dyn5, ONAN, Al-Al, Off Load Tap Changer 7 Pos, Hermetically Sealed Totally Oil Filled, Indoor, SPLN D3.002-1: 2020 |
1 |
|
PT. SUNINDO MANDIRI PERKASA |
755 |
DISTRIBUTOR |
STOK |
2025 |
Transformator; 1000 kVA, Dyn5, IEC, Indoor, Winding Cu-Cu |
1 |
|
PT. SUNINDO MANDIRI PERKASA |
756 |
DISTRIBUTOR |
STOK |
2025 |
Transformator; 1000 kVA, Dyn5, IEC, Indoor, Winding Al-Al |
1 |
|
PT. SUNINDO MANDIRI PERKASA |
757 |
DISTRIBUTOR |
STOK |
2025 |
Transformator; 630 kVA, Dyn5, IEC, Indoor, Winding Al-Al |
2 |
|
PT. SUNINDO MANDIRI PERKASA |
758 |
DISTRIBUTOR |
STOK |
2025 |
Transformator; 800 kVA, Dyn5, Indoor, Winding Al-Al |
1 |
|
PT. SUNINDO MANDIRI PERKASA |
759 |
DISTRIBUTOR |
STOK |
2025 |
Transformator, 400 KVA, DYN5, IEC, Indoor , Winding AL-AL Dan Deadbreak Straight 50mm AL |
2 |
|
PT. SINAR SAKTI METALINDO |
760 |
INDUSTRY |
PROYEK PENGGANTIAN TRAFO EKSISTING LOKASI CILEUNGSI |
2025 |
Transformator; 3 Phase, 1600 kVA, 20 kV - 400 V, 50 Hz, Dyn5, ONAN, Cu-Cu, Off- Load Tap Changer 5 Pos, Hermetically Sealed Totally Oil Filled, Indoor, IEC 60076 |
1 |
|
PT. PLN (PERSERO) PUSAT PENELITIAN DAN PENGEMBANGAN KETENAGALISTRIKAN |
761 |
BUMN |
PT PLN PUSLITBANG |
2025 |
Hight Voltage transformerset 100KV 160KVA with control bench and divider |
1 |
|
PT. MEDIKA ANUGERAH RIYADI |
762 |
COMMERCIAL BUILDING |
HOSPITAL- ANUGERAH LOKASI JAWA TENGAH |
2025 |
Trafo Oil Immersed type 400kVA; 20KV - 400V; Ynyn0; 50Hz; Indoor (PIB 70mm); ONAN; 3Phase; 5 tap; OCTC; Hermetically Sealed; IEC 60076; DMCR Winding : AL- AL |
1 |
|
PT. PLN HALEYORA POWER |
763 |
BUMN |
PT PLN JAWA TIMUR |
2025 |
Transformator; 3 Phase, 50 kVA, 20 kV - 400 V, 50 Hz, Yzn5, ONAN, Al-Al, Off Load Tap Changer 9 Pos (14-14,75-15,5- 16,25,17-17,75-18,5-19,25-20 kV), Hermetically Sealed Totally Oil Filled, Outdoor, IEC 60076 (Losses SPLN 2020) |
2 |
|
PT. PLN HALEYORA POWER |
764 |
BUMN |
PT PLN JAWA TIMUR |
2025 |
Transformator; 3 Phase, 100 kVA, 20 kV - 400 V, 50 Hz, Yzn5, ONAN, Al-Al, Off Load Tap Changer 9 Pos (14-14,75-15- 16,25,17-17,75-18,5-19,25-20 kV), Hermetically Sealed Totally Oil Filled, Outdoor, IEC 60076 (Losses SPLN 2020) |
4 |
|
PT. PLN HALEYORA POWER |
765 |
BUMN |
PT PLN JAWA TIMUR |
2025 |
Transformator; 3 Phase, 100 kVA, 20 kV - 400 V, 50 Hz, Yzn5, ONAN, Al-Al, Off Load Tap Changer 9 Pos (14-14,75-15- 16,25,17-17,75-18,5-19,25-20 kV), Hermetically Sealed Totally Oil Filled, Outdoor, IEC 60076 (Losses SPLN 2020) |
12 |
|
PT. PLN HALEYORA POWER |
766 |
BUMN |
PT PLN JAWA TIMUR |
2025 |
Transformator; 3 Phase, 160 kVA, 20 kV - 400 V, 50 Hz, Yzn5, ONAN, Al-Al, Off Load Tap Changer 9 Pos, Hermetically Sealed Totally Oil Filled, Outdoor, IEC 60076 |
2 |
|
PT. PLN HALEYORA POWER |
767 |
BUMN |
PT PLN JAWA TIMUR |
2025 |
Transformator; 3 Phase, 160 kVA, 20 kV - 400 V, 50 Hz, Yzn5, ONAN, Al-Al, Off Load Tap Changer 9 Pos, Hermetically Sealed Totally Oil Filled, Outdoor, IEC 60076 |
5 |
|
PT. PLN HALEYORA POWER |
768 |
BUMN |
PT PLN JAWA TIMUR |
2025 |
Transformator; 3 Phase, 250 kVA, 20 kV - 400 V, 50 Hz, Dyn5, ONAN, Off Load Tap Changer 9 Pos (14-14,75-15-16,25,17- 17,75-18,5-19,25-20 kV), Hermetically Sealed Totally Oil Filled, Outdoor, IEC 60076 (Losses SPLN 2020) |
1 |
|
PT. PLN HALEYORA POWER |
769 |
BUMN |
PT PLN JAWA TIMUR |
2025 |
Transformator; 3 Phase, 250 kVA, 20 kV - 400 V, 50 Hz, Dyn5, ONAN, Off Load Tap Changer 9 Pos (14-14,75-15-16,25,17- 17,75-18,5-19,25-20 kV), Hermetically Sealed Totally Oil Filled, Outdoor, IEC 60076 (Losses SPLN 2020) |
1 |
|
PT. WIRAKY NUSA TELEKOMUNIKASI |
770 |
COMMERCIAL |
SMART TRANSFORMER STATION BESS- IKN NUSA DAYA LOKASI IKN BALIKPAPAN |
2025 |
Trafo 5000 Kva, AL-AL, 800V & 800V-20 kV, Dyn5Yn5, Mineral Oil, Corrugated Radiator, E-DMCR + Modbus Module |
2 |
|
PT. PLN NUSA DAYA |
771 |
POWEPLANT |
PROYEK PEMBANGKIT MOROWALI |
2025 |
Transformator; 3 Phase, 1600 kVA, 400 V - 20 kV, 50 Hz, YNd5, ONAN, CU-CU, Off- Load Tap Changer 5 Pos, Hermetically Sealed Totally Oil Filled, Outdoor, IEC 60076 |
5 |
|
PT. PLN NUSA DAYA |
772 |
POWEPLANT |
PROYEK PEMBANGKIT MOROWALI |
2025 |
Transformator; 3 Phase, 1250 kVA, 400 V - 20 kV, 50 Hz, YNd5, ONAN, CU-CU, Off- Load Tap Changer 5 Pos, Hermetically Sealed Totally Oil Filled, Outdoor, IEC 60076 |
1 |
|
PT. TANJUNG ENIM LESTARI PULP AND PAPER |
773 |
INDUSTRY |
PROJECT PENGGANTIAN TRAFO EXISTING 2 mVa, LOKASI PALEMBANG |
2025 |
Step Down, 3 Phase, 2MVA, 24kV-400V, 50 Hz, Dyn5, ONAN, Hermetically Sealed Totally Oil Filled and Corrugated Radiator, Off Load Tap Changer 5 Pos, SHORT CIRCUIT CURRENT 0.8II48 KA,IMPEDANCE VOLTAGE 6%, CLASS 10P20,COMPLETE WITH PROTECTIONS |
1 |
|
PT. SURYA KARYA MANDIRI |
774 |
COMMERCIAL BUILDING |
PROYEK THE PREMIER HILLS-SAMARINDA |
2025 |
Transformator; 3 Phase, 630 kVA, 20 kV - 400 V, 50 Hz, Dyn5, ONAN, Al-Al, Off- Load Tap Changer 5 Pos, Hermetically Sealed Totally Oil Filled, Indoor, IEC 60076 |
2 |
|
PT. SURYA KARYA MANDIRI |
775 |
PROJECT Proyek Sport Club Anwa - Meruya Lokasi Meruya |
2025 |
Trafo Oil Immersed Hermetically Sealed type 315kVa; 20KV/400V; Dyn5; 50Hz; Indoor; ONAN; 3Phase; OCTC 5 tap; Integrated Safety Device DGPT2; IEC 60076 Winding : AL - AL DeadBreak Straight 50mm Pin AL-AL =3 Pcs |
1 |
||
PT. WIRA JAYA SASWATA |
776 |
MINING |
PROJECT Pengembangan TLS 6&7 Bukit Asam Lokasi Palembang |
2025 |
Trafo Oil Immersed Hermetically Sealed type 160 kVa; 20KV/400V; Dyn5; 50Hz; Outdoor with Cable Box; ONAN; 3 Phase; 5 tap OCTC; Integrated Safety Device DMCR; IEC 60076 Winding : AL-AL |
1 |
|
PT. ADHI KARYA (PERSERO) TBK |
777 |
COMMERCIAL |
LIQUID IMMERSED POWER TRANSFORMER & NER PUSRI - IIIB PROJECT |
2025 |
Trafo Oil Immersed Hermetically Sealed type step up 1500kVa; 400V/20kV; Dyn5; 50Hz; Indoor; ONAN; 3 Phase; Off load tap changer 5 pos; DMCR; Hermetically Sealed; IEC 60076. |
3 |
|
PT. ADHI KARYA (PERSERO) TBK |
778 |
COMMERCIAL |
LIQUID IMMERSED POWER TRANSFORMER & NER PUSRI - IIIB PROJECT |
2025 |
Step Down, 3 Phase, 1250 kVA, 13.8 kV - 2.4 kV, 50 Hz, Dyn11, ONAN, Hermetically Sealed with nitrogen cushion and Panel Radiator, Off Load Tap Changer 5 Pos, Outdoor with HV/LV Cable Box, Oil / Winding Temperature Rise 50/55?C, include; Mar |
1 |
|
PT. ADHI KARYA (PERSERO) TBK |
779 |
COMMERCIAL |
LIQUID IMMERSED POWER TRANSFORMER & NER PUSRI - IIIB PROJECT |
2025 |
Step Down, 3 Phase, 1600 kVA, 13.8 kV - 480 V, 50 Hz, Dyn11, ONAN, Hermetically Sealed with nitrogen cushion and Panel Radiator, Off Load Tap Changer 5 Pos, Outdoor with HV/LV Cable Box, Oil / Winding Temperature Rise 50/55?C, include; Mari |
2 |
|
PT. TASNIM GERAK PERSADA |
780 |
POWERPLANT |
PLTMG 100 MW BATAM,SITE SEKUPANG, LOKASI BATAM |
2025 |
3 Phase, 1500 kVA, 20 kV - 400 V, 50 Hz, YNyn0, ONAN, Hermetically Sealed Totally Oil Filled and Corrugated Radiator, Off Load Tap Changer 5 Pos Outdoor, Z = 4 % ,IEC 60076 Winding : CU-CU |
2 |
|
PT. TASNIM GERAK PERSADA |
781 |
POWERPLANT |
PLTMG 100 MW BATAM,SITE SEKUPANG, LOKASI BATAM |
2025 |
3 Phase, 2500 kVA, 20kV - 400 V, 50 Hz, Dyn5, ONAN, Hermetically Sealed Totally Oil Filled and Corrugated Radiator, Off Load Tap Changer 5 Pos ,Outdoor, Z = 5 % ,IEC 60076 Winding : CU-CU |
1 |
|
PT. BORNEO MAJUJAYA |
782 |
MINING |
PROJECT TAMBANG EMAS PELSART TIMBURU GOLD LOKASI KALIMANTAN |
2025 |
Transformator Distribusi 3 Phase, 160 kVA, 20 kV - 400 V, 50 Hz, Dyn11, ONAN, Hermetically Sealed Totally Oil Filled and Panel Radiator, Off Load Tap Changer 5 Pos, Outdoor with HV/LV Cable Box, IEC 60076 Winding : CU-CU |
1 |
|
PT. BORNEO MAJUJAYA |
783 |
MINING |
PROJECT TAMBANG EMAS PELSART TIMBURU GOLD LOKASI KALIMANTAN |
2025 |
Transformator Distribusi 3 Phase, 400 kVA, 20 kV - 400 V, 50 Hz, Dyn11, ONAN, Hermetically Sealed Totally Oil Filled and Panel Radiator, Off Load Tap Changer 5 Pos, Outdoor with HV/LV Cable Box, IEC 60076 Winding : CU-CU |
1 |
|
PT. BORNEO MAJUJAYA |
784 |
MINING |
PROJECT TAMBANG EMAS PELSART TIMBURU GOLD LOKASI KALIMANTAN |
2025 |
Transformator Distribusi 3 Phase, 1000 kVA, 20 kV - 400 V, 50 Hz, Dyn11, ONAN, Hermetically Sealed Totally Oil Filled and Panel Radiator, Off Load Tap Changer 5 Pos, Outdoor with HV/LV Cable Box, IEC 60076 Winding : CU-CU |
1 |
|
PT. BORNEO MAJUJAYA |
785 |
MINING |
PROJECT TAMBANG EMAS PELSART TIMBURU GOLD LOKASI KALIMANTAN |
2025 |
Transformator Distribusi 3 Phase, 1250 kVA, 20 kV - 400 V, 50 Hz, Dyn11, ONAN, Hermetically Sealed Totally Oil Filled and Panel Radiator, Off Load Tap Changer 5 Pos, Outdoor with HV/LV Cable Box, IEC 60076 Winding : CU-CU |
1 |
|
PT. LS ELECTRIC INDONESIA |
786 |
COMMERCIAL |
Pasar Terban Yogyakarata |
2025 |
Trafo 500kVA, 20kV/400V, Step Down , Oil Ester Synthetic, Ynyn0, 50Hz, Indoor, 3 Phase, thermally up graded paper, Standar IEC 60076, Winding: CU-CU Deadbreak Straight N2XSY 3X 1CX120mm?= 3 Pcs |
1 |
|
PT. ADHI KARYA (PERSERO) TBK |
787 |
BUMN |
PROJECT PUSRI III-B LIQUID IMMERSED POWER TRANSFORMER & NER LOKASI PUPUK SRIWIJAYA III-B PALEMBANG |
2025 |
STEP DOWN; 3 PHASE; 7500kVA; 13,8 kV - 2,4 kV; 50Hz; Dyn11; ONAN; Hermetically Sealed with Nitrogen Cushion and Panel Radiator; Off Load Tap Changer 5 Pos; Outdoor with HV/LV Cable Box; Oil/Winding Temperature Rise 50/55?C; include: |
3 |
|
PT. ADHI KARYA (PERSERO) TBK |
788 |
BUMN |
PROJECT PUSRI III-B LIQUID IMMERSED POWER TRANSFORMER & NER LOKASI PUPUK SRIWIJAYA III-B PALEMBANG |
2025 |
STEP DOWN; 3 PHASE; 1250kVA; 13,8kV 2,4kV; 50Hz; Dyn11; ONAN; Hermetically Sealed with Nitrogen Cushion and Panel Radiator; Off Load Tap Changer 5 Pos; Outdoor with HV/LV Cable Box; Oil/Winding Temperature Rise 50/55?C; include: |
1 |
|
PT. ADHI KARYA (PERSERO) TBK |
789 |
BUMN |
PROJECT PUSRI III-B LIQUID IMMERSED POWER TRANSFORMER & NER LOKASI PUPUK SRIWIJAYA III-B PALEMBANG |
2025 |
STEP DOWN; 3 PHASE; 1600kVA; 13,8kV 0,48kV; 50Hz; Dyn11; ONAN; Hermetically Sealed with Nitrogen Cushion and Panel Radiator; Off Load Tap Changer 5 Pos; Outdoor with HV/LV Cable Box; Oil/Winding Temperature Rise 50/55?C; include: |
2 |
|
PT. ADHI KARYA (PERSERO) TBK |
790 |
BUMN |
PROJECT PUSRI III-B LIQUID IMMERSED POWER TRANSFORMER & NER LOKASI PUPUK SRIWIJAYA III-B PALEMBANG |
2025 |
NEUTRAL GROUNDING RESISTOR (MERK HUBBELL); 2,4kV; CURRENT RATING 300 Amp; Time On 10 Second; Outdoor Use |
4 |
|
PT. ARGANA AKHTARDILLAH PUTRA |
791 |
COMMERCIAL |
PROJECT HOTEL HILTON KOTA BARU PARAHYANGAN |
2025 |
Trafo Oil Immersed type 1250kVA; 20KV/400V; Dyn5; 50Hz; Indoor(120mm); ONAN; 3Phase; 5 tap; OCTC; Hermetically Sealed; DMCR; IEC 60076 Winding: AL-AL |
2 |
|
PT. NUSACIPTA INDONESIA |
792 |
WATER TREATMENT PLANT (WTP) |
PROJECT WTP SAMPORA SINARMAS - BSD TANGERANG |
2025 |
Trafo Step down, 3 Phase, 2000 kVA, 20 kV - 400V, 50 Hz, Dyn5, ONAN, Hermetically Sealed Totally Oil Filled and Corrugated Radiator, Off Load Tap Changer 5 Pos, Indoor with LV Busbar, IEC 60076 Winding: CU-CU |
1 |
|
PT. KURNIA PURNAMATAMA |
793 |
POWERPLANT |
PROJECT PLN BATAM PEMBANGKIT DIESEL |
2025 |
Kontainer 10 feet trafo Step up AL-AL 1600kVA; 400V/20kV; Ynd5; Hermatically sealed; IEC 60076 tanpa kubikel |
18 |
|
PT. PLN MANDAU CIPTA TENAGA NUSANTARA |
794 |
INDUSTRY |
Pabrik Kertas PT. Tanjungenim Lestari Pulp and Paper - Sumatera Selatan |
2025 |
Trafo Step Up, 3 Phase, 15.000 kVA, 20 kV-24kV, 50 Hz, Ynd5, ONAN, Hermetically Sealed With Conservator, Panel Radiator, OLTC (17 Step 250V/Step), HV-LV Cable Box, HV-LV Cooper Bar, IEC 60076 Winding : CU-CU |
1 |
|
PT. PLN MANDAU CIPTA TENAGA NUSANTARA |
795 |
INDUSTRY |
Pabrik Kertas PT. Tanjungenim Lestari Pulp and Paper - Sumatera Selatan |
2025 |
Netral Grounding Resistor (NGR), Aplication for Trafo 15.000 kVA: Outdoor Instalation 20kV/24kV Include NCT |
1 |
|
PT. IHI POWER SERVICE INDONESIA |
796 |
INDUSTRY |
Pabrik Besi PT. IHI POWER - Cilegon |
2025 |
Trafo Oil Immersed type 1000kVA; 20KV/6,6kV; Dd6; 50Hz; Indoor; ONAN; 3 Phase; 5 tap; DGPT-2; Hermetically Sealed; IEC 60076 Winding : CU-CU |
1 |
|
PT. IHI POWER SERVICE INDONESIA |
797 |
INDUSTRY |
Pabrik Besi PT. IHI POWER - Cilegon |
2025 |
Trafo Oil Immersed type 2000kVA; 20KV/400V; Dyn5; 50Hz; Indoor; ONAN; 3 Phase; 5 tap; DGPT-2; Hermetically Sealed; IEC 60076 Winding: CU-CU |
1 |
|
PT. BORNEO MAJUJAYA |
798 |
POWERPLANT |
PROJECT ADARO LOKASI KALIMANTAN |
2025 |
Trafo Oil Immersed type 800kVA; 20KV/400V; Dyn5; 50Hz; Outdoor; ONAN; 3 Phase; Of Load Tap Changer 5 tap; DMCR; Hermetically Sealed; IEC 60076 Winding : AL-AL |
1 |
|
PT. BORNEO MAJUJAYA |
799 |
POWERPLANT |
PROJECT ADARO LOKASI KALIMANTAN |
2025 |
Trafo Oil Immersed type 250kVA; 20KV/400V; Dyn5; 50Hz; Outdoor; ONAN; 3 Phase; Of Load Tap Changer 5 tap; Hermetically Sealed; IEC 60076 Winding : AL-AL |
1 |
|
PT ARTA JAYA ELEKTRIK |
800 |
COMMERCIAL |
RESORT BALI |
2025 |
Trafo Oil Immersed type 1250kVA; 20KV/400V; Dyn5 50Hz; Indoor; ONAN; 3 Phase; 5 tap; DMCR; Hermetically Sealed; IEC 60076 Winding AL-AL |
1 |
|
PT. MAJU TERANG GEMILANG |
801 |
COMMERCIAL |
RESORT NIHI - SUMBA, NUSA TENGGARA TIMUR |
2025 |
Trafo step down type Oil transformer; kap 1600 KVA; 20kV/400V; Dyn5 Primer Indoor; ONAN; 3 Phase; 5 tap; Hermetically Sealed; On Load Tap Changer; ecotap 9 steps; Z= 4,5%; Winding :CU-CU |
1 |
|
PT. WIRAKY NUSA TELEKOMUNIKASI |
802 |
BUMN |
PROJECT SMART TRANSFORMER STATION BESS- IKN NUSA DAYA LOKASI IKN BALIKPAPAN |
2025 |
Trafo 5000 Kva, AL-AL, 800V & 800V-20 kV, Dyn5Yn5, Mineral Oil, Corrugated Radiator, E-DMCR + Modbus Module |
2 |
|
PT. WIRAKY NUSA TELEKOMUNIKASI |
803 |
BUMN |
PROJECT SMART TRANSFORMER STATION BESS- IKN NUSA DAYA LOKASI IKN BALIKPAPAN |
2025 |
TRAFO 250 KVA, AL-AL, Dyn5, 800 V / 400 V, MINERAL OIL, CORRUGATED, INDOOR TYPE, IEC |
2 |
|
PT. JAGAT SAKSANA MAKMUR |
804 |
BUMN |
WASKITA KARYA GEDUNG GRUP D MARKAS KOMANDO PENGAMANAN PRESIDEN LOKASI JAKARTA PUSAT |
2025 |
Trafo Oil Synthetic Ester with Thermal Upgrading Paper (TUP) Type 630kVA; 20kV/400V; Dyn5; 50Hz; Indoor; KNAN; 3 PHASE; DMCR Transformer Safety Device; Hermetically Sealed; Off Load Tap Changer 5 Pos; IEC60076 Winding : CU- CU |
1 |
|
PT JAYA KENCANA |
805 |
COMMERCIAL BUILDING |
PROJECT MALL 23 - SEMARANG |
2025 |
Trafo Oil Syntetic Ester type 2000kVA; 20KV/400V; Ynyn0; 50Hz; Indoor; KNAN; (TUP Thermal Upgrading Paper); 3 Phase; 5 tap; DMCR; Hermetically Sealed; IEC 60076; Winding:CU-CU |
1 |
|
PT JAYA KENCANA |
806 |
COMMERCIAL BUILDING |
PROJECT MALL 23 - SEMARANG |
2025 |
Trafo Oil Syntetic Ester type 3150kVA; 20KV/400V; Ynyn0; 50Hz; Indoor; KNAN; (TUP Thermal Upgrading Paper); 3 Phase; 5 tap; DMCR; Hermetically Sealed; IEC 60076; Winding:CU-CU |
2 |
|
PT. LS ELECTRIC INDONESIA |
807 |
INDUSTRY |
PROJECT PJT Echopoly /Yisu Jababeka Cikarang, Bekasi |
2025 |
Transformer 630kVA, 20kV/400V, Step Down, Oil Immersed, ONAN, 3 Phase, 50Hz, Dyn5, 5 Tap Changer, OCTC, Hermetically Sealed, Indoor, Integrated Safety Device, Elastimold, IEC 60076 Winding: AL-AL |
1 |
|
PT. PRATAMA LINTAS NUSA |
808 |
POWERPLANT |
PLTD TAGULANDANG 2MW LOKASI SULAWESI |
2025 |
Trafo Oil Immersed type step up 2500kVA, 400V/20kV, ONAN, 3 Phase, 50Hz, Ynd5, Off load Changer 5 pos, DMCR Safety Device; Hermetically Sealed, Indoor, IEC 60076, Winding : AL-AL |
1 |
|
PT. SUNINDO MANDIRI PERKASA |
809 |
INDUSTRY |
STOCK LOKASI TANGERANG |
2025 |
Trafo Oil Immersed type 400kVA; 20KV - 400-231V; YNyn0; 50Hz; Outdoor; ONAN; 3Phase; 5 tap; OCTC; Hermetically Sealed; IEC 60076; DMCR Winding : AL-AL |
1 |
|
PT. LS ELECTRIC INDONESIA |
810 |
INDUSTRY |
KT24-4228 Electric H2 |
2025 |
Transformer Oil Immersed Type Padmounted Radial Feed, 3 Phase, 2500kVA, 34.5kV - 480V, 60 Hz, Dyn11, KNAN-FR3, CU-CU Hermetically Sealed With N2 Cushion & Panel Radiator, Off Load Tap Changer 5 Pos, Outdoor with HV/LV Cable Box, IEEE C57.12 |
1 |
|
PT. SUKSES TANET PERKASA |
811 |
INDUSTRY |
STOCK |
2025 |
Trafo Oil Immersed type 800kVA; 20KV - 400V; Dyn5; 50Hz; Outdoor; ONAN; 3Phase; Off Load Tap Changer 5 Pos; DMCR Transformer Safety Device; Hermetically Sealed; IEC 60076; Winding: AL-AL |
1 |
|
PT. CIMENDANG SAKTI KONTRAKINDO- PT.MEDAL JAYA PURNAMA, KSO |
812 |
INDUSTRY |
STOCK |
2025 |
Trafo Oil Ester Synthetic type 1600kVA; 20KV - 400V; Dyn5; 50Hz; Outdoor; KNAN; 3Phase; Off Load Tap Changer 5 Pos; DMCR Transformer Safety Device; Hermetically Sealed; IEC 60076; Winding CU - CU |
1 |
|
PT. PLN NUSA DAYA |
813 |
POWER PLANT |
PEMBANGKIT DIESEL |
2025 |
Transformator; 3 Phase, 1600 kVA, 400 V - 20 kV, 50 Hz, YNd5, ONAN, Al-Al, Off- Load Tap Changer 5 Pos, Hermetically Sealed Totally Oil Filled, Outdoor, IEC 60076 |
2 |
|
PT PRIDA DENIA TEKNINDO |
814 |
INDUSTRY |
LOAD TEST TRAKINDO |
2025 |
Trafo Oil Immersed Hermetically Sealed type 2000 kVa; 11KV/400V; Dyn5; 50Hz; Outdoor; ONAN; 3 Phase; Off Load Tap Changer 5 Pos; Transformer Safety Device DMCR; AL-AL; IEC 60076 Winding : AL-AL |
1 |
|
PT. ATEKINDO |
815 |
INDUSTRY |
PABRIK DELTAMAS |
2025 |
Trafo Oil Immersed Hermetically Sealed type 250kVa; 20KV/400V; Dyn5; 50Hz; Outdoor; ONAN; 3Phase; Off Load Tap Changer 5 tap; DMCR; IEC 60076. AL - AL |
1 |
|
PT. LS ELECTRIC INDONESIA |
816 |
BUILDING COMMERCIAL RESIDENCE |
DGT - FUJIHAYA PJT |
2025 |
PAD MOUNTED XMER 1000KVA 13.8KV/400/230V 3PH PAD-MOUNTED TRANSFORMER TYPE : 3PHASE 60Hz RADIAL FEED RATING : 1000KVA PRIMARY : 13800V, 3W (DELTA CONNECTED), 95KV (BIL) TAPPINGS : (+/- ) 5%, 2.5% PER STEP SECONDARY : 400/230V, 4W (WYE C |
1 |
|
PT. LS ELECTRIC INDONESIA |
817 |
BUILDING COMMERCIAL RESIDENCE |
DGT - FUJIHAYA PJT |
2025 |
PAD MOUNTED XMER 225KVA 13.8KV 3W 400/230V 4W 3PH PAD-MOUNTED TRANSFORMER TYPE: 3PHASE 60Hz RADIAL FEED RATING: 225KVA PRIMARY: 13800V 3W (DELTA CONNECTED), 95KV (BIL) TAPPINGS : (+/- ) 5%, 2.5% PER STEP SECONDARY : 400/230V 4W (WYE CO |
2 |
|
PT. LS ELECTRIC INDONESIA |
818 |
BUILDING COMMERCIAL RESIDENCE |
DGT - FUJIHAYA PJT |
2025 |
PAD MOUNTED XMER 150KVA 13.8KV 3W 400/230V 4W 3PH PAD-MOUNTED TRANSFORMER TYPE: 3PHASE 60Hz RADIAL FEED RATING: 150KVA PRIMARY: 13800V 3W (DELTA CONNECTED), 95KV (BIL) TAPPINGS : (+/- ) 5%, 2.5% PER STEP SECONDARY : 400/230V 4W (WYE CO |
2 |
|
PT. LS ELECTRIC INDONESIA |
819 |
BUILDING COMMERCIAL RESIDENCE |
DGT - FUJIHAYA PJT |
2025 |
PAD MOUNTED XMER 300KVA 13.8KV 3W 400/230V 4W 3PH PAD-MOUNTED TRANSFORMER TYPE: 3PHASE 60Hz RADIAL FEED RATING: 300KVA PRIMARY: 13800V 3W (DELTA CONNECTED), 95KV (BIL) TAPPINGS : (+/- ) 5%, 2.5% PER STEP SECONDARY : 400/230V 4W (WYE CO |
1 |
|
PT. GRAHA USAHA TEKNIK |
820 |
INDUSTRY |
PROJECT PT SEMEN GROBOGAN (INDOCEMENT) LOKASI SEMARANG |
2025 |
3Phase, Trafo 2000 kVA, 10kV/400V, 50 Hz, Dyn11, ONAN, Hermetically Sealed with Conservator and Corrugated Radiator; Off Load Tap Changer 5 Pos, Outdoor, IEC 60076 Winding : AL-AL Include : - HV-LV Cabel Box - Terminal Control Box - L |
1 |
|
PT. BORNEO MAJU JAYA |
821 |
MINING |
TAMBANG BATU BARA - ADARO |
2025 |
Trafo Oil Immersed type 2500kVA; 20KV/400V; Dyn5; 50Hz; Outdoor; ONAN; 3 Phase; Off Load Tap Changer 5 tap; HV-LV Cable Box; DMCR; Hermetically Sealed; AL-AL; IEC 60076 |
1 |
|
PT. PERTAMINA HULU ROKAN |
822 |
OIL & GAS |
CALL-OFF ORDER (COO) TRANSFORMER (PAKET 1) |
2025 |
TRANSFORMER,3PH,150kVA,13200V- 480V/960V,PAD MOUNTED,5 TAPS,60HZ,DYN1,IEEE, IMPEDANCE:4%, HV BILL:110KV,LV BILL:45KV,NO OF TAP:5 (2x5% ABOVE & 2x5% BELOW), NO LOAD LOSSES:450 W, TOTAL LOSSES:2900 W, BUSHING POSITION HV:TOP, LV:SIDE,CU-CU |
60 |
|
PT. PERTAMINA HULU ROKAN |
823 |
OIL & GAS |
CALL-OFF ORDER (COO) TRANSFORMER (PAKET 1) |
2025 |
TRANSFORMER,3PH,300/300/300 kVA,13200V/480/960/1100V,PAD MOUNTED,5 TAPS(2X5% ABOVE&2X5% BELOW),60HZ,DYN1,IEEE,IMPEDANCE:4% , HV BILL:110KV,LV BILL:30KV,NO LOAD LOSSES:600 W, TOTAL LOSSES:2900 W, BUSHING POSITION HVTAB:TOP, LVTAB:SIDE,CU-CU |
100 |
|
PT. DW TECHNIC |
824 |
BUILDING COMMERCIAL |
BLUEBIRD POOL MAMPANG |
2025 |
3 Phase; Trafo Oil Immersed type 3000kVA; 20kV/400V; Dyn5; 50 Hz; Indoor; ONAN; OCTC 5 Tap; DMCR Transformer Safety Device; Hermatically Sealed; IEC 60076 Winding : AL-AL Deadbreak straight 70mm Pin CU-CU=3 pcs |
1 |
|
PT. SUNINDO MANDIRI PERKASA |
825 |
INDUSTRY |
STOCK |
2025 |
Trafo Oil Immersed Hermetically Sealed type 630kVA; 20KV - 400V; Dyn5; 50Hz; Indoor; ONAN; 3Phase; 5 tap; Off Load Tap Changer; Trasformer Safety Device DMCR; IEC 60076. Winding : AL - AL Deadbreak Straight Ukuran 70mm= 3 Pcs |
1 |
|
PT. PLN (PERSERO) UP3 PRINGSEWU |
826 |
BUMN |
PENGADAAN TRAFO SPEK KHUSUS |
2025 |
Trafo 3 Phase, 50 kVA, 20 kV - 400 V, 50 Hz, ONAN Yzn5, Hermetically Sealed Totally Oil Filled Off Load Tap Changer 9 Pos (14-14,75-15,5-16,25-17-17,75- 18,5-19,25-20 kV) Outdoor; IEC 60076 (Losses mengacu SPLN D3.002-1:2020) Winding :AL-AL |
1 |
|
PT BANUA ABADI JAYA |
827 |
MINING |
TAMBANG BATU BARA BORNEO INDOBARA (SINARMAS) - CIPTA KRIDATAMA KALSEL |
2025 |
Trafo Natural Ester Type, 3 Phase, 3000kVA, 20kV/400 V,50 Hz, Dyn5, KNAN-INSULATION CLASS B, Hermetically Sealed Totally Oil Filled and Corrugated Radiator, On Load Tap Changer 17 pos (ECOTAP MR, 13-21 KV) Outdoor, IEC 60076 Winding : CU-CU |
1 |
|
PT. PLN NUSA DAYA |
828 |
BUMN |
PEMBANGKIT DIESEL |
2025 |
Transformator; 3 Phase, 1600 kVA, 400 V - 20 kV, 50 Hz, YNd5, ONAN, Al-Al, Off- Load Tap Changer 5 Pos, Hermetically Sealed Totally Oil Filled, Outdoor, IEC 60076 |
2 |
|
PT. LS ELECTRIC INDONESIA |
829 |
PROJECT PJT YOOWON/YISU |
2025 |
Transformer 1600kVA, 20kV/400V, Step Down, Dyn5, Mineral Oil, ONAN, 3 Phase, 50Hz, 5Tap, Hermetically Sealed, Indoor, IEC 60076 Winding : AL-AL Deadbreak Straight 70mm? Pin : CU-CU =3 Pcs |
1 |
||
PT. CANDIDA MABEL MUTIARA INDONESIA |
830 |
BUMN |
PROJECT KAI |
2025 |
Trafo 4.420kVA; 3 Phase; 50 Hz; 20.000V - 1.200V & 1.200V; Yy0 & Yd 11 |
1 |
|
PT. LS ELECTRIC INDONESIA |
831 |
INDUSTRY |
PROJECT CLOTHING FACTORY/BUANA INSKONSI JAYA, |
2025 |
Transformer 1000kVA, 20kV/400V, Step Down, Mineral Oil , ONAN, 3 Phase, 50Hz, Dyn5, Hermetically Sealed Oil, 5 Tap, OCTC, Indoor, IEC 60076, Winding : CU- CU DeadBreak Straight 50mm? Pin CU- CU= 3 Pcs |
1 |
|
PT. KURNIA TUNGGAL NUGRAHA |
832 |
INDUSTRY |
PROJECT PEMASANGAN BARU PANEL TRAFO PLANT 1 di PT. KTN LOKASI JAMBI |
2025 |
Step Up, 3 Phase, 4500 kVA, 400V - 20kV, 50 Hz, YNd5, ONAN, AL-AL, Outdoor, Hermetically Sealed Totally Oil Filled and Corrugated Radiator, Off Load Tap Changer 5 Pos, IEC 60076. Winding : AL-AL |
1 |
|
PT. SUKSES TANET PERKASA |
833 |
INDUSTRY |
STOCK |
2025 |
Trafo Oil Immersed type 1000kVA; 20KV - 400V; Dyn5; 50Hz; Indoor; ONAN; 3Phase; Off Load Tap Changer 5 Pos; DMCR Transformer Safety Device; Hermetically Sealed; IEC 60076 Winding : AL-AL Deadbreak Straight 95mm?= 3 Pcs |
1 |
|
HASILWAN ENGINEERING SDN BHD |
834 |
EXPORT - MALAYSIA |
PROJECT FELCRAJAYA UPGRADING LOKASI MALAYSIA |
2025 |
Transformer Oil Immersed Step down, 3 Phase, 2500 kVA, 11 kV - 433 V, 50 Hz, Dyn11, ONAN, Hermetically sealed totally oil filled with corrugated radiator, Off load tap changer 5 pos, Outdoor with HV-LV Cable Box, IEC 60076 Winding : CU-CU |
1 |
|
HASILWAN ENGINEERING SDN BHD |
835 |
EXPORT - MALAYSIA |
PROJECT FELCRAJAYA UPGRADING LOKASI MALAYSIA |
2025 |
TRANSFORMER OIL IMMERSED STEP DOWN, 3 PHASE, 2500 KVA, 11KV - 415V, 50HZ, DYN11,CU-CU, ONAN, HERMETICALLY SEALED TOTALLY OIL FILLED WITH CORRUGATED RADIATOR, OFF LOAD TAP CHANGER 5 POS, OUTDOOR WITH HV-LV CABLE BOX, IEC 60076 Winding:CU-CU |
1 |
|
PT. SURYA KARYA MANDIRI |
836 |
COMMERCIAL BUILDING |
PROJECT RS BRAWIJAYA-CENGKARENG LOKASI CENGKARENG |
2025 |
Trafo Oil Immersed Hermetically Sealed type 1250kVa; 20KV/400V; Dyn5; 50Hz; Indoor; ONAN; 3Phase; Off Load Tap Changer 5 tap; Integrated Safety Device DMCR; IEC 60076 Winding:CU-CU Deadbreak Straight 150mm? Pin CU-CU=3 Pcs |
1 |
|
PT. ADIKARA SATRIA TEKNIK |
837 |
INDUSTRY |
PROJECT ASS - SUBSTATION KLAPANUNGGANG LOKASI KLAPANUNGGANG |
2025 |
Trafo Oil Immersed Hermetically Sealed type 1000kVa; 20KV/400V; Dyn5; 50Hz; Indoor; ONAN; 3Phase; Off Load Tap Changer 5 tap; Integrated Safety Device DMCR; IEC 60076 Winding : AL - AL Deadbreak Straight 50mm? Pin CU-CU =3 Pcs |
1 |
|
PT. KAWAN BERSAMA ENERCOM |
838 |
INDUSTRY |
PABRIK PTPTP V RIAU |
2025 |
Transformer Oil Immersed Hermatically Sealed Totally Oil Filled type 2000kVA; 20kV/400V; Dyn5; 50 Hz; Indoor; ONAN; OCTC 7 Taps; DMCR Transformer Safety Device; IEC 60076 Winding : AL-AL Deadbreak Straight 150mm Pin AL-AL= 3 Pcs |
1 |
|
PT. TASNIM GERAK PERSADA |
839 |
POWERPLANT |
PLTU SITE SAGULUNG |
2025 |
3 Phase, 2250kVA, 20kV-400V, 50Hz, Ynyn0, ONAN, Hermetically Sealed Totally Oil Filled and Corrugated Radiator, Off Load Tap Changer 5 Pos, Outdoor, Z=4%, IEC 60076, Winding : CU-CU |
1 |
|
PT. FIKRINDO UTAMA MANDIRI |
840 |
AGRO INDUSTRY |
PT PTP V LOKASI SEI INTAN PEKANBARU |
2025 |
Trafo Oil Immersed Hermetically Sealed type 2000kVa; 20KV/400V; Dyn5; 50Hz; Indoor; ONAN; 3Phase; Off Load Tap Changer 5 tap; Integrated Safety Device DMCR; IEC 60076 Winding : AL - AL Deadbreak Straight 150mm Pin CU-CU =3 Pcs |
1 |
|
PT. CITRA PALU MINERALS |
841 |
MINING |
PROJECT TAMBANG EMAS-PALU SULTENG |
2025 |
Trafo Oil Immersed type 1000kVA;20kV/400V; Dyn-11; 50 Hz; Outdoor; ONAN; OCTC 5 Tap; Impedance 6%; DMCR; HV-LV BOX, Control Box, Hermatically Sealed; IEC 60076 WINDING : CU-CU |
1 |
|
PT. INDEXIM COALINDO |
842 |
MINING |
PROJECT TAMBANG BATUBARA KALTIM KALIORANG |
2025 |
Trafo Oil Immersed type, 3P, 100 kVA, 20kV/0,4kV, 50Hz, Dyn5, ONAN, Hermatically Sealed, DMCR, Marine Painting, OCTC 7 Pos, Outdoor, IEC 60076 Winding: CU-CU |
1 |
|
PT. INDOPOLY SWAKARSA INDUSTRY TBK |
843 |
INDUSTRY |
PROJECT Offline Coating PT INDOPOLY SWAKARSA - PURWAKARTA |
2025 |
Trafo Oil 3 Phase, 1600 kVA, 20kV/400V, 50 Hz, Dyn5, ONAN, Hermetically Sealed with Conservator and Corrugated radiator, Off Load Tap Changer 5 Pos, Indoor with LV Box Acrylic, IEC 60076 |
1 |
|
PT. ADHI KARYA (PERSERO) DEPARTEMEN GEDUNG |
844 |
COMMERCIAL BUILDING |
RUMAH SAKIT ONKOLOGI PALEMBANG |
2025 |
STEP DOWN; Trafo Oil Ester Synthetic Type 2500kVA; w/Thermally Upgrading Paper; Overload Capability 120% Continuous; 20kV/400V; Dyn5; 50Hz; 3 Phase; Indoor with LV Cable Box ACRYLIC; KNAN; OCTC 5 tap; DMCR Transformer Safety Device; lanjutan deskripsi : H |
1 |
|
PT. ANEKA JAYA LANGGENGSENTOSA |
845 |
BUMN |
PLN PLTD DOMPU-LOKASI DOMPU |
2025 |
Trafo Oil Immersed Step up type 3150 kva ; 400V-20kV; Ynd5; 50Hz; Outdoor; ONAN; 3 Phase; 5 Tap; OCTC; Hermatically Sealed; Wfe = 3400 Watt; Wcu = 32500 Watt; IEC 60076; Winding AL-AL |
4 |
|
PT SYNTEK OTOMASI INDONESIA |
846 |
POWERPLANT |
PLTS Pabrik Kaca PT Mulia Industrindo - Cikarang |
2025 |
Trafo Oil Immersed Step Up type 2500kVA; 400V/20kV; Dyn11; 50Hz; Outdoor; ONAN; 3 Phase; 5 tap; OCTC; Hermetically Sealed with Conservator; HV- LV Terminal Box; IEC 60076 Winding : AL- AL |
1 |
|
PT. SUNINDO MANDIRI PERKASA |
847 |
INDUSTRY |
STOCK LOKASI TANGERANG |
2025 |
Trafo Oil Immersed type 400kVA; 20KV - 400-231V; Dyn5; 50Hz; Indoor; ONAN; 3Phase; 5 tap; Off Load Tap Changer 5 Pos; Hermetically Sealed; Transformer Safety Device DMCR; IEC 60076; (Deadbreak Straight 50mm)= 9 Pcs |
3 |
|
PT. SUNINDO MANDIRI PERKASA |
848 |
INDUSTRY |
STOCK LOKASI TANGERANG |
2025 |
Trafo Oil Immersed type 630kVA; 20KV - 400-231V; Dyn5; 50Hz; Indoor; ONAN; 3Phase; 5 tap; Off Load Tap Changer 5 Pos; Hermetically Sealed; Transformer Safety Device DMCR; IEC 60076; (Deadbreak Straight 70mm)= 9 Pcs |
3 |
|
PT. SUKSES TANET PERKASA |
849 |
INDUSTRY |
STOCK |
2025 |
Transformator; 400 kVA, Dyn5, IEC, Indoor, Winding Al-Al |
2 |
|
PT. SUKSES TANET PERKASA |
850 |
INDUSTRY |
STOCK |
2025 |
Transformator; 630 kVA, Dyn5, IEC, Indoor, Winding Al-Al |
2 |
|
PT. SUKSES TANET PERKASA |
851 |
INDUSTRY |
STOCK |
2025 |
Transformator; 800 kVA, Dyn5, Indoor, Winding Al-Al |
2 |
|
PT. SUKSES TANET PERKASA |
852 |
INDUSTRY |
STOCK |
2025 |
Transformator; 1250 kVA, Dyn5, IEC, Indoor, Winding Al-Al |
2 |
|
PT. SUKSES TANET PERKASA |
853 |
INDUSTRY |
STOCK |
2025 |
Transformator; 1600 kVA, Dyn5, IEC, Indoor, Winding Al-Al |
2 |
|
PT. PLN (Persero) UP3 SAMARINDA |
854 |
BUMN |
PENGADAAN TRAFO TEGANGAN KHUSUS UNTUK PELANGGAN DENGAN KELUHAN TEGANGAN DROP (REPEAT ORDER) |
2025 |
3 Phase, 50 kVA, 20 kV - 400 V, 50 Hz, ONAN, Yzn5, Hermetically Sealed Totally Oil Filled, Off Load Tap Changer 9 Pos (14 14,75-15,5-16,25-17-17,75-18,5-19,25- 20 kV), AL-AL Outdoor, IEC 60076 (Losses mengacu SPLN D3.002-1: 2020) |
1 |
|
PT. PLN (Persero) UP3 SAMARINDA |
855 |
BUMN |
PENGADAAN TRAFO TEGANGAN KHUSUS UNTUK PELANGGAN DENGAN KELUHAN TEGANGAN DROP (REPEAT ORDER) |
2025 |
3 Phase, 100 kVA, 20 kV - 400 V, 50 Hz, ONAN, Yzn5, Hermetically Sealed Totally Oil Filled, Off Load Tap Changer 9 Pos (14 14,75-15,5-16,25-17-17,75-18,5-19,25- 20 kV), AL-AL Outdoor, IEC 60076 (Losses mengacu SPLN D3.002-1: 2020) |
4 |
|
PT. PLN NUSA DAYA |
856 |
PLTS |
PROJECT PEMBANGUNAN DISTRIBUSI 20 kV PT. KURNIA PURNAMA MINERAL |
2025 |
Trafo Oil Immersed type 1250kVA; 20kV/400V; Dyn5; 50Hz; Outdoor; ONAN; 3 Phase; Off Load Tap Changer 7 Pos; Hermetically Sealed; CU-CU IEC 60076 |
1 |
|
PT. PLN (PERSERO) UPK TIMOR |
857 |
BUMN |
PENGADAAN TRANSFORMATOR STEP UP 1600 KVA PLTD WAIKABUBAK PT. PLN (PERSERO) UNIT INDUK WILAYAH NTT UNIT PELAKSANA PEMBANGKITAN TIMOR |
2025 |
Trafo 1600kVA YNd5 400V/20kV 50 Hz - ONAN Outdoor IEC 60076 Winding : CU- CU |
1 |
|
PT. SUNINDO MANDIRI PERKASA |
858 |
INDUSTRY |
PROJECT STOCK LOKASI TANGERANG |
2025 |
Trafo Oil Immersed type 400kVA; 20KV - 400-231V; Dyn5; 50Hz; Indoor; ONAN; 3Phase; 5 tap; Off Load Tap Changer 5 Pos; Hermetically Sealed; Transformer Safety Device DMCR; IEC 60076; (Deadbreak Straight 50mm)= 9 Pcs |
3 |
|
PT. SUNINDO MANDIRI PERKASA |
859 |
INDUSTRY |
PROJECT STOCK LOKASI TANGERANG |
2025 |
Trafo Oil Immersed type 630kVA; 20KV - 400-231V; Dyn5; 50Hz; Indoor; ONAN; 3Phase; 5 tap; Off Load Tap Changer 5 Pos; Hermetically Sealed; Transformer Safety Device DMCR; IEC 60076; (Deadbreak Straight 70mm)= 9 Pcs |
3 |
|
PT. SUKSES TANET PERKASA |
860 |
INDUSTRY |
STOCK UNTUK PT. SUKSES TANET |
2025 |
Transformator; 400 kVA, Dyn5, IEC, Indoor, Winding Al-Al |
2 |
|
PT. SUKSES TANET PERKASA |
861 |
INDUSTRY |
STOCK UNTUK PT. SUKSES TANET |
2025 |
Transformator; 630 kVA, Dyn5, IEC, Indoor, Winding Al-Al |
2 |
|
PT. SUKSES TANET PERKASA |
862 |
INDUSTRY |
STOCK UNTUK PT. SUKSES TANET |
2025 |
Transformator; 800 kVA, Dyn5, Indoor, Winding Al-Al |
2 |
|
PT. SUKSES TANET PERKASA |
863 |
INDUSTRY |
STOCK UNTUK PT. SUKSES TANET |
2025 |
Transformator; 1250 kVA, Dyn5, IEC, Indoor, Winding Al-Al |
2 |
|
PT. SUKSES TANET PERKASA |
864 |
INDUSTRY |
STOCK UNTUK PT. SUKSES TANET |
2025 |
Transformator; 1600 kVA, Dyn5, IEC, Indoor, Winding Al-Al |
2 |
|
PT. PLN (Persero) UP3 SAMARINDA |
865 |
BUMN |
PENGADAAN TRAFO TEGANGAN KHUSUS UNTUK PELANGGAN DENGAN KELUHAN TEGANGAN DROP LOKASI DI ULP MELAK PT. PLN (PERSERO) UP3 SAMARINDA |
2025 |
3 Phase, 50 kVA, 20 kV - 400 V, 50 Hz, ONAN, Yzn5, Hermetically Sealed Totally Oil Filled, Off Load Tap Changer 9 Pos (14 14,75-15,5-16,25-17-17,75-18,5-19,25- 20 kV), AL-AL Outdoor, IEC 60076 (Losses mengacu SPLN D3.002-1: 2020) |
1 |
|
PT. PLN (Persero) UP3 SAMARINDA |
866 |
BUMN |
PENGADAAN TRAFO TEGANGAN KHUSUS UNTUK PELANGGAN DENGAN KELUHAN TEGANGAN DROP LOKASI DI ULP MELAK PT. PLN (PERSERO) UP3 SAMARINDA |
2025 |
3 Phase, 100 kVA, 20 kV - 400 V, 50 Hz, ONAN, Yzn5, Hermetically Sealed Totally Oil Filled, Off Load Tap Changer 9 Pos (14 14,75-15,5-16,25-17-17,75-18,5-19,25- 20 kV), AL-AL Outdoor, IEC 60076 (Losses mengacu SPLN D3.002-1: 2020) |
4 |
|
PT. PLN NUSA DAYA |
867 |
BUMN |
PROJECT PEMBANGUNAN DISTRIBUSI 20 kV PT. KURNIA PURNAMA MINERAL |
2025 |
Trafo Oil Immersed type 1250kVA; 20kV/400V; Dyn5; 50Hz; Outdoor; ONAN; 3 Phase; Off Load Tap Changer 7 Pos; Hermetically Sealed; CU-CU IEC 60076 |
1 |
|
PT. PLN (PERSERO) UPK TIMOR |
868 |
BUMN |
SPK NO : 007.SPK/DAN.01.01/F20050000/2025, TGL 7 MEI 2025, DIREKSI PEKERJAAN ASMAN OPERASI DAN PEMELIHARAAN PEMBANGKIT, TURUN SO AWAL 29 APRIL 2025 KARNA BELOM ADA SPK REVISI KE TGL 2 MEI 2025, |
2025 |
TRANSFORMATOR STEP UP 1600 KVA High Voltage/Low Voltage : Step Up (0,4/20 kV) High Voltage/Low Voltage : Step Up (0,4/20 kV) Hermetically Sealed Totally Oil Filled ONAN YNd5 3 Phase Tap Changer 5 Pos 50 Hz Winding :(Cu- Cu) Protection : I |
1 |
|
PT. NEOTAMA NISIDABA DAGUN |
869 |
INDUSTRY |
PROJECT STOCK |
2025 |
Trafo Oil Immersed type 1000 kVA; 20KV 400-231V; Dyn5; 50Hz; Indoor; ONAN; 3Phase; 5 tap; Off Load Tap Changer 5 Pos; Hermetically Sealed; Transformer Safety Device DMCR; IEC 60076; Winding : AL - AL (Deadbreak Straight 35mm pin CU)=3Pcs |
1 |
|
PT. LS ELECTRIC INDONESIA |
870 |
EXPORT - PHILIPPINES |
PROJECT CEBU CLI LPU LOKASI PHILIPPINES |
2025 |
Padmounted Radial-Feed Type Transformer, 3 Phase, 1000 kVA, 13.8 kV - 400 V, 60 Hz, CU-CU, Dyn11, KNAN- FR3, Hermetically sealed with N2 Cushion & Panel Radiator, Off Load Tap Changer 5 Pos, Outdoor with Cable Box, Z=5.75 %, IEEE C57.12 |
3 |
|
PT SHIMIZU |
871 |
COMMERCIAL BUILDING |
PROJECT RUMAH BUDAYA INDONESIA KAYA (RUBIK) LOKASI JAKARTA |
2025 |
Trafo Dry Non Resin enclosure type 200kVA; 400V/400V; Dyn11; 50Hz; Indoor; AN; 3Phase; CU-CU; IEC 60076 |
1 |
|
PT. BORNEO MAJU JAYA |
872 |
MINING |
PROJECT ADARO-KALIMANTAN |
2025 |
Trafo Oil Immersed type 250kVA; 20KV/400V; Dyn5; 50Hz; Outdoor; ONAN; 3 Phase; Of Load Tap Changer 7 tap; Hermetically Sealed; IEC 60076 WINDING : AL-AL |
1 |
|
PT. SUMBERDAYA SEWATAMA |
873 |
POWERPLANT |
PLTD TUAL |
2025 |
Trafo Oil Immersed Step Up type 2000kVA; 400V/20kV; Ynd11; 50Hz; Outdoor; ONAN; 3 Phase; Off Load Tap Changer 5 Pos; DMCR Transformer Safety Device; Hermetically Sealed IEC 60076 Winding : CU-CU |
10 |
|
CV. RAJAWALIMAS ENERGI PERKASA |
874 |
OIL & GAS |
PROJECT EMP ENERGI RIAU-MERBAU 1 & 2 |
2025 |
Step Up; 3 Phase; 3000kva; 0.48- 2.4kv;60 Hz; Dyn5; ONAN; Hermatically Sealed with conservator and corrugated radiator; Off Load Tap Changer 5 Pos; Outdoor with HV-LV Cable Box; IEC 60076; CU-CU |
1 |
|
CV. RAJAWALIMAS ENERGI PERKASA |
875 |
OIL & GAS |
PROJECT EMP ENERGI RIAU-MERBAU 1 & 2 |
2025 |
Step Down; 3 phase; 1000kva;2.4kv- 460V;60Hz; Dyn5; ONAN; Hermatically Sealed conservator and corrugated radiator; Off Load Tap Changer 5 Pos; Outdoor with HV-LV Cable box; IEC 60076 ; CU-CU |
1 |
|
PT. MULTITAMA KARYATRONINDO |
876 |
INDUSTRY |
PROJECT PT. ABADI PLASTIK LOKASI BEKASI |
2025 |
Trafo Oil Immersed type 400kVA; 20KV - 400v; Dyn5; 50Hz; Indoor; ONAN; 3Phase; 5 tap; Off Load Tap Changer 5 Pos; Hermetically Sealed; Transformer Safety Device DMCR; IEC 60076; (Deadbreak Straight 50mm)= 3PCS |
1 |
|
PT. PLN (PERSERO)UP3 BANTEN SELATAN |
877 |
BUMN |
PENGADAAN TRAFO TAP KHUSUS |
2025 |
Transformator; 3 Phase, 250 kVA, 20 kV - 400 V, 50 Hz, Dyn5, ONAN, Al-Al, Off- Load Tap Changer 7 Pos, Hermetically Sealed Totally Oil Filled, Outdoor, SPLN D3.002-1: 2020 |
2 |
|
PT. BACH MULTI GlOBAL |
878 |
POWERPLANT |
PLTD BALI |
2025 |
Trafo Oil Immersed Hermetically Sealed type 2500kVa; 20kV/400V; Dyn5; 50Hz; Outdoor; ONAN; 3 Phase; Off LoadTap Changer 5 Pos; Transformer Safety Device DMCR; AL-AL; IEC 60076. |
17 |
|
PT. BINA TEKNIK CIPTAMANDIRI |
879 |
INDUSTRY |
PROJECT CIKARANG SMS LOKASI CIKARANG |
2025 |
Trafo Oil Immersed type 315 kVA; 20KV - 400v; Dyn5; 50Hz; Indoor; ONAN; 3Phase; 5 tap; Off Load Tap Changer 5 Pos; Hermetically Sealed; Transformer Safety Device DMCR; IEC 60076;Winding: AL-AL (Deadbreak Straight 50mm CU)=3 Pcs |
1 |
|
PT. RIZKY HAZURA JAYA |
880 |
MINING |
PROJECT BGA-LOKASI KALIMANTAN |
2025 |
Step Down,3Phase,1000kVA,20kV-400V, 50Hz,Dyn5,ONAN,Hermetically Sealed Totally Oil Filled with Corrugated Radiator, On Load Tap Changer 9 Pos ex. MR - Germany (17kV-21kV, 500 V/step),Indoor,IEC 60076,Winding:AL- AL(Deadbreak Straight 50mm=3 |
1 |
|
PT. RIZKY HAZURA JAYA |
881 |
MINING |
PROJECT BGA-LOKASI KALIMANTAN |
2025 |
Trafo Oil Immersed Hermetically Sealed type 50kVa; 20KV/400V; Dyn5; 50Hz; Outdoor; ONAN; 3Phase; Off Load Tap Changer 5 tap; DMCR; IEC 60076, Winding : AL - AL |
1 |
|
PT. RIZKY HAZURA JAYA |
882 |
MINING |
PROJECT BGA-LOKASI KALIMANTAN |
2025 |
Trafo Oil Immersed Hermetically Sealed type 100kVa; 20KV/400V; Dyn5; 50Hz; Outdoor; ONAN; 3Phase; Off Load Tap Changer 5 tap; DMCR; IEC 60076, Winding : AL - AL |
1 |
|
PT. RIZKY HAZURA JAYA |
883 |
MINING |
PROJECT BGA-LOKASI KALIMANTAN |
2025 |
Trafo Oil Immersed Hermetically Sealed type 160kVa; 20KV/400V; Dyn5; 50Hz; Outdoor; ONAN; 3Phase; Off Load Tap Changer 5 tap; DMCR; IEC 60076, Winding : AL - AL |
1 |
|
PT. RIZKY HAZURA JAYA |
884 |
MINING |
PROJECT BGA-LOKASI KALIMANTAN |
2025 |
Trafo Oil Immersed Hermetically Sealed type 250kVa; 20KV/400V; Dyn5; 50Hz; Outdoor; ONAN; 3Phase; Off Load Tap Changer 5 tap; DMCR; IEC 60076, Winding : AL - AL |
3 |
|
PT. BACH MULTI GlOBAL |
885 |
POWER PLANT |
PROJECT PLTD BALI-LOKASI BALI |
2025 |
Trafo Oil Immersed Hermetically Sealed type 2500 kVa; 20KV/400V; Dyn5; 50Hz; Outdoor; ONAN; 3Phase; Off Load Tap Changer 5 tap; DMCR; IEC 60076, Winding : AL - AL |
3 |
|
PT. BACH MULTI GlOBAL |
886 |
POWER PLANT |
PROJECT PLTD BALI-LOKASI BALI |
2025 |
Trafo Oil Immersed Hermetically Sealed type 1250kVa; 20KV/400V; Dyn5; 50Hz; Outdoor; ONAN; 3Phase; Off Load Tap Changer 5 tap; DMCR; IEC 60076, Winding : AL - AL |
1 |
|
PT. SURYA PERDANA ELEKTRIKA |
887 |
COMMERCIAL BUILDING |
PROJECT BIOFARMA CISARUA LOKASI BANDUNG BARAT |
2025 |
Trafo Oil Ester Synthetic type 3500kVA; with Thermally Upgraded Paper; 20kV/400V; Dyn5; 3P; 50 Hz; Indoor; KNAN; OCTC 5 Tap; e-DMCR (SKEMA 2); Midel 7131; Hermatically Sealed; IEC 60076 WINDING : CU-CU Deadbreak straight 120mm pin CU=6 Pcs |
2 |
|
PT. PLN NUSA DAYA |
888 |
POWER PLANT |
PEMBANGKIT DIESEL |
2025 |
Transformator; 3 Phase, 1600 kVA, 400 V - 20 kV, 50 Hz, YNd5, ONAN, Al-Al, Off- Load Tap Changer 5 Pos, Hermetically Sealed Totally Oil Filled, Outdoor, IEC 60076 |
2 |
|
PT. BORNEO MAJU JAYA |
889 |
MINING |
PROJECT TGT LOKASI KALIMANTAN |
2025 |
Trafo 3 Phase, 400 kVA, 20kV/400 V, 50 Hz, Dyn5, ONAN, Hermetically Sealed Totally Oil Filled and Corrugated Radiator, DMCR, Off Load Tap Changer 5 Pos, Outdoor, SPLN D3.002-1. 2007 Winding : AL-AL |
1 |
|
WUHUAN ENGINEERING |
890 |
BUMN |
PROJECT PUSRI IIIB (DRY TRNSFORMER) |
2025 |
Dry Type Transformer, 200 kVA, 480/400- 230V, 50Hz, Z = 4%, Dyn11, Copper Winding, AN, insulation class H, top entry, Min. IP2X, Indoor installation c/w enclosure (Sheet steel with suitable ventilating openings), foot mounted, short circuit |
1 |
|
WUHUAN ENGINEERING |
891 |
BUMN |
PROJECT PUSRI IIIB (DRY TRNSFORMER) |
2025 |
Dry Type Transformer, 40 kVA, 480/400- 230V, 50Hz, Z = 4%, Dyn11, Copper Winding, AN, insulation class H, top entry, Min. IP2X, Indoor installation c/w enclosure (Sheet steel with suitable ventilating openings), foot mounted, short circuit d |
2 |
|
WUHUAN ENGINEERING |
892 |
BUMN |
PROJECT PUSRI IIIB (DRY TRNSFORMER) |
2025 |
Dry Type Transformer for RWI Substation (93200-TR-01) , 20 kVA, 480/400-230V, 50Hz, Z = 4%, Dyn11, Copper Winding, AN, insulation class H, top entry, Min. IP2X, Indoor installation c/w enclosure (Sheet steel with suitable ventilating openin |
1 |
|
WUHUAN ENGINEERING |
893 |
BUMN |
PROJECT PUSRI IIIB (DRY TRNSFORMER) |
2025 |
Dry Type Transformer for RWI Substation (93200-TR-01) , 30 kVA, 480/400-230V, 50Hz, Z = 4%, Dyn11, Copper Winding, AN, insulation class H, top entry, Min. IP2X, Indoor installation c/w enclosure (Sheet steel with suitable ventilating openin |
1 |
|
PT. SUKSES TANET PERKASA |
894 |
INDUSTRY |
PROJECT STOCK LOKASI |
2025 |
Trafo Oil Immersed type 1000kVA; 20KV - 400V; Dyn5; 50Hz; Indoor; ONAN; 3Phase; Off Load Tap Changer 5 Pos; DMCR Transformer Safety Device; Hermetically Sealed; IEC 60076. Winding : AL - AL |
1 |
|
PT. SUKSES TANET PERKASA |
895 |
INDUSTRY |
PROJECT STOCK LOKASI |
2025 |
Trafo Oil Immersed type 1250kVA; 20KV - 400V; Dyn5; 50Hz; Indoor; ONAN; 3Phase; Off Load Tap Changer 5 Pos; DMCR Transformer Safety Device; Hermetically Sealed; IEC 60076. Winding : CU - CU |
1 |
|
PT. MUTIARA AGRO SEJAHTERA |
896 |
INDUSTRY |
PABRIK SAWIT BANGKA BELITUNG |
2025 |
Trafo Oil Immersed type 800kVA; 20KV - 400V; Dyn5; 50Hz; Indoor; ONAN; 3Phase; Off Load Tap Changer 5 Pos; DMCR Transformer Safety Device; Hermetically Sealed; AL-AL; IEC 60076 deadbreak straight 120 mm? pin Cu=3 Pcs |
1 |
|
PT. PETRA NUSA KENCANA |
897 |
COMMERCIAL BUILDING |
PROJECT ANANTI CANGGU BALI-LOKASI BALI |
2025 |
Trafo Oil Immersed type 1000kVA; 20KV - 400V; Dyn5; 50Hz; Indoor; ONAN; 3Phase; Off Load Tap Changer 5 Pos; DMCR Transformer Safety Device; Hermetically Sealed; IEC 60076. Winding : AL - AL |
1 |
|
PT. RIZKY HAZURA JAYA |
898 |
INDUSTRY |
PROJECT BGA (LISTRIK LIMBAH PEMBUANGAN LIMBAH) BGA GROUP BMKM-LOKASI KALIMANTAN |
2025 |
Step Down,3 Phase,1000 kVA,20 kV- 400V,50Hz,Dyn5,ONAN,Hermetically Sealed Totally Oil Filled with Corrugated Radiator,On Load Tap Changer 17Pos(20.500V-16.500V) ex.MR-Germany Indoor,IEC 60076,Winding: AL-AL |
1 |
|
PT. RIZKY HAZURA JAYA |
899 |
INDUSTRY |
PROJECT BGA (LISTRIK LIMBAH PEMBUANGAN LIMBAH) BGA GROUP BMKM-LOKASI KALIMANTAN |
2025 |
Trafo Oil Immersed Hermetically Sealed type 50kVa; 20KV/400V; Dyn5; 50Hz; Outdoor; ONAN; 3Phase; Off Load Tap Changer 5 tap; Oil Level Indicator; IEC 60076, Winding : AL - AL |
1 |
|
PT. RIZKY HAZURA JAYA |
900 |
INDUSTRY |
PROJECT BGA (LISTRIK LIMBAH PEMBUANGAN LIMBAH) BGA GROUP BMKM-LOKASI KALIMANTAN |
2025 |
Trafo Oil Immersed Hermetically Sealed type 100kVa; 20KV/400V; Dyn5; 50Hz; Outdoor; ONAN; 3Phase; Off Load Tap Changer 5 tap; Oil Level Indicator; IEC 60076, Winding : AL - AL |
1 |
|
PT. RIZKY HAZURA JAYA |
901 |
INDUSTRY |
PROJECT BGA (LISTRIK LIMBAH PEMBUANGAN LIMBAH) BGA GROUP BMKM-LOKASI KALIMANTAN |
2025 |
Trafo Oil Immersed Hermetically Sealed type 160kVa; 20KV/400V; Dyn5; 50Hz; Outdoor; ONAN; 3Phase; Off Load Tap Changer 5 tap; Oil Level Indicator; IEC 60076, Winding : AL - AL |
1 |
|
PT. RIZKY HAZURA JAYA |
902 |
INDUSTRY |
PROJECT BGA (LISTRIK LIMBAH PEMBUANGAN LIMBAH) BGA GROUP BMKM-LOKASI KALIMANTAN |
2025 |
Trafo Oil Immersed Hermetically Sealed type 250kVa; 20KV/400V; Dyn5; 50Hz; Outdoor; ONAN; 3Phase; Off Load Tap Changer 5 tap; Oil Level Indicator; IEC 60076, Winding : AL - AL |
3 |
|
PT. THRIVENI INDO MINING |
903 |
MINING |
PROJECT Tambang Batu Bara SATUI COAL - Kalsel-LOKASI KALIMANTAN |
2025 |
Trafo Oil Immersed type 500kVA; 20KV/400V; Dyn5; 50Hz; Outdoor; HV-LV Cabel Box; 7 Tap; ONAN; 3Phase; Hermetically Sealed; IEC 60076 Winding : AL-AL |
1 |
|
PT. MAJU TERANG GEMILANG |
904 |
COMMERCIAL BUILDING |
PROJECT RUMAH SAKIT RKZ PHASE 2 - SURABAYA |
2025 |
Trafo Oil Immersed type 630 kVa; 20KV - 400V; Dyn5; 50Hz; Indoor; ONAN; 3 Phase; Off Load Tap Changer 5 pos; Transformers Safety Device DMCR; Hermetically Sealed; IEC 60076 Winding : CU - CU (Deadbreak Straight 50mm Pin CU=3 Pcs) |
1 |
|
PT. POINT SEJAHTERA LAND |
905 |
COMMERCIAL |
PROJECT PT POINT SEJAHTERA LAND - PIK 2- LOKASI KALIMANTAN |
2025 |
Trafo Oil Immersed type 800kVA; 20KV/400V; Dyn5; 50Hz; Indoor; ONAN; 3 Phase; 5 tap; DMCR; Hermetically Sealed; IEC 60076 Winding : AL-AL (Deadbreak Straight 50mm Pin CU=3 Pcs) |
1 |
|
PT. PLN (PERSERO)UP3 BANTEN SELATAN |
906 |
BUMN |
PENGADAAN TRAFO SPEK KHUSUS |
2025 |
3 Phase, 250 kVA, 16-20kV - 400 V, 50 Hz, Dyn5, AL-AL, ONAN, Tap Changer 5 Pos, Outdoor Winding : AL-AL |
2 |
|
PT. BINA TEKNIK CIPTAMANDIRI |
907 |
INDUSTRY |
PROJECT CIKARANG-SMS LOKASI CIKARANG |
2025 |
Trafo Oil Immersed type 400 kVA; 20KV - 400v; Dyn5; 50Hz; Indoor; ONAN; 3Phase; 5 tap; Off Load Tap Changer 5 Pos; Hermetically Sealed; Transformer Safety Device DMCR; IEC 60076; Winding : AL - AL |
1 |
|
ADHI - PANDU, KSO |
908 |
COMMERCIAL BUILDING |
PROJECT RSUD PONGTIKU TANA TORAJA UTARA |
2025 |
STEP DOWN;Trafo Oil Ester Synthetic Type 1000kVA; w/Thermally Upgrading Paper;Overload Capability 120% Continuous;Oil/Winding Temperature 50/55?C;20kV/400V;Dyn5;50Hz;3Phase;I ndoor;KNAN; OCTC 5 tap;DMCR Transformer Safety Device; Lanjut Des |
1 |
|
PT. MAJU TERANG GEMILANG |
909 |
COMMERCIAL |
RESORT BALI |
2025 |
Transformator WELTRAF Oil Immersed 1600 kVA, 20kV - 400V, Dyn 5, 3 Phase, 50 Hz Proteksi : DMCR Ceramic Bushing OutDoor Winding : AL-AL |
1 |
|
PT. KRAKATAU CHANDRA ENERGI |
910 |
POWERPLANT |
PROJECT PLTD Pelsart Tambang Kencana (PTK) Tambang Emas |
2025 |
3 Phase, 630 kVA, 20 kV - 400 V, 50 Hz, Dyn11, ONAN, Hermetically Sealed with Conservator and Panel Radiator, Off Load Tap Changer 5 Pos, Outdoor with HV/LV Cable Box, HV/LV Cooper Bar; Temp. 50- 55, IEC 60076 |
1 |
|
PT. KRAKATAU CHANDRA ENERGI |
911 |
POWERPLANT |
PROJECT PLTD Pelsart Tambang Kencana (PTK) Tambang Emas |
2025 |
3 Phase, 3150 kVA, 20 kV - 400 V, 50 Hz, Dyn11, ONAN, Hermetically Sealed with Conservator and Panel Radiator, Off Load Tap Changer 5 Pos, Outdoor with HV/LV Cable Box, HV/LV Cooper Bar; Temp. 50-55, IEC 60076 |
8 |
|
PT. PLN NUSA DAYA |
912 |
BUMN |
PROJECT KALIMANTAN TENGAH |
2025 |
3 Phase, 100 kVA, 20 kV - 400 V, 50 Hz, Yzn5, Al-Al, ONAN, Hermetically Sealed Totally Oil Filled and Corrugated Radiator, Off Load Tap Changer 5 Pos, Outdoor,IEC 60076 Winding : AL-AL |
4 |
|
NINDYA - PENTA, KSO |
913 |
COMMERCIAL BUILDING |
PROJECT PEMBANGUNAN GEDUNG KANTOR DPRD PROVINSI PAPUA SELATAN |
2025 |
STEP DOWN;Trafo Oil Ester Synthetic Type 630kVA; w/Thermally Upgrading Paper;Overload Capability 120% Continuous;20kV/400V;Dyn5;50Hz;3 Phase;Indoor;KNAN;OCTC 5 tap;DMCR Transformer Safety Device;Hermetically Sealed;IEC 60076.Winding:CU-CU |
1 |
|
PT. SENTRA KARYA CAHAYA RAYA |
914 |
INDUSTRY |
PROJECT PKS MEDAN |
2025 |
3 Phase, Trafo 1600 kVA, 20 kV - 400 V, 50 Hz, Dyn5, ONAN, Hermetically Sealed Totally Oil Filled and Corrugated Radiator, Off Load Tap Changer 5 Pos, Outdoor with HV/LV Cable Box, IEC 60076 Winding CU-CU, |
1 |
|
PT. CITRA PALU MINERALS |
915 |
MINING |
PROJECT Tambang Emas HEAP BLEACH POWER SUPPLY - SULAWESI |
2025 |
Trafo Oil Immersed type 2000kVA; 20kV/400V; Dyn-11; 50 Hz; Outdoor; ONAN; OCTC 5 Tap; Painting C5; DMCR; HV-LV BOX, Hermatically Sealed; IEC 60076 Winding CU-CU |
1 |
|
PT. SURYA KARYA MANDIRI |
916 |
INDUSTRY |
PROJECT BANJARMASIN LOKASI- BANJARMASIN |
2025 |
Trafo Oil Immersed Hermetically Sealed type 1600kVa; 20KV/400V; Dyn5; 50Hz; Indoor; ONAN; 3Phase; Off Load Tap Changer 5 tap; Integrated Safety Device DMCR; IEC 60076 Winding : AL - AL |
1 |
|
PT. DISTRITAMA PERKASA |
917 |
COMMERCIAL BUILDING |
RUMAH SAKIT PENDIDIKAN |
2025 |
Transformer Oil Ester Synthetic 1000kVA; w/Thermally Upgrading Paper; Insulation Class B; 20kV/400V; Dyn5; 50 Hz; 3 Phase; Indoor; KNAN; Off Load Tap Changer 5 Tap; DMCR Transformer Safety Device;Hermatically Sealed;IEC 60076 Winding: CU-CU |
1 |
|
PT. DINAMIK DELTA MAHAKAM |
918 |
BUMN |
PROJECT PLN NUSA DAYA |
2025 |
Trafo oil immersed type step UP; 1600kVA; 400V-20kV;Ynd5; 50Hz; Outdoor; ONAN; 3 Phase; 5 Tap; OCTC; Hermatically Sealed; IEC 60076 Winding : AL-AL |
3 |
|
PT. DINAMIK DELTA MAHAKAM |
919 |
BUMN |
PROJECT PLN NUSA DAYA |
2025 |
Trafo oil immersed type step down; 1600kVA; 20kv-400V; Dyn5; 50Hz; Outdoor; ONAN; 3 Phase; 5 Tap; OCTC; Hermatically Sealed; IEC 60076 Winding : AL-AL |
1 |
|
PT. SATYA ENERGI SOLUSI |
920 |
MINING |
PROJECT SINARMAS BORNEO INDONESIA |
2025 |
Trafo Oil Immersed type 100kVA, 20kV/400V, 50Hz, Dyn5, ONAN, 3 Phase, Indoor 5 Tap, Hermetically Sealed Oil, CU- CU, IEC 60076 |
1 |
|
PT. SATYA ENERGI SOLUSI |
921 |
MINING |
PROJECT SINARMAS BORNEO INDONESIA |
2025 |
Trafo Oil Immersed type 400kVA, 20kV/400V, 50Hz, Dyn5, ONAN, 3 Phase, Indoor, 5 Tap, Hermetically Sealed Oil, CU- CU, IEC 60076 |
5 |
|
PT. SATYA ENERGI SOLUSI |
922 |
MINING |
PROJECT SINARMAS BORNEO INDONESIA |
2025 |
Trafo Oil Immersed type 500kVA, 20kV/400V, 50Hz, Dyn5, ONAN, 3 Phase, Indoor, 5 Tap, Hermetically Sealed Oil, CU- CU, IEC 60076 |
1 |
|
PT. SATYA ENERGI SOLUSI |
923 |
MINING |
PROJECT SINARMAS BORNEO INDONESIA |
2025 |
Trafo Oil Immersed type 1000kVA, 20kV/400V, 50Hz, Dyn5, ONAN, 3 Phase, Indoor, 5 Tap, Hermetically Sealed Oil, CU- CU, IEC 60076 |
2 |